BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales Court of Appeal (Civil Division) Decisions |
||
You are here: BAILII >> Databases >> England and Wales Court of Appeal (Civil Division) Decisions >> Howard & Anor v Wigan Council & Anor [2015] EWCA Civ 854 (01 July 2015) URL: http://www.bailii.org/ew/cases/EWCA/Civ/2015/854.html Cite as: [2015] EWCA Civ 854 |
[New search] [Printable RTF version] [Help]
ON APPEAL FROM THE HIGH COURT OF JUSTICE
QUEEN'S BENCH DIVISION
Strand London, WC2A 2LL |
||
B e f o r e :
____________________
HOWARD & ANR | Applicant | |
v | ||
WIGAN COUNCIL & ANR | Respondent |
____________________
WordWave International Limited
A Merrill Communications Company
165 Fleet Street London EC4A 2DY
Tel No: 020 7404 1400 Fax No: 020 7404 1424
(Official Shorthand Writers to the Court)
Mr S White QC (instructed by Gateley LLP) appeared on behalf of the Respondent
____________________
Crown Copyright ©
1. LORD JUSTICE BURNETT: I am concerned with three applications for permission to appeal against orders made by Supperstone J in the Planning Court which have been refused on paper by Sullivan LJ.
"8. I accepted the evidence of Mr Tomkins, Mr Pennington and Mr Walsh, which was supported by the contemporaneous documentation. I was entirely satisfied that the work that Mr Tomkins said was done was indeed carried out. He produced his original notebook in his own handwriting which included notes of the work that he did on 11 and 12 February in relation to the individual trial pits which he wrote at the time. He also referred to the trial pit log which includes his notes as written up by him afterwards which also shows the work that was done. The evidence in issue focused in the main on trial pits 4, 16, 17 and 18.
9. In my view, the contemporaneous notes Mr Tomkins made and the trial pit logs fully supported his oral evidence. In an ex tempore judgment I concluded that his new ground of challenge based on the allegation that GRM and their contractors had been dishonest and deliberately produced false soil sampling data was not arguable and accordingly permission to apply for judicial review was refused.
10. After delivering that judgment I heard submission on the sole remaining issue in claim 2 and claim 1. Mr Dale-Harris accepted that in the event that claim 2 was dismissed claim 1 was academic and should also be dismissed. At the conclusion of the hearing on 12 December I reserved judgment on those issues, namely ground 1 in claim 2 and claim 1."
"In essence, the contention of the Appellant is that 4 trial pits... were not carried out on the 11th and 12th of February 2014 and that, in essence, the results of those trial pits were fabricated by the IP's consultants.
14. It is worth just reflecting on that for a moment. Even putting the Appellant's case at its highest, the IP's consultants fabricated only 4 of 24 trial pits and those 4 trial pits all showed levels of contamination which exceeded the accepted levels. Therefore, the IP's consultants fabricated results which showed unacceptable levels of contamination requiring remediation. It is a complete mystery why professional consultants would invent results that would ruin the individuals concerned, ruin the consultancy who specialise in producing such results, only seek to invent 4 such results in a field of 24 and finally produce results which required an onerous remediation requirement."
"16. The evidence on which the claimants now rely is contained in the fifth witness statement of Ms Bennett, the fourth witness statement of Ms Foster of Richard Buxton, who has had the handling of this case throughout these proceedings, and the exhibits to those two statements, all of which were before Walker J. There is now a further witness statement from Ms Bennett dated 25 February 2015. That is here sixth witness statement. From Morris Homes there is the third witness statement of Mr Tomkins dated 19 February 2015, a witness statement from Mr Hodgkinson of GRM of the same date and a witness statement from Mr Grady of Morris Homes.
17. It is common ground that no order having been drawn up dismissing the two claims I have no power to revisit my decision to refuse permission on ground 2 in claim 2. In the matter of L and B Children [2013] UKSC 8, the Supreme Court confirmed that a judge is entitled to reverse his decision at any time before his order is drawn up and perfected. In L and B, having reviewed the authorities, Lady Hale (with whom the other members of the court agreed) stated at paragraph 27 that, when a judge is exercising his jurisdiction to revisit his own decision at any time up until his resulting order is perfected, she...
20. "... it is highly likely that there is a slab or concrete foundation within the fenced off area, and that if further trenches were to be dug in the location of TP4, TP16 and TP17 this would reveal concrete in the locations of TP4, TP16 and TP17 alleged by Mr Tomkins to have been dug at a depth of 3.3m, 3m and 3.1m respectively. These holes are supposed (according to the trial pit logs) also to be 3m x 0.6m. We believe that the concrete would have impeded digging much below the surface at TP4, TP16 and TP17."
