BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Zurich Insurance Company v Gearcross Ltd [2007] EWHC 1318 (TCC) (25 May 2007) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2007/1318.html Cite as: [2007] EWHC 1318 (TCC), 112 Con LR 82 |
[New search] [Printable RTF version] [Help]
TECHNOLOGY & CONSTRUCTION
Fetter Lane London, EC4 |
||
B e f o r e :
____________________
ZURICH INSURANCE COMPANY |
Claimant |
|
- and - |
||
GEARCROSS LIMITED |
Defendant |
____________________
6th Floor, 12-14 New Fetter Lane, London EC4A 1AG
Telephone No: 020 7936 6000. Fax No: 020 7427 0093.
Email: [email protected]
MR. W. WEBB (instructed by Messrs. Mischon de Reya) for the Defendant.
____________________
Crown Copyright ©
HIS HONOUR JUDGE PETER COULSON QC:
A. Introduction
"Failure to reimburse Zurich the cost of carrying out the remedial works which is in breach of clause 40 of the Zurich Rules of Registration which states that the cost of carrying out the remedial works is recoverable on demand."
By an application under CPR Part 24 dated 16th April 2007, which followed the service of Gearcross's defence, Zurich sought summary judgment against Gearcross in the full amount of that claim. That is the application which I have heard this afternoon.
B. The Rules and What They Mean
"19. Requirements
Builders and developers shall procure that each new home shall be built to the [written] Requirements [of Zurich]...
21. Contractual Responsibilities
(a) Subject to sub-rule (b) below if a developer enters an agreement with an original buyer of a new home such developer shall warrant that:
(i) he is currently registered as a developer;
(ii) he will fulfil his obligations under the rules;
(iii) the new home would have been built pursuant to the Requirements and in a workman-like fashion such that it is fit for human habitation ...
(vii) he will comply with the Developer's Responsibilities which shall be set out in full in such agreement…
(ix) he will be liable for and will repair any Damage or rectify any Defect which has manifested during the developer's guarantee period including any damage or defect which is the result of his building on adjoining property and any consequential damage to the new home ...
32. Defective Works
Where the company [Zurich] considers that a builder or developer has not performed his obligations under a scheme or the rules, then the company may:
(a) prohibit continuation of work on a new home in relation to which the builder or developer has so failed except for such work as may be specified by the company;
(b) serve the builder or developer with notice in writing specifying work and timescale which the company is of the opinion is required to remedy the position.
34. Failure to Comply with Instructions
If a builder or developer does not carry out any instructions given to him by the company as soon as practicable, the company may instruct another builder to carry them out at the expense of the defaulting builder or developer.
40. Recovery
Sums which a builder or developer is liable to pay either to a buyer or to the company pursuant to a scheme may be recovered from the builder or developer on demand and shall carry interest at the rate of 4% per annum above the base rate of the NatWest Bank plc prevailing at that time."
a) That the work originally performed by Gearcross was defective in accordance with rule 32, because Gearcross had not complied with their obligations under rules 19 and 21;
b) That a notice specifying the remedial work necessary to rectify those defects had been served by Zurich on Gearcross in accordance with rule 32(b);
c) That Gearcross had not carried out such remedial work "as soon as practicable" in accordance with rule 34;
d) That as a result of Gearcross's failure, Zurich had instructed another contractor to carry out the work in the notice in accordance with rule 34;
e) That the sum now claimed by Zurich was in respect of the remedial work which Gearcross refused to carry out and which was therefore carried out by other contractors (rule 40).
C. The Evidence
C.1 General Observations
a) The Gearcross witness statements were light on detail and contained references to very few dates which, in a dispute where the chronology was so important, was unhelpful. Moreover, the exhibits to the statements were plainly just a photocopy of the relevant (unsorted) files, so that they started at the end and worked backwards, and even then were not in any discernible chronology order.
b) Zurich put in no evidence at all until yesterday, when they served a statement from a Mr. Philip Money which ran to 62 paragraphs. Despite its length, the statement does not suggest that Mr. Money had any involvement in the detailed events at issue between the parties. His exhibits, which fill a lever arch file, largely replicated the documentation which had been attached to the particulars of claim and exhibited to the other statements.
