BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> All In One Building & Refurbishments Ltd v Makers UK Ltd [2005] EWHC 2943 (TCC) (19 December 2005) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2005/2943.html Cite as: [2006] CILL 2321, [2005] EWHC 2943 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
St Dunstan's House 133-137 Fetter Lane London, EC4A 1HD |
||
B e f o r e :
____________________
ALL IN ONE BUILDING & REFURBISHMENTS LIMITED |
Claimant |
|
- and - |
||
MAKERS UK LIMITED |
Defendant |
____________________
Kim Franklin (instructed by Over Taylor Biggs) for the Defendant
____________________
Crown Copyright ©
His Honour Judge Wilcox
"… as such it is not in our financial interests to allow All In One to void their contractual obligation …"
"… as per Makers Ltd verbal instruction all of our labour has been asked to leave site at 9.30 am …"
"We formally put on record that on Thursday 28 July 2005, Makers UK Ltd engaged third parties to undertake our works and on Friday 29 July 2005 Makers instructed our site management and operatives to vacate the site at 09.30 hours. This instruction has been recorded on Confirmation of Verbal Instruction No.1/204141 and is signed by an authorised agent of our Makers. As a result, All In One Building & Refurbishments Ltd are excluded from the project's premises and therefore no longer have possession of the site.
Your company's action is a repudiatory breach of contract and as such, we are no longer bound by the sub-contract and hereby terminate our employment under the sub-contract.
We shall be forwarding our account shortly, which will include our claim for damages flowing from your breach.
A dispute now exists under the sub-contract."
"The nature of the dispute is non payment by Makers of AIO's Interim Application dated 15 August 2005 in the gross sum of £547,411.05 in respect of which £309,866.90 is outstanding together with VAT.
2. No notices to withhold have been given by Makers with respect to this application.
Further AIO will say that Makers is in repudiatory breach of contract in that on 29 July Makers informed AIO that it was to leave site and thereby deny AIO possession of the site in question.
AIO will ask the adjudicator to:
(1) make a decision as to whether or not Makers acted in repudiatory breach of contract by ordering them to leave site on 29 July 2005;
(2) direct that Makers do pay to AIO the outstanding sum of £309,866.90 or such other sum as the adjudicator shall direct."
"4. The circumstances from which it may emerge that a claim is not admitted are Protean. For example, there may be an express rejection of the claim. There may be discussions between the parties from which objectively it is to be inferred that the claim is not admitted. The respondent may prevaricate, thus giving rise to the inference that he does not admit the claim. The respondent may simply remain silent for a period of time, thus giving rise to the same inference.
5. The period of time for which a respondent may remain silent before a dispute is to be inferred depends heavily upon the facts of the case and the contractual structure. Where the gist of the claim is well known and it is obviously controversial, a very short period of silence may suffice to give rise to this inference. Where the claim is notified to some agent of the respondent who has a legal duty to consider the claim independently and then give a considered response, a longer period of time may be required before it can be inferred that mere silence gives rise to a dispute.
7. If the claim as presented by the claimant is so nebulous and ill-defined that the respondent cannot sensibly respond to it, neither silence by the respondent nor even an express non-admission is likely to give rise to a dispute for the purposes of arbitration or adjudication."
"The substantial inherent risk in issuing a Decision on a £159,912 claim that had neither been properly evidenced nor tested."
"That it was appropriate to request from AIO particularisation and evidence of its damages claim. AIO provided the information on 18 October, as an attachment to an email of that date. By letter dated 20 October, I expressed the preference to allow Makers the opportunity of making a full response to the information provided with email, and I made the request for an extension to the deadline for my Decision. AIO consented to the request. I was then able to allow Makers the time that it said it required to respond to the particulars provided by AIO and I set the service deadline of Monday 24 October 2005."
(Emphasis provided by the adjudicator.)
"It is easy enough to make challenges of breach of natural justice against an adjudicator. The purpose of the scheme of the 1996 Act is now well known. It provides a speedy mechanism for setting disputes in construction contracts on a provisional interim basis, and requiring the decisions of adjudicators to be enforced pending final determination of disputes by arbitration, litigation or agreement. The intention of Parliament to achieve this purpose will be undermined if allegations of breach of natural justice are not examined critically when they are raised by parties who are seeking to avoid complying with adjudicator's decisions. It is only where the Defendants advance a properly arguable objection based on apparent bias that he should be permitted to resist summary enforcement of the adjudicator's award on that ground."
(Dyson LJ in Amec Payments Ltd v White Friars City Estates Ltd [2005] 1 BLR p.1 at paragraph 22.)
"At 11 am this morning I will advise the parties of my decision on the meeting. It is likely to be the case that after that time, I will be unable to embrace in my Decision any further written submissions from the parties – whether in the form of statements or new documents."
"I am now completing my review of all the party's submissions and proceeding towards my decision. If I require any further information from the parties I will ask for it."
"We feel we must deal with it despite the fact that the adjudicator has determined that submissions are closed.
Our clients inform us that Mr Bullen was dismissed by them at the end of his three month probationary period and left their employment four weeks ago. He was paid for four weeks notice but not required to attend work during the course of his notice period. He was also required to return mobile phones and all company equipment Though technically it is the case that Mr Bullen's employment with our client ends this week, to all practical purposes it ended four weeks ago. Our clients have endeavoured to contact him but without any success.
We do not know the motivation or reasons behind Mr Bullen seeking to go behind his affidavit. The circumstances under which it came to be signed are that the company's managing director having received the correspondence from AIO referring to this CVI gave instructions that if Mr Bullen was denying that he was a signatory to it that it was a matter which should be confirmed by affidavit as it was a matter of considerable importance. We do not know at this point in time whether the statement was typed by Mr Bullen himself or by someone on his behalf though our clients believe the likelihood is that he typed it himself. They are however satisfied that he chose the solicitor where he went to swear it and as far as our clients are aware went to these solicitors unaccompanied and then returned the affidavit to his manager …"
"… We have not heard from you as to whether you are accepting that statement as evidence in the adjudication and taking notice of it. If you are then we would make the following submission.
It is suggested by Nelsons that Mr Bullen swore an affidavit under duress with the threat of redundancy. He had only been employed for a few months by our clients on a probationary period. He was given notice of dismissal a few days after swearing the affidavit. Insofar as it was an attempt to stave off a dismissal it was clearly unsuccessful. We are not aware of any attempt by Mr Bullen to retract what he had previously said and where he was prepared to swear on oath.
The affidavit confirms entirely our client's understanding of what occurred. We would suggest that the attempt by either Mr Bullen or by AIO to go behind his sworn evidence should be ignored."
CONCLUSION
i) That in all probability the Claimant company is insolvent.ii) Its present ability to repay is doubtful.
iii) If it is able to return to trading there is no evidence that it will or will not be able to repay the debt should it be called upon to do so.
iv) There is no evidence as to when, if at all, the Claimants might be called upon to repay. No proceedings or arbitration has been embarked upon.
v) The financial status of the company now is not dissimilar to that that presented itself at the outset.
vi) The inference is warranted with one project company such as this, that its impecuniosity derives from non payment by the Defendant.
vii) Were it to have been demonstrated that the company was in insolvent liquidation then it would have been appropriate to refuse summary judgment, see Bouygues (UK) Ltd v Dahl-Jenson (UK) Ltd [2000] BLR p.522 Court of Appeal, in the judgment of Chadwick LJ para 29-36.