BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Upton McGougan Ltd v Bellway Homes Ltd & Ors [2009] EWHC 1449 (TCC) (12 June 2009) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2009/1449.html Cite as: [2009] EWHC 1449 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
133- 137 Fetter Lane London EC4A 1HD |
||
B e f o r e :
____________________
UPTON McGOUGAN LIMITED |
Claimant |
|
- and - |
||
BELLWAY HOMES LIMITED GEORGE WIMPEY WEST LONDON LIMITED BDW TRADING LIMITED (t/a BARRATT HOMES, SOUTHERN COUNTIES DIVISION) |
Defendants |
____________________
6th Floor, 12-14 New Fetter Lane, London EC4A 1AG.
Telephone No: 020 7936 6000 Fax No: 020 7427 0093 DX: 410 LDE
Email: [email protected]
Website: www.martenwalshcherer.com
Ms Anna Laney (instructed by Watson Burton LLP) for the Defendants.
____________________
Crown Copyright ©
Mr Justice Coulson :
A. INTRODUCTION
B. APPLICABLE PRINCIPLES
"The need for extensive pleadings including particulars should be reduced by the requirement that witness statements are now exchanged. In the majority of proceedings identification of the documents upon which a party relies, together with copies of that party's witness statements, will make the detail of the nature of the case the other side has to meet obvious. This reduces the need for particulars in order to avoid being taken by surprise. This does not mean that pleadings are now superfluous. Pleadings are still required to mark out the parameters of the case that is being advanced by each party. In particular they are still critical to identify the issues and the extent of the dispute between the parties. What is important is that the pleadings should make clear the general nature of the case of the pleader. This is true both under the old rules and the new rules."
"A major objective of case management under the CPR is to ensure that statements of case do indeed set out the parties' case and define the dispute between them … As part of its responsibility for managing cases, the court will ensure that the parties plainly state the factual ingredients of their case so that the true nature and scope of the dispute can be identified. The particulars of claim and the defence are considered by the procedural judge after the defence is filed and, if the issues cannot be readily identified from the statements of case, directions are given to rectify this."
"A reply to the defence is not always necessary. However, where the defendant has raised a positive defence on a particular issue, it may be appropriate for the claimant to set out in a reply how it answers such a defence."
In the present case, I agree with Mr Cross: a reply was necessary in order to demonstrate the real disputes between the parties. I consider that point further below.
C. THE PLEADED CASE
"(a) The claimant's design assumptions about the topography of the site as at the date of its instruction were either wrong; further or alternatively were not verified.
(b) Further in the alternative, the claimant
(i) failed to determine the existing topography of the site accurately or at all;
(ii) failed to visit the site before determining the site levels;
(iii) failed to appreciate the existence of the bunds located on the site and determine their size; and/or
(iv) failed to appreciate and/or advise the First Defendant and/or the Consortium that an up to date topographical 3D survey would be required in order to determine site levels that would satisfy the design requirement.
(c) In determining the site level, the Claimant failed to take account of arisings that would be generated by excavations to the foul and storm water drainage; further or in the alternative, failed to inform or warn the First Defendant and/or the Consortium that it had not taken account of the same."
D. THE EXPERTS' REPORTS
E. ANALYSIS OF UM'S APPLICATION
E1. The Issues
(a) whether the design requirement of zero cartaway was a reasonable and feasible engineering requirement that could be achieved;
(b) whether the site levels determined by UM satisfied the design requirement of zero cartaway;
(c) if they did not, whether the site levels determined by UM would have been determined by the reasonably competent engineer instructed to achieve the design requirement;
(d) if the design did not satisfy the design requirement and was not the design of a reasonably competent engineer, identification of the cause(s) of excess spoil generation including, but not limited to, the matters asserted by UM at paragraph 47 of its defence;
(e) quantification of the precise volumes of spoil associated with each of those causes;
(f) having identified the causes of additional spoil generation, discussion of whether or not those causes were the responsibility of UM.
E2. Part 1 of Mr Brown's Report
"…may have been set unnecessarily low due to a failure to appreciate site boundary constraints, additional sources of spoil from excavations arising from building foundations, road foundations, drainage and services excavations, inconsistent topographical survey format and additional excavations such as the block F basement."
E3. Part 2 of Mr Brown's Report
E4. Summary
F. LOGISTICS