BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Westwood Structural Services Ltd v Blyth Wood Park Management Company Ltd [2008] EWHC 3138 (TCC) (09 December 2008) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2008/3138.html Cite as: [2008] EWHC 3138 (TCC), [2009] CILL 2666 |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
133-137 Fetter Lane London EC4A 1HD |
||
B e f o r e :
____________________
WESTWOOD STRUCTURAL SERVICES LIMITED |
Claimant |
|
- and - |
||
BLYTH WOOD PARK MANAGEMENT COMPANY LIMITED |
Defendant |
____________________
6th Floor, 12-14 New Fetter Lane, London EC4A 1AG.
Telephone No: 020 7936 6000 Fax No: 020 7427 0093 DX: 410 LDE
Email: [email protected]
Website: www.martenwalshcherer.com
MR. ROBERT STEVENSON (instructed by Berrymans Lace Mawer) for the Defendant
____________________
Crown Copyright ©
MR. JUSTICE COULSON:
"D7.1 The decision of the Adjudicator shall be binding on the parties until the dispute or difference is finally determined by arbitration or by legal proceedings or by an agreement in writing between the parties made after the decision of the Adjudicator has been given.
D7.2 The parties shall, without prejudice to their other rights under this agreement, comply with the decision of the Adjudicator; and the Employer and the Contractor shall ensure that the decision of the Adjudicator is given effect.
D7.3 If either party does not comply with the decision of the Adjudicator the other party shall be entitled to take legal proceedings to secure such compliance pending any final determination of the referred dispute or difference pursuant to Clause D7.1."
"Upon determination of the employment of the Contractor under Clause 7.2.1 or Clause 7.2.2, the Contractor shall immediately cease to occupy the site of the Works and the Employer shall not be bound to make any further payment to the Contractor that may be due under this Agreement until after completion of the Works and the making good of any defects therein. The Employer may recover from the Contractor the additional cost to him of completing the Works and any expenses properly incurred by the Employer as a result of, and any direct loss and/or damage caused to the Employer by, the determination."
(a) although the Contract Administrator's letter of 15th January was not a practical completion certificate, practical completion had indeed been achieved on that date;
(b) the defendant did not repudiate the contract by the Contract Administrator's letter of 17th January;
(c) the sum of £40,000-odd plus VAT and fees was owing to the claimant in respect of work carried out up to 15th January, and should be paid by the defendant to the claimant by noon on 13th June 2008 (i.e. 7 days later).
"2.1.32 In this adjudication the claimant makes no claim for interest in respect of the late payment of its invoices 1, 2 and 4 which total £539.62.
2.1.33 Clause 4.3 requires the Contract Administrator to issue his penultimate certificate within 14 days of the date of practical completion and that the final date for the payment is 14 days thereafter. Thus, the final date for payment of the amount due in the penultimate certificate is 12th February 2008.
2.1.34 I consider that the claimant is entitled to simple interest on the amount I have determined as properly due to it at the rate of 5% over the base rate of the Bank of England from the date the payment became overdue until the date of this, my decision.
2.1.35 Payment became overdue on 13th February 2008 on which date the base rate of the Bank of England was 5.25%."
(a) the defendant had validly determined the claimant's employment under the contract on 25th April;(b) clause 7.2.3 "did not bite when the payment in question arose out of an adjudicator's decision";
(c) the expression "further payment" in clause 7.2.3 meant future payment, and did not apply to any payment that became due before the determination.
For these reasons the adjudicator rejected the defendant's argument that the defendant was not bound to pay the sums identified in Decision 1 as a result of the operation of clause 7.2.3.
(a) "The objective which underlies the Act and the statutory scheme requires the courts to respect and enforce the adjudicator's decision unless it is plain that the question which he has decided was not the question referred to him or the manner in which he has gone about his task is obviously unfair. It should be only in rare circumstances that the courts will interfere with the decision of an adjudicator": see paragraph 85 of the judgment of Chadwick LJ in Carillion Construction Limited v. Devonport Royal Dockyard Limited [2005] EWCA Civ 1358; [2006] BLR 18.(b) An error of fact or law will not invalidate an adjudicator's decision. If the adjudicator has answered the right question in the wrong way, his decision will nevertheless be binding. It is only if he has answered the wrong question that his decision will be a nullity: see the Court of Appeal decisions in Bouygues (UK) Limited v. Dahl-Jensen (UK) Limited [2000] BLR 522 and C & B Scene Concept Design Limited v. Isobars Limited [2002] BLR 93.
"I understand that the issue before the court is whether or not Blyth Wood is entitled to rely on the finding by the adjudicator in adjudication number 2 that Westwood's contract was properly and justifiably determined by Blyth Wood and Blyth Wood, as a consequence, can rely upon clause 7.2.3 of the contract and defer consideration of any further payment to Westwood until the works of the project are finally completed."
This appears to suggest that the defendant can defeat the claim under CPR Part 24 by relying on clause 7.2.3. That, of course, was the very argument which the adjudicator rejected in Decision 2. It does not therefore seem to me that this paragraph properly identifies what (if any) issue arises on this application.
(a) Decision 1 was not a decision that sums were due to the claimant prior to 13th June 2008;(b) By 13th June 2008, the claimant's employment under the contract had been validly determined, so that clause 7.2.3 applied;
(c) On a proper construction of that clause, the sum that was the subject matter of the Decision 1 was not due when the contract was determined and is therefore not due now.
Having been taken through the various constituent parts of that argument I have concluded that, on a proper analysis, it cannot succeed. My reasons are set out below.