21. Mr Tomkins responds to these allegations as follows. First in relation to TP4, he states:
22. "I explained in my earlier witness statements and in oral evidence to the court the process for the excavation of trial pits. I referred to the trial pit log, which is the record of the results of the trial pit exercise prepared by myself. The trial pit log for TP4 records the first presence of broken concrete at a depth of 1.3m and continued to be present up to 1.0m. As the concrete slab was broken it was weak enough to allow the excavator bucket to break through the concrete enabling excavation to continue at a lower depth. I refer also to my handwritten notes from my personal logbook which indicate the presence of a concrete slab and that the slab was broken through."
23. In relation to TP16 and TP17, Mr Tomkins says that these trial pits are located within the area that has historically been fenced off when the site was originally remediated. He says:
24. "The agreed remediation strategy for the area of TP16 and TP17 requires a 750mm capping layer to be constructed to protect end users from the contaminants found during the trial pits and sampling. This is to comprise 600mm of topsoil/subsoil and 150mm thick anti-dig layer (stone). The anti-dig layer (crushed sandstone) has already been laid across the area, sealing in the identified contaminants from the workforce. In due course a 450mm (approx.) of subsoil (sand) will be added and a layer of topsoil of 150mm (approx.) will be laid. Clean topsoil has already been stockpiled in this area on a plastic sheet for later use. There is no evidence of a concrete slab in the location of TP16 and TP17. The trial pit logs do not record the presence of concrete in the same way that the trial pit log did do for TP4. There is no evidence the concrete slab in TP4 extends to TP16 and TP17, rather, the trial pit logs prove otherwise.
25. Mr Hodgkinson, who is employed by GRM as a geotechnical engineer, says in his statement that he was on site on 17 February 2015 conducting a regular weekly visit to review progress. Whilst preparing to supervise the removal of the concrete slab and observe the ground below it, he looked at the location of TP4. Soil had been cleared from the concrete slab which was encountered in TP4. A hole in the concrete slab is clearly visible where the bucket of the excavator which excavated the trial pit had broken through the slab. He also confirmed that on that day he observed the area of TP16 and TP17 and he describes in his statement what he saw there. Mr Hodgkinson says there is no evidence on site to indicate that the concrete slab observed in the trial pit logs for TP4 and on his visit to site on 17 February extends to the positions of TP16 and TP17...
27. Mr White submits that there is no new evidence which relates to what happened on 11 and 12 February 2014, which are the material dates. The claimants' contention, that what they had seen in the last 10 days, namely a concrete base in the area of TP4, TP16 and TP17, proves the trial pits could not have been dug on those dates in February 2010, is, he submits, without foundation. The evidence of Mr Tomkins and Mr Hodgkinson, who have the requisite expertise, shows, Mr White submits, that the claimants are misinterpreting what they have seen. They acknowledged at the hearing in December last year they have no experience or knowledge of the works that have been undertaken. There is, Mr White submits, no professional evidence of any kind before the court that supports the claimants' contention that the trial pit samples in issue were not taken in manner described by Mr Tomkins on 11 and 12 February 2014. Mr White further submits that it is far too late no for this interim relief to be granted. When the claimants were served with the interested party's witness statements and contemporaneous documentation in November 2014 they should have then requested inspection or instructed an expert if they had wished to challenge the evidence. That was the time, pre-trial, for the further investigation that the claimants now apply for to have taken place.
28. Any new evidence has to be considered in the context of the evidence as a whole. In forming a view as to the credibility of the new evidence, I have had regard to the oral evidence I heard from Mr Tomkins and the other witnesses who gave evidence on behalf of Morris Homes in December 2014 and to the contemporaneous documentation, in particular the documents relating to TPs 4, 16 and 17 that were considered on that occasion. It is now said by the claimants that TP4 is not where Mr Tomkins said it was. At no stage during that hearing was the evidence of Mr Tomkins as to the position of TP4 challenged. I considered Mr Tomkins, having heard him give evidence and been cross-examined on the notes of the work that he did on 11 and 12 February 2014 in relation to the individual trial pits which he said he wrote at the time, to be a truthful witness. I have given careful consideration to the two witness statements of Ms Bennett, to which I have referred, and to the photographs exhibited to them and to the contents of the statements of Mr Tomkins and Mr Hodgkinson and also in particular to the original notes made by Mr Tomkins and the trial logs in relation to TPs 4, 16 and 17.
29. In my judgment, there is no real prospect that what the claimants contend to be new evidence would lead me to reach a different conclusion on claim 2, ground 2. In the circumstances, I consider that to admit the evidence at this stage would be wrong and contrary to the interests of justice. In reaching this conclusion I have also had regard to the factor referred to by Lady Hale in L and B, namely whether a party has acted upon the judge's decision to his detriment. I am informed that since my judgment in December 2014, Morris Home embarked on the works that they are presently carrying out, which are no partially completed. Mr Grady, employed by Morris Homes as the Northern Technical Director, who is responsible for the management of technical activities at the site, sets out in his witness statement of 25 February 2015 the implications on the restriction in carrying out works within TP16 and TP17 in terms of cost and the remediation strategy agreed with the Council and Environment Agency."