BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Felton Construction Ltd v Liverpool City Council [2007] EWHC 3049 (TCC) (21 December 2007) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2007/3049.html Cite as: [2007] EWHC 3049 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
133-137 Fetter Lane London, EC4A 1HD |
||
B e f o r e :
____________________
FELTON CONSTRUCTION LIMITED |
Claimant |
|
- and - |
||
LIVERPOOL CITY COUNCIL |
Defendant |
____________________
Mr Piers Stansfield (instructed by Halliwells) for the Defendant
Hearing dates: 5th 6th 7th November 2007
____________________
Crown Copyright ©
HIS HONOUR JUDGE TOULMIN CMG QC:
i) What are the terms of the contract [relationship] between the parties?ii) What are the terms of the contract under which the Claimant's works should be valued?
iii) Is the Claimant estopped from denying the terms of the contract relied upon by the Defendant in the Amended Defence and if so, on what basis?
iv) Does the contract, as found by the court, include an arbitration clause?
THE LAW
"In deciding whether the parties have reached agreement, the courts normally apply the objective test. Under this test, once the parties have to all outward appearances agreed in the same terms on the same subject matter, then neither can, generally, rely on some unexpressed qualification or reservation to show that he had not in fact agreed to the terms to which he had appeared to agree. Such subjective reservations of one party therefore do not prevent the formation of a contact."
i) Interpretation is the ascertainment of the meaning which the document would convey to a reasonable person having all the background knowledge which would be available to the parties in the situation in which they were at the time of the contract.ii) The background may include anything which would have affected the way in which the language of the document would have been understood by a reasonable man or woman.
iii) The law excludes from the admissible background the previous negotiations of the parties and their declarations of subjective intent.
iv) The meaning of the document is what the parties using those words against the relevant background would reasonably have been understood to mean.
v) Words should be given their "natural and ordinary meaning". However this does not require Judges to attribute to the parties an intention that they plainly could not have had.
To these propositions must be added the following when considering whether the parties have concluded an enforceable contract.
vi) The fact that a clause in a contract may be difficult to interpret does not mean that it is meaningless. The court must do its best to select among contending interpretations the one that best matches the language of the parties as expressed in the language they adopted – see Steyn LJ in "The Star Texas" [1993] 2 Lloyds Rep 445 at page 452.
vii) The Judge is entitled to look behind the apparent or literal meaning of the words of a letter in order to determine the true intent of the parties, see Latham LJ in Harvey Shop Fitters v Adi [2003] EWCA Civ 1757.
viii) Where there are contemporary exchanges and the carrying out of what was agreed in those exchanges, the course of dealing may create on one side a right to performance and on the other a right to be paid on an agreed basis – see Steyn LJ in Trentham Ltd v Archital Luxfer [1993] 1 Lloyds Rep 25 at 29.
ix) In principle it is for the parties to decide whether they wish to be bound and if so by what terms – see Lloyd LJ in Pagnan v Feed Products [1987] 2 Lloyds Rep 601 at 619.
x) Although the more important the term is the less likely it is to have been left by the parties for future decision, there is no legal obstacle to the parties agreeing to be bound now while deferring important matters to be agreed later – see Pagnan at page 619 (see above).
xi) In Trollope v NW Met Hospital Board [1973] 1 WLR 601 at 609 Lord Pearson emphasised that "the court's function is to interpret and apply the contract that the parties made for themselves … an unexpressed term can be implied only if the court finds that the parties must have intended the term to form part of the contract."
xii) In each case the courts must consider whether or not the terms of a contract have been agreed. In British Steel Corporation v Cleveland Bridge [1983] 24 BLR 94 Robert Goff J held that there was no binding executory contract since the claimants were asked to and did proceed with the work pending the preparation and issuing of a form of sub-contract being a sub-contract which was plainly in a state of negotiations not least on the issues of price, delivery dates and the applicable terms and conditions. It was impossible to say what the material terms of the contract would be.
