BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales Court of Appeal (Civil Division) Decisions |
||
You are here: BAILII >> Databases >> England and Wales Court of Appeal (Civil Division) Decisions >> Ferson Contractors Ltd. v Levolux A.T. Ltd. [2003] EWCA Civ 11 (22 January 2003) URL: http://www.bailii.org/ew/cases/EWCA/Civ/2003/11.html Cite as: [2003] 1 All ER (Comm) 385, [2003] EWCA Civ 11, 86 Con LR 98, [2003] BLR 118, [2003] 5 EG 145, (2003) 86 Con LR 98, [2003] TCLR 5 |
[New search] [Printable RTF version] [Help]
COURT OF APPEAL (CIVIL DIVISION)
ON APPEAL FROM HIS HONOUR JUDGE DAVID WILCOX
THE TECHNOLOGY AND CONSTRUCTION COURT.
Strand, London, WC2A 2LL |
||
B e f o r e :
LORD JUSTICE MANTELL
and
LORD JUSTICE LONGMORE
____________________
FERSON CONTRACTORS LIMITED |
Appellant |
|
- and - |
||
LEVOLUX A.T. LIMITED |
Respondent |
____________________
Smith Bernal Wordwave Limited, 190 Fleet Street
London EC4A 2AG
Tel No: 020 7421 4040, Fax No: 020 7831 8838
Official Shorthand Writers to the Court)
Mr S Brannigan (instructed by Davies and Partners) for the Respondent
____________________
AS APPROVED BY THE COURT
CROWN COPYRIGHT ©
Crown Copyright ©
Lord Justice Mantell:
"(1) A party to a construction contract has the right to refer a dispute arising under the contract for adjudication under a procedure complying with this section.
For this purpose "dispute" includes any difference.
(2) The contract shall-
(a) enable a party to give notice at any time of his intention to refer a dispute to adjudication;
(b) provide a timetable with the object of securing the appointment of the adjudicator and referral to the dispute to him within 7 days of such notice;
(c) require the adjudicator to reach a decision within 28 days of referral or such longer period as is agreed by the parties after the dispute has been referred;
(d) allow the adjudicator to extend the period of 28 days by up to 14 days, with the consent of the party by whom the dispute was referred;
(e) impose a duty on the adjudicator to act impartially; and
(f) enable the adjudicator to take the initiative in ascertaining the facts and the law.
(3) The contract shall provide that the decision of the adjudicator is binding until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration) or by agreement.
The parties may agree to accept the decision of the adjudicator as finally determining the dispute.
(4) The contract shall also provide that the adjudicator is not liable for anything done or omitted in the discharge or purported discharge of his functions as adjudicator unless the act or omissions is in bad faith, and that any employee or agent of the adjudicator is similarly protected from liability.
(5) If the contract does not comply with the requirements of subsections (1) to (4), the adjudication provisions of the Scheme for Construction Contracts apply."
"The intention of Parliament in enacting the Act was plain. It was to introduce a speedy mechanism for settling disputes in construction contracts on a provisional interim basis, and requiring the decision of adjudicators to be enforced pending the final determination of disputes by arbitration, litigation or agreement: see s 108(3) of the Act and paragraph 23(2) of Part 1 of the Scheme. The timetable for adjudications is very tight (see s 108 of the Act). Many would say unreasonably tight, and likely to result in injustice. Parliament must be taken to have been aware of this. So far as procedure is concerned, the adjudicator is given a fairly free hand. It is true (but hardly surprising) that he is required to act impartially (s 108(2)(e) of the Act and paragraph 12(a) of Part 1 of the Scheme). He is, however, permitted to take the initiative in ascertaining the facts and the law (s 108(2)(f) of the Act and paragraph 13 of Part 1 of the Scheme). He may, therefore, conduct on entirely inquisitorial process, or he may, as in the present case, invite representations from the parties. It is clear that Parliament intended that the adjudication should be conducted in a manner which those familiar with the grinding detail of the traditional approach to the resolution of construction disputes apparently find difficult to accept. But Parliament has not abolished arbitration and litigation of construction disputes. It has merely introduced an intervening provisional stage in the dispute resolution process. Crucially, it has made it clear that the decisions of adjudicators are binding and are to be complied with until the dispute is finally resolved."