C.2 The Relevant Facts
"I write further to our correspondence dated 1st November 2002 where you agreed to look at our project manager's costings for the necessary remedial works.
During our conversation of today, I specifically asked you if you were able to respond with a positive answer within 3 days of receipt of the costings. You stated that you would like a copy of this sent to your surveyor, Mr. D. Webb. He is currently on annual leave and returns the week commencing 18th November 2002. You advised that you were not in a position to accept any costings until Mr. Webb returns.
As you are aware, this claim has been outstanding since June 2002 and we are no further forward in acquiring an actual start date for works to commence. Another 2 weeks have gone by and you have not asked a contractor to submit any estimates as you promised within our conversation before you went on holiday.
In view of the on-going time delays in resolving this claim we have no option but to instruct our contractor to carry out the works. On completion of these works we will be looking for reimbursement of our outlays from you."
"…it seemed to me that the work that was reported to Gearcross Limited initially was much narrower in scope than the amount of work that they have now done. I was allowed into the property initially to inspect a small list of defects within the ground floor and part of the first floor, but was not allowed access to some of the areas I needed to see before being abused and physically pushed out of the building by Miss Faude. We were never allowed back into the property."
"We are well aware of the protocols involved in arranging remedial works and will revert to you once a full costing and a scope of works is made available to us. We are satisfied that our contractor will carry out any works necessary including specialist works, if they are necessary, without him charging whatever 'he feels he should charge'. We have a longstanding relationship with this company and are content to rely on their recommendations, specialist or not. Had the property been constructed adequately in the first place we would not have found ourselves in this situation. We appreciate your clients' intentions and we will continue to communicate to ensure that your client is kept informed and the costs are contained. We too have a vested interest to ensure this happens."
a) Continual difficulties were placed the way of Mr. Webb who was unable to make a proper inspection. He referred to these difficulties in his various letters of 10th February 2003 and 17th February 2003.
b) Mr. Haskins and/or his surveyors identified further alleged defects which they said required to be rectified.
c) Further investigations were apparently carried out which did not involve Gearcross or Mr. Webb in any way.
"…relates to the rectification of items you are responsible for under the developer's guarantee period and would request you forward a cheque in the sum of £36,538.64 to cover our expenditure following the works."
D. Analysis of the CPR Part 24 Application
D1. Was the work defective?
D2. Was the required remedial work the subject of a notice?
D3. Did Gearcross carry out the work as soon as practicable?
D4. As a result of Gearcross's failure, did Zurich instruct another contractor to carry out the work?
D5. Does the sum demanded by Zurich refer to and relate to the work that Gearcross refused to carry out?
a) Some of the work that was carried out by other contractors between early 2003 and May 2005 and paid for by Zurich was the work required by the report of 26th September 2002.
b) The remainder of that work was not in the report of 26th September and was never therefore the subject of Zurich's notices to Gearcross. In respect of that work, it cannot be said that Gearcross did not carry it out as soon as practicable. They never knew that such work was required of them.
a) There is a claim for relocating spot lights. Mr. Webb of counsel demonstrated to my satisfaction that that was not an item that was referred to in the notice of 26th September 2002.
b) There is a claim for work to the roof terrace and balcony, although the defects themselves are not detailed in the invoices. There is nothing about such defects in the report of 26th September or the subsequent notices. There is no mention in the report even of damp in those areas. The reference to the balcony in the report is to a suggestion by Mr Haskins of possible structural problems, on which the surveyor expressly accepts that he could express no opinion.
c) There is a claim for plumbing works, including new WCs and systems. No particulars of the defects or the remedial work are provided. Again, this aspect of the property does not appear to be something that gets any mention at all in the report of 26th September. Although there is a reference to an historical complaint about leaks in the shower, it seems from the report that that had been dealt with by 26th September.
d) Mr. Webb of counsel points out that it appears to be accepted by Zurich that notification of all relevant defects has not been provided. In paragraph 22 of the particulars of claim, Zurich admit that some of the later claims are in respect of defects "which only became apparent once the remedial works were underway". Such remedial works were carried out long after September/November 2002, and there is no pleaded notice in respect of such defects.