xiii) In commercial contracts the court, whilst applying established legal principles, will strive to uphold a commercial bargain:
a) In Sykes v Fine Fare [1967] 1 Lloyds Rep 53 Lord Denning MR said that in a commercial agreement the further the parties have gone on with their contract, the more ready are the courts to imply any reasonable term so as to give effect to their intentions. "When much has been done the courts will do their best not to destroy the bargain."b) In Sudbrook Trading Estate v Eggleton [1983] 1 AC 444 at 460 the court said that it will even provide a substitute machinery to fill a gap in the contract when it is appropriate to do so.c) In Mamidoil v Okta [2001] Lloyds Rep 76 at 89 Rix LJ said at paragraph 66 of his judgment:"In a commercial contract which when dealing with the future and sometimes the long-term future, of necessity leaves out certain matters to be worked out over time - an arbitration clause assists the court to find certainty by means of the implication of what is reasonable. Which is not to say that the Court will not itself provide the dispute resolution machinery even in the absence of an arbitration clause."d) At paragraph 69:"However, particularly in commercial dealings between parties who are familiar with the trade in question, and particularly where the parties have acted in the belief that they had a binding contract, the courts are willing to imply terms where that is possible that enable the contract to be carried out … For these purposes an express stipulation for a reasonable or fair measure or price will be a sufficient criterion for the courts to act on. But even in the absence of express language the courts are prepared to imply an obligation in terms of what is reasonable."
THE FACTS
"Following your agreement to tender for the above scheme we now have pleasure in enclosing herewith the following:
(i) One copy of the Bills of Quantities.
(ii) One copy of the Form of Tender.
(iii) One set of the Architect's and Structural Engineer's tender drawings as listed in the specification page 1/3 Clause 110.
(iv) One set of the Mechanical and Electrical Technical Specifications plus listed drawings.
(v) Tender Envelope …"
"Having read the Conditions of Contract and Specification and having examined the drawings referred to herein and visited the site do hereby offer to execute and complete the Works described in a workmanlike manner to the reasonable satisfaction of the architect/ca for the FIRM PRICE of £3,191,800."
"Please will you price out the Bill in its entirety including the preliminary section by next Tuesday at the latest?"
"In respect of the Preliminaries please can you price each "fixed" and "time related" item as applicable. The measured sections should not include all-encompassing rates that cover a number of items."
"We enclose herewith as requested our priced Bill of Quantities.
Please note that we have included alternative suppliers/subcontractors in some instances."
"I/We having reading the Conditions of Contract and Specification and having examined the drawings referred to therein and visited the site do hereby offer to execute and complete the Works described in a workmanlike manner to the reasonable satisfaction of the architect/CA for the FIRM PRICE sum of …"
"I/We further undertake and agree when so required to execute a Form of Contract in the form referred to in the said Conditions of Contract …"
"However, as discussed, savings are necessary in order to achieve an agreed contract sum. In the mean time we would very much welcome offers from yourselves where meaningful savings might be found."
"Employers Requirements for Contractor Designed Pre-Cast Floors. Felton is requested to provide a price for carrying out these revised works."
"You will recall a phone conversation we had when we asked you to indicate the minimum requirement of external works you required in order to provide your necessary hardstanding during the contract. Please will you advise on this in order that we can calculate the level of saving achievable."
"We advise that the minimum hardstanding requirement for construction purposes would be a 5 metres wide strip to the perimeter of the building plus the access road, car park and service area."
"We would endeavour to submit a price for the precast units on Monday next."
"We have received a revised ironmongery schedule and would advise after subsequent discussions that we recommend a reduction in the provisional sum of £10,000 for this item."
"Further to your telephone call last Friday we offer a saving of £400 for air filled double glazed units to windows (not doors) in lieu of argon filled."