"To enable a quick and interim, but enforceable, award to be made in advance of what is likely to be complex and expensive disputes."
In the same case at para. 26 Chadwick LJ stated;
"The purpose of those provisions is not in doubt. They are to provide a speedy method by which disputes under construction contracts can be resolved on a provisional basis. The adjudicator's decision, although not finally determinative, may give rise to an immediate payment obligation. That obligation can be enforced by the courts. But the adjudicator's determination is capable of being reopened in subsequent proceedings. It may be looked upon as a method of providing a summary procedure for the enforcement of payment provisionally due under a construction contract."
In the latter, Sir Murray Stuart-Smith lent further emphasis to the draconian character of s. 108 at para. 23:
"The whole purpose of s.108 of the Act, which imports into construction contracts the right to refer disputes to adjudication, is that it provides a swift and effective means of resolution of disputes which is binding during the currency of the contract and until final determination by litigation or arbitration, s.108 (3). The provisions of s.109-111 are designed to enable the contractor to obtain payment of interim payments. Any dispute can be quickly resolved by the adjudicator and enforced through the courts. If he is wrong, the matter can be corrected in subsequent litigation or arbitration."
"If he answered the right question in the wrong way his decision will be binding. If he has answered the wrong question, his decision will be a nullity."
"Subject to the proviso to clause 38B.1, the decision of the adjudicator is binding until the dispute is finally determined by arbitration or agreement; and the parties do not agree to accept the decision of the adjudicator as finally determining the dispute."
Clause 38B.1 allowed for a reference to arbitration with the following proviso:
"Provided always, that where any dispute, difference or question has been referred to an adjudicator under Clause 38A and the adjudicator has issued his decision thereon, a Party shall not be entitled to refer such dispute, difference or question to arbitration, and the adjudicator's decision thereon shall become unchallengeable, unless that Party serves the above notice within 42 days of receipt of notification of the adjudicators decision; and, for the avoidance of doubt, this proviso shall apply whether or not the adjudicator has notified his decision within the time limit specified in Clause 38A.5."
The "notice" referred to is that by which either party may refer the matter to an arbitrator.
"The Contractor and the Sub-contractor shall comply forthwith with any decision of the adjudicator; and shall submit to summary judgment/decree and enforcement in respect of all such decisions."
"If it did, then (subject to a further argument about pay-when-paid clauses) the withholding was lawful and the Claimant's case fails. If it did not comply, the Respondent was not entitled to withhold the payment and the Claimant's case succeeds."
The adjudicator held that the notice of withholding payment did not comply with the statutory requirements in that it did not specify the ground for withholding. Accordingly he found for Levolux.
"If the Contractor shall determine the Sub-Contract for any reason mentioned in Clause 29.6,"(including wrongful suspension of work) "the following provisions shall apply:-
(1) All sums of money that they may then be due or accruing due from the Contractor to the Sub-Contractor will cease to be due or to accrue due;"
"If, therefore, by the time an Adjudicator makes a decision requiring payment by a party the contract has been lawfully terminated by that party (or that party has real prospects of success in supporting that termination) or some other event has occurred which under the contract entitles the party not to pay, then the amount required to be paid by the decision does not have to be paid".
The Appeal.
"The necessary implication of the award which was a competent award within the Adjudicator's jurisdiction and arose out of the terms of the reference is that the Claimant was entitled to suspend the works and that the purported determination based on wrongful suspension has no contractual effect."
Mr Collings argues that all that can be read into the adjudicator's decision is that a certain sum was due and owing as at 22nd February 2002. The adjudicator was not required to, and accordingly did not, decide whether or not there had been a valid determination of the contract. It follows that the point was available for argument before the judge without in any way resiling from the binding nature of the adjudicator's decision.
"If the contractor shall determine the Sub-Contract for any reason mentioned in clause 29.6 the following provisions shall apply:
1. All sums of money that may then be due or accruing due from the Contractor to the Sub-Contractor shall cease to be due or accrue due;"
Clause 29.9 provides:
"Until after completion of the Sub-Contract Works and the making good of defects as referred to in clause 14.3 the contractor shall not be bound by any provisions of the sub-contract to make any further payment to the sub-contractor."
"(1) The decision of an adjudicator that money must be paid gives rise to a second contractual obligation on the paying party to comply with that decision within the stipulated period. This obligation will usually preclude the paying party from making withholdings, deductions, set-offs or cross-claims against that sum. (2) For a withholding to be made against an adjudicator's decision, an effective notice to withhold payment must usually have been given prior to the adjudication notice being given, or possibly the decision being given, and which was ruled upon and made part of the subject matter of that decision. (3) However, where other contractual terms clearly have the effect of superseding, or provide for an entitlement to avoid or deduct from, a payment directed to be paid by an adjudicator's decision, those terms will prevail. (4) Equally where a paying party is given an entitlement to deduct from or cross-claim against the sum directed to be paid as a result of the same, or another, adjudication decision, the first decision will not be enforced or, alternatively, judgment will be stayed."
It is, of course, upon the third conclusion that Mr Collings relies in support of his submissions and that which gives rise to the obvious question; was Judge Thornton right in reaching that particular conclusion?
"Other rights under the contract which were not the subject of the decision remain available to the relevant party. If, therefore, by the time an adjudicator makes a decision requiring payment by a party to the contract, the contract has been lawfully terminated by that party (or that party has real prospects of success in supporting that termination) or some other event has occurred which under the contract entitles a party not to pay, then the amount required to be paid by the decision does not have to be paid."
Judge Thornton also had recourse to a decision of this court in Parsons Plastics (Research and Development) Ltd v. Purac Ltd (2002) BLR 334. In that case the court was not concerned with a construction contract as such, but with a contract which nevertheless contained what may be termed the s.108 provisions. It follows, that the point of construction was much the same as here. At para. 15 Pill LJ stated:
"It is open to the respondents (employment paying party) to set-off against the adjudicator's decision any other claim they have against the appellants (contractor receiving party) which had not been determined by the adjudicator. The adjudicator's decision cannot be re-litigated in other proceedings but, on the wording of this sub-contract, can be made the subject of set-off and counter-claim."
However, having referred to that passage, Judge Thornton went on to say that the adjudication was a purely contractual adjudication without the statutory backing of the HGCRA and that "it is only clear words that can trump the payment decision".
Lord Justice Longmore:
"38A.9 Notwithstanding clause 38B [the arbitration clause], the Contractor and the Sub-Contractor shall comply forthwith with any decision of the adjudicator; and shall submit to summary judgment/decree and enforcement in respect of all such decisions."
The parties have thus agreed not merely that the adjudication is to be binding but also that they will comply with the adjudication notwithstanding the arbitration clause. For good measure, they have agreed they will submit to applications for summary judgment. If Ferson had a genuine point, there would then be a dispute which would have to be referred to arbitration but the parties have expressly agreed that course is not open to them once an adjudication has occurred. The clause thus prevents the party who has lost the adjudication from applying for a stay and, for good measure, requires him to submit to applications for summary judgment. The point of that must be not that the court should hear argument, at the stage of the application for summary judgment, about matters which (apart from the adjudication provision) should be referred to arbitration, but rather that summary judgment should be given without further ado. That is what HH Judge Wilcox correctly did.
Lord Justice Ward: