BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Amec Capital Projects Ltd v Whitefriars City Estate Ltd [2003] EWHC 2443 (TCC) (19 September 2003) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2003/2443.html Cite as: [2003] EWHC 2443 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand London WCA 2LL |
||
B e f o r e :
____________________
AMEC CAPITAL PROJECTS LIMITED |
CLAIMANT |
|
-v- |
||
WHITEFRIARS CITY ESTATE LIMITED |
DEFENDANT |
____________________
190 Fleet Street, London EC4A 2AG
Telephone 020 7404 1400 Fax No: 020 7831 8838
(Official Shorthand Writers to the Court)
Mr David Thomas QC (instructed by Kingsley Napley) appeared on behalf of the Defendant.
____________________
Crown Copyright ©
"President or a Vice President of the Royal Institution of Chartered Surveyors."
These provisions, and especially the former, formed a key part of the defendant's case as to the interpretation to be given to the letter of intent.
"Pending execution of a formal contract based upon an amended standard form of Building Contract with Contractor's Design 1998 Edition issued by the Joint Contract Tribunal with amendment 1 1999, TC/94/WCD and any further amendments as specified, drafts of which were included in the tender documents, and any other amendments as may be agreed between ourselves, we hereby issue this letter of intent of instruction in relation to your firm price tender dated 12th April 2000 for the execution and completion of the above works, including the development and completion of design and within a construction period to be agreed prior to contract."
It then said:
"The scope of the works is outlined in the Employers Requirements dated March 2000 at a total estimated cost of £4.55 million, or such other sum as may be agreed."
Then, importantly:
"Until the execution of a contract in the form referred to above, neither you nor we shall be bound or committed in any way beyond the scope of the works instructed by this letter, and the terms of payment and all other terms and conditions, including the arbitration agreement in Article 5, shall be as contained in the form of contract referred to above."
The reference to Article 5 is wrong. The arbitration agreement is in Article 6A. Article 5 is about adjudication. The letter says what the work is to be done first, namely the provision of pre-contract services, and then the procurement of the second stage of tender. It also said:
"If you want to place orders for work or materials, you must get prior written authorisation."
"The payment for any works will be administered in accordance with the terms of the proposed contract as set out above. However, there will be no payment for the pre-construction services prior to January 2001. Until the formal building contract is completed, our maximum liability to you will be £3.25 million. The value of the works carried out by you will, in due course, form part of the contract sum under the above mentioned contract if our negotiations are successful."
No formal contract was in fact completed, as envisaged by the letter of intent. The letter of intent was countersigned by the claimant as its acceptance. It therefore constituted a conditional or "if" contract. In my judgment the letter envisaged that substantial works could be carried out under its terms even though further authorisation was needed from the defendant once the initial or preparatory stages were complete.
"Where the entry in the appendix stating that clause 39B applies has not been deleted, then, subject to Article 5, if any dispute or difference as to any matter or thing of whatsoever nature arising out of this contract or in connection herewith, except in connection with the enforcement of any decision of an Adjudicator appointed to determine the dispute or difference arising thereunder, shall arise between the Parties either during the progress or after the completion or abandonment of the Works or after the determination of the employment of the Contractor,….. it shall be referred to arbitration under clause 39B and the JCT 1988 edition of the Construction Industry Model Arbitration Rules (CIMAR)."
"If it had been intended to qualify the word 'decision' in some way, then this could have been done. Why not give the word its plain and ordinary meaning? I confess that I can think of no good reason for not so doing, and none was suggested to me in argument. If his decision on the issue referred to him is wrong, whether because he erred on the facts or the law, or because in reaching his decision he made a procedural error which invalidates the decision, it is still a decision on the issue. Different considerations may well apply if he purports to decide a dispute which was not referred to him at all."
Dyson J was there foreshadowing the familiar question: is this a decision which the adjudicator was authorised to make? It was not, then it would not have been a decision in the sense discussed in Macob. If it was then, even if the decision was itself wrong (see Bouygues) or flawed it would nevertheless be a decision for the purposes of those three documents. Challenging a decision because it is said to have been unauthorised is not only a typical and legitimate way in which enforcement of a decision is resisted, but is probably the principal means available. So, here, the defendant's case is that this is not a decision which Mr Biscoe was authorised to make as he was not the right adjudicator.