"B. The contractor must include for all costs associated with all preliminary items and make due allowance in the programme for all works indicated by the following PC and Provisional Sums."
and
"C. The CA reserves the right to deduct the whole or any part of any PC or Provisional Sum indicated in this Bill and the contractor shall take the instructions of the CA regarding the estimates of specialists etc."
"Following the finalisation of the measurement of the omission for the external works, the saving against the pin boards was not necessary and consequently they remained in the contract sum."
"Item 20 was an adjustment of the contingency sum in order than an overall saving of £4,930 was achieved following the final measurement for the reduction to the external works for inclusion in the Addendum Bill the saving against contingency was not as high as had been anticipated in the "list of saving"."
"I refer to your tender reasonably submitted for the above scheme and write to confirm that the City Council has decided to accept your tender and conditions which we have agreed.
Whilst the City Council will embody the agreed terms and conditions in a formal contract document as soon as possible, it is the full intention of the City Council (as evidenced herein) that once the duplicate of this letter has been signed by your company a binding legal contract shall arise between the parties enforceable by each."
"All those within the JCT Standard Form of Building Contract Local Authority with Quantities 1999 Edition incorporating Amending 1, 2 and 3 with Amendment 4 all as adapted by the JCT Contractor's Designed Portion Supplement 1998 edition revised May 2000 and as amended by the Project Specific Amendments and in the conditions referred to in the "Tender Letter" dated 26 February 2003 as prepared by Markhams."
"We enclose a copy of the signed letter of intent for your attention and look forward to receiving the contract documents in due course …"
"I/We acknowledge receipt of a letter of which this is a duplicate and agree that, upon my/our signature hereof, a contractual relationship exists between Felton Construction Ltd on whose behalf I/we sign and Liverpool City Council."
"All items marked PROVISIONAL in the Bills of Quantities are to be priced out at the same rates as other similar items of measured work and would be subject to re-measurement on completion …"
"The contract is the JCT Standard Form of Building Contract Local Authorities with Quantities 1988 Edition incorporating Amendments 1, 2 and 3 with Amendment 4 all as adapted by the JCT Contractor's Design Portion Supplement 1988 Edition revised 2000."
"Two blank copies of the Bill of Addendum will be issued to Feltons week commencing 6 May 2003."
"A completed Bill of Addendum will be issued by Markhams to include the agreed changes to that tendered."
"All revised as Bill of Addendum – omitting hard/soft landscaping, fencing, gates, safety barriers, reducing parking and access road to kerbs and hardcore only; adding 5m wide hardcore working zone."
The reference to the 5m wide hardcore working zone is a clear reference to Felton's earlier requirement.
"John,
Find attached the Addendum Bill for the above scheme. There are a couple of items which require further information from you in order that the descriptions reflect the changes made. [Reference to two savings amounting to £10,236)]
Once the information requested has been provided I will be in a position to finalise the addendum and be in a position to complete the contract documents and the two "blank bills"."
"2.0 Carry out works as described on drawing 1495013 – timber fencing, security fencing, hard landscaping details 1-3 omitted as per Bill of Addendum – Pallisade gate, games court fencing and vehicle crossing detail retained."
This relates to a number of items of external works which had been omitted in the contract price but which were to be reinstated. These items had already been priced in the Bill of Quantities before they were omitted.
"Re: Stockton Wood
Delay to the Contract
In accordance with Clause 25.2.1 of the contract we write formally to advise you that the progress of the works is likely to be delayed. The cause and material circumstances of the delay is due to compliance with Architect's instructions 31 and 32 relating to external works requirements …
This is a relevant event under Clause 25.4.5.1 of the contract …"
"The delay notice has been issued as we are contractually obliged to do so under the terms and conditions of the contract should such an event become apparent."
"Please find enclosed the Bill of Quantities for the site works. Please will you check the rates and confirm that they are in accordance with your previous submissions." (ie, previous Bills)
"Further to you(r) issue of priced BOQ (Bill of Quantities) in respect of the above, we would confirm that the rates are in accordance with our tender submission."
