![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | |
England and Wales Court of Appeal (Civil Division) Decisions |
||
You are here: BAILII >> Databases >> England and Wales Court of Appeal (Civil Division) Decisions >> Gwynedd Council v British Telecommunications Plc [2004] EWCA Civ 942 (16 July 2004) URL: http://www.bailii.org/ew/cases/EWCA/Civ/2004/942.html Cite as: [2004] 4 All ER 975, [2004] EWCA Civ 942 |
[New search] [Printable RTF version] [Help]
COURT OF APPEAL (CIVIL DIVISION)
ON APPEAL FROM MANCHESTER COUNTY COURT
HIS HONOUR JUDGE HOLMAN
SE300196
Strand, London, WC2A 2LL |
||
B e f o r e :
LORD JUSTICE JACOB
and
LORD JUSTICE WALL
____________________
GWYNEDD COUNCIL |
Appellant |
|
- and - |
||
BRITISH TELECOMMUNICATIONS PLC |
Respondent |
____________________
Ian Mayes QC and Niran de Silva (instructed by British Telecommunications Group) for the Respondent
Hearing date: 16 June 2004
____________________
Crown Copyright ©
Lord Justice Wall:
Introduction
"… except in a case where, as described in Appendix C1.2 of the Code of Practice, by agreement between the authority (here Gwynedd) and the undertaker (here BT), the procedures set out in Appendix C to the code can be foreshortened and the Draft Scheme and Budget Estimate stage omitted, an authority is required to meet its share of an undertaker's reasonable costs of providing a Detailed Estimate under Appendix C4 of the Code."
The practical question raised by the case
The Act
(a) to identify any measures needing to be taken in relation to the apparatus in consequence of, or in order to facilitate, the execution of the authority's works,
(b) to settle a specification of the necessary measures and determine by whom they are to be taken, and
(c) to co-ordinate the taking of those measures and the execution of the authority's works,
so as to secure the efficient implementation of the necessary work and the avoidance of unnecessary delay.
Where an undertaker's apparatus in a street is affected by major highway works, major bridge works or major transport works, the allowable costs of the measures needing to be taken in relation to the apparatus in consequence of the works, or in order to facilitate their execution, shall be born by the highway, bridge or transport authority concerned and the undertaker in such manner as may be prescribed.
The Regulations
For the purposes of these Regulations "allowable costs" means all the reasonable costs of the measures needed to be taken for the purpose specified in section 84(1) of the Act except costs incurred –
(a) in preparing the initial set of plans and estimates in relation to those measures (but not in preparing any further plans and estimates which the authority may require);
(b) (does not apply here).
The Code of Practice
The "allowable costs" are the costs of the works described in Appendix C section 4C and do not include financing charges, nor the costs of either party in respect of that part of the work described in Appendix C section C2, C3 and C4 which consists of preliminary planning and liaison.
While the procedures set out in this Appendix represent those, which would normally be followed for larger-scale works, they may, depending on local circumstances and agreement, be foreshortened by the omission of certain of the following stages.
(i) preliminary inquiries
(ii) draft scheme and budget estimates
(iii) detailed scheme and detailed estimates
(iv) formal notices and advance orders
(v) selection of contractor and issue of main orders
(vi) construction
(vii) financial monitoring and payment.
At this stage the highway authority would seek from the undertakers details of their apparatus within a specific section of the scheme, which is being considered for improvement without making any commitment to the scheme. Undertakers should provide such information as they have available from records and draw attention to any likely special problems, which could arise from the authority's works…. Information should be provided normally within 10 days.
Budget estimates provided by undertakers should include all costs likely to arise from the necessary measures in consequence of the authority's works as far as can be assessed at the draft design state, including administration and supervision charges, and specifying a base date. These estimates should be provided normally within 20 working days.
Where undertakers are not aware of the general position in line and depth of their apparatus, they should at this stage take any necessary steps to determine this information.
This stage may be followed by discussions between the authority and undertakers, either separately or jointly, to consider any modifications to the scheme which may assist in facilitating the programming of the works and / or reducing the cost of diversionary works.
