BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Commercial Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Commercial Court) Decisions >> Pentonville Shipping Ltd. v Transfield Shipping Inc (MV Johnny K) [2006] EWHC 134 (Comm) (10 February 2006) URL: http://www.bailii.org/ew/cases/EWHC/Comm/2006/134.html Cite as: [2006] EWHC 134 (Comm) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
COMMERCIAL COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
PENTONVILLE SHIPPING LTD |
Claimants (Disponent Owners) |
|
- and - |
||
TRANSFIELD SHIPPING INC m.v. "JOHNNY K" |
Respondents (charterers) |
____________________
Mr Julian Kenny (instructed by Messrs Swinnerton Moore) for the Respondents
Hearing dates: 25 November 2005
____________________
Crown Copyright ©
Mr Justice Tomlinson:
"In any event, we do not think that the Charterers can be held liable for the instruction to vacate the berth given by the port authorities and that at the end of the day was the real reason for the vessel sailing. Even had they wanted to (and from a commercial perspective, it would have been unrealistic for them to want to block the use of one of the only two berths that could take ships of this size) the Charterers could not have prevailed against the wishes of the port authorities."
"23. Had she remained at the berth, loading could have been completed within a matter of hours (and would have been completed, since we are satisfied that despite what the Owners say, there was no shortage of cargo) and with completion of loading, demurrage would have ceased. In the absence of any breach by the Charterers of the safe berth warranty, the cost of the subsequent delay would prima facie have fallen to the Owners, as would any liability to the owners of the berth in continuing to occupy it after loading had been completed.
28. We accept of course that the charter provides for the Owners to specify that up to 10% more or less cargo above the basic intake be loaded and that the Master asked for 172,700 mt, that is 1.59% above the basic figure. Clearly as we have indicated above, the reason why the nominated cargo was not loaded was because had it been, the vessel would have been unable to sail for approximately 3 weeks and it was the Owners' responsibility to ensure that the quantity of cargo they sought could be loaded. In any event, as we have already pointed out, it was the port authorities that ordered the vessel to sail.
29. We do not believe that the charterers can be blamed in this instance for the failure to load the quantity originally sought by the Master.
31. We do not believe that there was a failure by the charterers, or those for whom they are responsible, to make a full cargo available for loading, either when the vessel became an arrived ship or subsequently. That it was not loaded within the allowed laytime (indeed loading did not commence until after demurrage began) does not give to any remedy other than the payment of demurrage.
32. We were referred at some length to the well known case of Aktieselskabet Reidar v. Arcos Ltd [1926] 25 L1.1. Rep. 513, a decision of the Court of Appeal and the principles enunciated therein.
33. Suffice to say, we are satisfied that that case remains good law. Whether to bring themselves within those principles, the Owners must demonstrate a separate breach of some other contractual provision other than the obligation to load the intended cargo within the agreed laytime or simply that the Owners must show that they have suffered two distinct heads of damage, the second being of a separate type, which was not covered by the demurrage rate, is in this case academic. However it is viewed, the loss said to have been suffered by the Owners, other than the delay which is covered by the demurrage provision, did not arise from any fault on the part of the charterers. At the end of the day, the order to sail was given by the port authorities and the Charterers cannot be blamed for that decision."
"54. Conventional wisdom has it that having elected to carry a specific figure, the Master is obliged to load that quantity. However in the present case, the Master certainly did not refuse to load more cargo. He was prevented from doing so by the orders of the port authorities to sail. To that extent, the Owners are right when they say they committed no breach of charter and were not responsible for the full nominated quantity of being loaded. In the same way, we have held that the Charterers are not liable to the Owners for the consequence of the vessel being ordered to sail, we similarly hold that the Owners are not liable to the Charterers for the failure to load the nominated quantity. It follows that any loss resulting from the port authorities' instructions, must lie where it falls. Consequently the Charterers' counterclaim fails."