"… This discussion will be held in light of the stated position of the client on this issue not to pursue damages provided costs are not raised by Felton Construction in relation to any extension of time and the project is delivered satisfactorily by 20 August 2004."
"External Works start date and the increase in the period to completion for the revised works from 21.60 Working Weeks to 24 Working Weeks".
"At present we have not received any information in support of or notification of delay to progress for the ten week period beyond 11 June 2004 up to your reported programme completion date of 20 August 2004. In the absence of this information, we will be issuing a certificate of non-completion at the end of the revised contract completion date …"
"We have reviewed the contract documents for the above project and we are unable to sign the contract, as the drawings do not reflect the post tender revisions. For instance you have included the drawing for external works. These were omitted as a cost saving exercise.
I would recommend that the document be reviewed with your design team to ensure the relevant information is applicable."
"TH (Mr Herd of Felton) reported some anomalies in the tender package is to prevent FC from sign documents. HLP to contact Melanie Gill to establish the extent of anomaly."
"HLP and FC (Felton) to progress extent of anomalies in tender documentation. HLP to contact City Solicitors."
"Latest slip in programme due to late installation date for gas meter given as 18 August – additional of CCTV system and over painting to teaching walls."
i) Felton contended that the three week extension of time which they had been granted did not reflect their true legal entitlement (1.01).ii) There had been a number of recent variations not properly accounted for (1.02).
iii) Felton had written a letter dated 3 August 2004 (not in the bundle) relating to landscape work and other matters which were discussed extensively.
iv) Felton "categorically deny in accordance with Peter Coleman's advice" that a construction programme had ever been issued for the contract but only Tender programmes. Mr Coleman was the solicitor from Waterfords.
v) Felton offered (for discussion purposes only) that they should be entitled to a full extension of time to 6 September 2004 and be paid the full sum to which they were entitled on the final account.
"In accordance with Clause 25.2.1 of the contract we write formally to advise you that the progress of the works has been delayed due to exceptionally adverse weather conditions and that this is a relevant event under Clause 25.4.2 of the contract."
"We believe that it is pertinent to refer to Clause 30.1.3 of the Main Contract in this respect. Practical Completion has been achieved and therefore interim certificates shall be issued as and when further amounts are ascertained as payable to the contractor …"
"We should point out that it was for you to review extensions of time under Clause 25.3.3 within 12 weeks of the date of Practical Completion of the Works and to convey your decision to us irrespective of whether we had provided any further information. However the parties to the Contract are free to agree to extend such time and we are prepared to extend the period sufficiently to enable you to consider our claim when we re-submit it …"
"The correspondence between Feltons and me was in respect to the ongoing preparation of the addendum. When the extent of the omission of finished external surfaces had been finalised it was found that the saving was greater than originally envisaged. Consequently the pin boards were added back and the contingency sum adjusted.
The revised addendum was sent to John Matthews on 22 May 2003. I did not at that point in time receive any correspondence from Feltons stating that they disagreed with the contents. Consequently the addendum was incorporated into the contract documents.
During the course of the contact the addendum has been accepted as being part of the contract documents and has been used repeatedly including in the preparation of valuations. At no point did Feltons question the validity of the document.
I consider that reverting back to a list of potential savings, other than the addendum bill, will just serve to confuse the issue and ultimately will lead to little financial adjustment. Time will be spent adjusting various instructions upon which the quantities in the addendum form an integral part. For example, the adding back of the site works will have to be re-assessed on the basis that the original bill contains more items than had been the case."
"As to your letter of 14 October 2005, given there is no executed Contract Agreement, the JCT conditions of contract to which you allude are not at all relevant to the matter under discussion and we are certainly under no obligation in terms of clause 2.3 of those conditions."
"If indeed this position has not already been reached HLP will meet with the employer and quantity surveyor to establish a complete and accurate set of contract documents."