Following joint discussions, the authority should submit to each undertaker details of the final design with working drawings and an outline programme. The undertaker should respond, normally within 25 working days, by providing details of their requirements (if there is a requirement to provide more than one detailed estimate, the utility may charge for such additional estimates) as follows –
(i) Description of the necessary measures, clearly stating the reason for diversion or protection and giving details of the existing apparatus affected, such as lengths and sizes of pipes / cables / ducts, depths of cover and ages …..
(ii) A detailed specification of the works required as appropriate –
(11 examples are given)
(iii) A detailed estimate with itemised costs also to include –
(four particular items are identified)
(iv) Provisional programmes and timescales for works, including as appropriate
(five particular examples are given)
The Manual
Budget estimates from the undertakers should include all costs likely to arise from the necessary measures in consequence of the (authority's) works as far as can be reasonably assessed at preliminary design stage, including administration and supervision charges and specifying a base date.
4.1.4. The (Highway Authority) will accept the cost of the preparation of initial C4 estimates. The exception to this rule is smaller–scale works when the preliminary or draft scheme stages could be omitted and the process could commence with the submission of a detailed scheme to the Undertakers. In cases when no C3 budget estimate has been prepared the Undertaker should prepare the C4 estimates free of charge. Payment for C4 estimates should only be made when the estimate has been received in full and all clarifications have been resolved with the Undertaker
The Code of Practice states that Undertakers are entitled to charge for additional C4 estimates requested after the initial C4 estimate. When amendments are required, the (Highway Authority) will only pay for the costs of the necessary revisions to the initial estimate. The (Highway Authority's) agent shall verify when amendments are made, that costs are for 'revisions' only.
The facts as found by the judge
If you are not confident or aware of the general position in line and depth of your apparatus you would take any necessary steps to determine this information at your own expense…..
Detailed discussions should follow in order to consider any modifications to the scheme which may assist in facilitating the programming of the works and / or reducing the costs of diversionary works. Following the consultation period, the Authority will submit details of the final design scheme with working drawings and an outline programme.
BT will accept your letter as an order to produce the detailed specification and will invoice you on completion of this work whether or not your scheme progresses to the execution stage.
The arguments addressed to the judge
(1) the word "initial" in Regulation 2(2)(a) may embrace more than just a first set of plans / estimates, but it is far removed from "final" and Appendix C4 is concerned with the final detailed scheme and detailed estimates.
(2) The wording in brackets near the start of Appendix C4 "(if there is a requirement to provide more than one detailed estimate the utility may charge for such additional estimates)" does not means that BT may not charge for the first detailed C4 estimate.
(3) The plain meaning of paragraph 9.2 of the Code of Practice is that such costs incurred at Appendix C4 stage as represent preliminary planning and liaison are not recoverable. That stage is at an end once joint discussions have taken place and the final design is submitted. The dividing line comes after the words "following joint discussion" at the start of C4.
(4) The definitions in the Oxford English Dictionary (OED) are of assistance. The primary definition of "initial" is: "of or pertaining to a beginning; existing at, or constituting, the beginning of some action or process; existing at the outset; primary; sometimes = elementary, rudimentary." Of "preliminary" it is "a subordinate step, measure, statement, etc., that precedes another to which it is introductory or preparatory. Chiefly in pl. = preparatory measures or arrangements".
(5) The words "set of plans" are directly analogous with the word "scheme". The initial set is the draft scheme.
(6) There is no valid distinction to be drawn between the cost of implementing measures to safeguard apparatus and the cost of providing plans and estimates. Section 85 is simply the money aspect. Section 84 deals with the taking of the measures. This is in accordance with the title given to each section.
(1) the Act draws a distinction between (1) the identification and planning of measures which may need to be taken to protect apparatus – addressed in section 84; and (2) the measures themselves and who is to meet the costs of those measures – addressed in section 85 and the Regulations.
(2) The Regulations follow this distinction between, on the one hand, identifying settling and co-ordinating the measures i.e. planning and, on the other hand, the measures themselves. The allowable costs are the costs of the works themselves, not the preparation.