"On the basis of the list an addendum bill would be produced which would pick up the changes in measurement and specification."
"We conclude that the variations amount to an addition of £258,311.14 compared to your application for £631,190.86 (excluding the claim and VAT). Taking into account our valuation of the variations our Final Account for the contract amounts to £3,240,111.14 excluding any substantial claim and VAT. The Final Account is therefore £217,000.64 less than Valuation No.17 issued on 16 November 2004."
i) the external works amounting to £133,766;ii) provisional savings on ironmongery of £10,000;
iii) the omission of the pin boards amounting to £14,637; and
iv) the reduction of the contingency sum by £4,930.
"18. It is Felton's case that, notwithstanding the signature of the said Letter of Intent, as a result of ambiguities and uncertainties in the scope and therefore the price of the Works to be carried out, there was in fact no binding contract between the parties as a result of the exchange of correspondence."
"Accordingly The Council is put to proof both as to the existence of any contract and the terms thereof under which the works undertaken by Felton should be valued and paid."
"In the premises Felton contends that as at 30 April 2003 the parties did not enter into a contract as contemplated in the Letter of Intent dated 25 April 2003."
"Moreover it is Felton's case that not only did they not do so then, they did not do so subsequently."
i) Markham's letter dated 17 December 2002;ii) Felton's tender, the priced Bills of Quantities, the drawings and documents referred to therein;
iii) the correction of errors agreed in the faxes between Markhams and Felton on 31 March 2003;
iv) the document entitled "agreed list of savings" dated 16 April 2003;
v) The Council's letter dated 25 April 2003; and
vi) Felton's response dated 30 April 2003 together with the countersigned letter.
CONCLUSIONS
i) the Form of Tender;ii) the Bills of Quantities;
iii) the architect and structural engineers Tender drawings; and
iv) the Mechanical and Electrical specifications and the Tender envelope.
i) There was a binding contract between the parties as set out in or evidenced by The Council's letter dated 25 April 2003 and Felton's signed response dated 30 April 2003.ii) The contract price was that set out in the letter from The Council dated 25 April 2003.
iii) It incorporated Felton's priced Bills of Quantities and the tender and drawings and other documents referred to therein. It also incorporated any savings which were offered by Felton during the end negotiations and accepted by The Council, and any savings suggested by The Council to reduce the price to £2,981,800 of which Felton had had due notice and not registered their disagreement.
iv) The JCT Standard Form subject to amendments set out in The Council's letter and further identified in the Bill of Quantities No.1 with the appendix completed as set out in Bill of Quantities No.1.
v) Markham's letter dated 17 December 2002.
vi) I add that the contract provided for variations to the contract works to be dealt with in accordance with the provisions of the contract. These were agreed variations to the original contract.
vii) If I am wrong about this I hold that there was a binding contract except for any specific item on which there was no agreement on 30 April 2003.
viii) I reject Felton's plea that there was no binding contract.
i) Felton's work (including any variations) should be valued in accordance with the JCT Standard Form as amended, the priced Bills of Quantities and the Tender drawings and the specification referred to therein.ii) Items 2, 4, 14 and 20 relied on by Felton are priced items which were omitted from the agreed work to be carried out as the contract works (as opposed to variations).
i) Finished surfaces: Bill of Quantities No.6, items 6/3A & C; 6/6H & J; 6/7N & M; 6/9E; 6/12B to 6/14A; 6/14B to 6/19B.ii) Soft landscaping: Bill of Quantities No.6, items 6/12B to 6/14A.
iii) Fencing: Bill of Quantities No.6, items 6/14B to 6/19B.
iv) Pin boards: Bill of Quantities No.4, 4/49C to 4/50G.
i) This is clearly set out in Article 7A and clause 41B of the JCT Standard Form. Clause 7B and clause A20 of the Bills of Quantities set out detailed provisions including the method of appointing the arbitrator.