(3) C4 is the final part not of the process but of the planning aspect. By reference to the word "initial" the specification produced at C4 is BT's plan for dealing with their apparatus and is provided at the beginning of the works. By reference to the word "preliminary" the C4 plans are preparatory to the works that are to be carried out.
(4) The words in Regulation 2(2) "but not in preparing any further plans and estimates which the authority may require" (the reasonable cost of which is allowable) are remarkably similar to the words in brackets near the start of C4. Those words in C4 would be unnecessary if the first C4 estimate was chargeable, since it would inevitably follow, if the first was chargeable, that subsequent ones would be as well.
(5) This interpretation is consistent with the objectives set out in section 84. It would be contrary to the purpose, spirit and intent of the legislation if an authority got all the information it needed at C4 stage (for which it had to pay) and then, in the light of that information, had to change its final plans (so that it would have to pay again).
The judge's decision
40. I do not find my task particularly easy. As is not uncommon, the Regulations and Code of Practice are not a model of clarity. However, applying what I believe to be a common sense, everyday approach to the word "initial", if one looks at the various stages in the process, C3 is the initial stage. C4 may not be the end of the process, but it cannot properly be categorised as initial. I agree also with Mr Mayes QC (for BT) that "set of plans" can properly be equated with "scheme". The draft scheme is the initial step. It is difficult to think of a final scheme being an initial stage, when it has been preceded by a draft scheme, and where it is also plainly contemplated that there will be discussions after the draft, which may result in changes to the scheme. Since the word in the Regulations is "initial", I do not strictly need to address the word "preliminary" but, even if I do, C4 can hardly be described as introductory or preparatory. The process has gone beyond that by this stage. Some assistance can be derived from the wording of the headings to the sections in the Code of Practice. C3 concerns the draft scheme – plainly initial. C4 concerns the final scheme, and consistently with that a detailed specification and estimate is required in contrast with C3, which call only for preliminary details of effects and budget estimates. The word preliminary appears in C3 but not C4.
41. Section 9.2 of the Code of Practice does not undermine this view. It excludes from allowable costs only those parts of the C4, which consist of preliminary planning and liaison. Joint discussions prior to the issuing of the final scheme are an obvious example and self-evidently this preliminary planning and liaison element will be greater, if stages C2 and C3 have been omitted. It may be a small point, but if the detailed estimate is part of the preliminary process, but the specification is part of the works, it seems a little odd that the requirements for the detailed estimate appear as (iii) in C4 after the requirements for the specification which appear as (ii).
42. In the pre-litigation correspondence (Gwynedd) repeatedly based its position on the wording in brackets near the start of C4 – "if there is a requirement for more than one detailed estimate the utility may charge for such additional estimates". This is point 4 in my summary of Mr. Sauvain's submissions (for Gwynedd). Whilst it is certainly a possible interpretation that it means you cannot charge for the first C4 estimate that view is, as I see it, inconsistent with the proper interpretation of regulation 2(2). Where there is inconsistency, the regulation prevails.
The judge accordingly found for BT.
The grounds of appeal
The argument for the appellant in this court
The argument for BT
(if there is a requirement to provide more than one detailed estimate, the utility may charge for such additional estimates)…"
was not, on BT's construction, redundant.
Discussion and analysis
Riders
…. there is an obvious temptation to (the undertaker) to do as little as possible at C2 and C3, so as to load as much as possible of its costs into C4. This may well be contrary to the spirit and intent of the code of practice. Self-interest must not prevail, as the guiding principles in the code of practice make clear.
….. as is stated in the Executive Overview to the Code of Practice, there must be close co-operation and co-ordination and "the need for this underpins all the provisions of the code". I have the clear impression that relationships between the parties have been allowed to deteriorate over a period of time (which period began well before this dispute) to such an extent that the objectives of the code of practice have been undermined. Where the fault lies, I do not know. Each side accuses the other of being intransigent. I rather suspect that, as Mr. Sauvain observed, there has been fault on both sides. They need to start working together again in order "to obtain the optimum solution".
.
Lord Justice Jacob:
Lord Justice Auld: