BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Imperial Cancer Research Fund & Anor v OVE ARUP & Partners Ltd & Anor [2009] EWHC 1453 (TCC) (23 June 2009) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2009/1453.html Cite as: [2009] EWHC 1453 (TCC), [2009] BLR 458 |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
IMPERIAL CANCER RESEARCH FUND CANCER RESEARCH UK |
Claimants |
|
- AND - |
||
OVE ARUP & PARTNERS LIMITED OVE ARUP & PARTNERS INTERNATIONAL LIMITED |
Defendants |
____________________
Christopher Lewis (instructed by Clare Bristow, Arup Legal group) for the Defendants
Hearing dates: 21st May 2009
____________________
Crown Copyright ©
The Hon. Mr. Justice Ramsey :
Introduction
Applications under CPR r 7.6
"(1) The claimant may apply for an order extending the period for compliance with rule 7.5.
(2) The general rule is that an application to extend the time for compliance with rule 7.5 must be made –
(a) within the period specified by rule 7.5; or
(b) where an order has been made under this rule, within the period for service specified by that order.
(3) If the claimant applies for an order to extend the time for compliance after the end of the period specified by rule 7.5 or by an order made under this rule, the court may make such an order only if –
(a) the court has failed to serve the claim form; or
(b) the claimant has taken all reasonable steps to comply with rule 7.5 but has been unable to do so; and
(c) in either case, the claimant has acted promptly in making the application.
(4) An application for an order extending the time for compliance with rule 7.5 –
(a) must be supported by evidence; and
(b) may be made without notice."
(1) The general rule is that a Claim Form must be served within 4 months after date of issue: CPR 7.5(1);(2) In relation to an application under CPR 7.6.(2), that rule does not impose any threshold condition on the right to apply for an extension of time. The discretion to extend time should be exercised in accordance with the overriding objective identified in CPR 1.1: Hashtroodi at [17], [18] and [19].
(3) In order to deal with an application under CPR 7.6(2) justly it will always be relevant for the court to determine and evaluate the reason why the claimant did not serve the claim form within the specified period: Hashtroodi at [22]
(4) The preconditions in CPR 7.6(3) do not apply to 7.6(2) but those requirements will always be relevant to the exercise of discretion on an application under CPR 7.6(2) but the fact that the conditions are not satisfied is not necessarily determinative of the outcome of a CPR 7.6(2) application: Collier at [87];
(5) The matters which the Court may take into account include the following in relation to the reason why the Claimant has not served the claim form within the specified period:
(a) Whether the claim has become statute barred since the date on which the claim form was issued is a matter of considerable importance.Where there is doubt as to whether a claim has become time-barred since the date on which the claim form was issued, it is not appropriate to seek to resolve the issue on an application to extend the time for service or an application to set aside an extension of time for service. In such a case, the approach of the court should be to regard the fact that an extension of time might "disturb a defendant who is by now entitled to assume that his rights can no longer be disputed" as a matter of "considerable importance" when deciding whether or not to grant an extension of time for service: Hashtroodi at [18] citing Zuckerman on Civil Procedure (2003) at paragraph 4.121; Hoddinott at [52].Where the application is made before the end of the four month period the fact that the claim is clearly not yet statute barred is a relevant consideration: Hoddinott at [52], [53].(b) Whether before the expiry of the four month period the nature of the claim was brought to the attention of the defendant: Hoddinott at [57].(c) Whether a party was in a position where it could not determine whether the claim had real prospects of success and could not responsibly proceed against the defendant without an expert report which was delayed awaiting a response to proper requests for information from the defendant's solicitors: Steele at [33].(6) In considering whether to set aside an order granting an extension of time it is not a relevant consideration that the claimant has proceeded in reliance of the extension of time granted on the ex parte application: Hoddinott at [48] to [50].
(7) In relation to the reason why the claim form has not been served, then:
(a) Where the Claimant has taken all reasonable steps to serve the claim form, but has been unable to do so, the Court will have no difficulty in deciding that there is a very good reason for the failure to serve: Hashtroodi at [19].(b) If the reason why the Claimant has not served the claim form within the specified period is that he (or his legal representative) simply overlooked the matter, that will be a strong reason for the Court refusing to grant an extension of time for service: Hashtroodi at [20].(c) Whilst the view could be taken that justice requires a short extension of time to be granted even when the reason for the failure to serve is the incompetence of the claimant's solicitor, especially if the claim is substantial, there are limitation periods and a claimant has four months in which to serve the claim form, which does not have to contain full details but only a concise statement of the nature of the claim: Hashtroodi at [21].
"We wrote to the various treatment providers and record holders on 28 April 2003. We had great difficulty in finding an expert who would prepare a report for liability before the beginning of September. We did not receive the first and second defendants' records until the beginning of July. We were not obviously able to instruct our expert until these records, especially the first defendant's records, were received. An expert (consultant gynaecologist) is currently preparing a liability report, although he does not feel able to comment totally until the missing records are obtained. As stated previously, a causation report and then condition and prognosis report will need to be obtained on top of the liability report if it is favourable. We do not consider that the above can be provided to us in a shorter period of time than four months".
"We are in no doubt that the applications for an extension of time for service of the claim form should have been allowed if they had been made on 15 August and 10 December 2003. The claimant had a good reason for not serving the claim form within the period prescribed by rule 7.5(2) and for requiring a further few weeks thereafter. The claimant's solicitors behaved sensibly and responsibly in not serving proceedings when they did not know whether the claimant had a claim which had real prospects of success against any, and if so which, of the three defendants. They could not responsibly proceed against any of the defendants without the support of an expert, and the reason why they needed the extension of time was that they were awaiting the expert's report. The report was delayed because the first defendant himself had not responded to proper requests for his clinical notes. The situation was quite different from that which often arises where the claimant seeks an extension of time for service of the claim form because he or she wants further time to prepare a schedule of loss. In the present case, the outstanding information went to the very heart of the claimant's case. Without the expert's report, she did not know whether she had a viable case. In these circumstances, we think that both extensions of time should have been granted. We do not find it at all surprising that those representing the second and third defendants in the present case understood that the claimant was seeking an extension of time for service of the claim form, and did not object to it."
"128. In our judgment, there was no good reason for the failure by the claimant's solicitors to serve by 24 March. The witness statement by the solicitor who was dealing with the case on behalf of the claimant, makes clear that she knew that the claim form had to be served by 24 March. At para 6, she gave the reason why she was applying for an extension of time. It was because she had received no substantive response from the first defendant to the clinical negligence protocol letter of claim….
129. In our judgment, the failure of the first defendant to respond to the letter of claim was no reason at all for not serving the claim form. It may have been a sufficient reason for seeking an extension of time for service of the particulars of claim, although even that is questionable."
"… the apparent justification advanced on behalf of the claimant, namely that his solicitors were awaiting receipt of the accountant's report, is not a reason for delaying service of the claim form. In the first place, if that point could justify any extension of time, it would be an extension for the service of the particulars of claim, not the service of the claim form
…
Quite apart from this, although the accountant's report may have been received later than the claimant's solicitors had hoped, it was received more than a month before the time for the service of the claim form expired. Further, the particulars of claim had actually been drafted by counsel some two weeks before the expiry of the 4 months period for service of the claim form. Accordingly, the matters relied on by the claimant as a reason for not serving the claim form in time would not, in our view, even have justified an extension of time for service of the particulars of claim."
"The reason given by Mr Paterson was stated in Leeson's case to be "no reason at all" for not serving the claim form. It is true that it is possible to think of more egregious examples of failure to serve. Mr Patterson did not overlook the need to serve within the 4 months period. He stated in terms in his witness statement that, if the application to extend time was dismissed, he would serve the claim form before the end of the 4 months' period. He took the trouble and incurred the expense on behalf of his client making an application without notice to extend time. But in out view, he made a serious error of judgment."
The facts of this case
(1) At paragraph 3 to 5:"3.The Claimants appointed Sheppard Robson to carry out the design of a new building at a research laboratory centre at Clare Hall in Potters Bar in or around March 2001. Sheppard Robson subsequently appointed the Defendants to carry out mechanical and electrical services, geotechnical engineering, structural engineering design and acoustic advice pursuant to a sub-consultancy agreement.4. Prior to the tendering of the works, in July 2001, the Defendants carried out a geotechnical desk study of the site, which reported that there was no shallow ground surface water issues expected at the site, which was described as a "non- aquifer".5. Work commenced on the construction around 18 March 2002, and practical completion was certified on 11 April 2003. There have been problems with water ingress into the ground floor and basement of the building, including a severe leak in February 2004. Some rectification works have taken place, but have failed to adequately address the cause of the water ingress, with the latest flood occurring in April 2008."(2) At paragraphs 9 to 13:
"9. Shortly before issuing proceedings, the Claimants engaged an independent engineering expert to advise on the causes of the water ingress and the likely remedial works required. To date that expert has been able to undertake a preliminary investigation based on a visit to the site. The claimants had hoped that this expert advice would have enabled them to serve a properly particularised claim within the stipulated time limits. However as a result of the expert's advice it has now become apparent that subterranean opening up works are required in order to enable the claimants to fully particularise their case.10. The building is currently in use by the Claimants as a research laboratory. The proposed opening up works will create a significant functional burden for the Claimants and therefore some time is required in order to make the necessary and proper arrangements. Some time will also be required for undertaking this investigation and for the Claimants' expert to advise them of his findings. It is expected that the opening up can commence later this month.11. The Claimants would also note that the preparation of their case has been obstructed by the Defendants' failure to provide documentary evidence upon reasonable request. The Claimants wrote to both Defendants on 3 October 2008 to request drawings and documentation that are necessary to the investigation of the cause of the water ingress and to the preparation of the Claim. Correspondence was entered into and a copy of the sub-contract agreement was received from the Defendants in late October 2008. Despite requests no further documents have been received to date.12. The Claimants consider that it is preferable that the additional time afforded by an extension of the period for service of the Claim Form will enable them to produce full and proper Particulars of Claim, thereby avoiding the need for amendments at a later date, which would merely create additional costs for all of the Parties.13. The service of the claim form by 22 April 2009 without fully particularised details would be premature and could lead to one or both of the Defendants incurring wasted costs. The Claimants would almost certainly then seek leave of the Court to amend the particulars of claim."
(1) At paragraph 13:
"The Claimants were at the time convinced that the grounds on which they based the application provided sufficient justification for an extension of time and they remain so convinced. The Claimants were aware of the nature of the defects that had materialised at the laboratory and believed that these had been caused or alternatively contributed to by errors in the design of the works. As the Defendants had acted as engineers with a design responsibility, it was probable that they had some liability for the deficiencies in the design of the structure that have caused the current water ingress problem."
(2) At paragraph 16:
"At the time for service of both Claim Forms approached, the Claimants' expert had still not seen the necessary project documentation and designs (on account of the behaviour of the Defendants) and, although he had undertaken an inspection of the building and prepared an initial report, he had advised that extensive subterranean excavations and further documents would be required to specify the nature of the problem and liability for the breaches. In the circumstances it would not have been sensible for the Claimants to proceed to serve the First Claim Form on the Defendants, without knowing the particulars of the design breaches levelled against the Defendants by the expert. At the time it appeared as though a considerable period would be required for arranging the subterranean excavation of this working laboratory, performing those works, preparing a written report and for a discussion of the findings between the expert and the Claimants' legal representatives."
(3) At paragraph 18:
"By way of an update on the progress of the Claimants' expert, the expert has now undertaken an invasive investigation of the condition of the water-resisting membrane system installed to the junction of the reinforced concrete basement walls and cavity wall construction. That investigation confirmed shallow excavation adjacent to the building in three areas to expose the top of the concrete wall and the water-resisting membrane, together with the removal of a number of courses of brickwork from the outer leaf of the cavity wall construction. This enabled the observation of the quality of the installation of the membrane across the basement wall and the inner leaf of the cavity wall up to the damp-proof course installed above ground level. A consolidated report has been prepared, but the expert has now been instructed to consider the documents recently provided by the Defendants to evaluate whether they have any impact upon his opinions. The expert expects to be in a position to respond during the course of next week."
Submission of the parties
Decision
(1) This is a case where, although the water ingress defect first appeared in 2002, remedial work was carried out but there was further flooding in April 2008. To investigate the cause of the flooding and the responsibility for it, the claimants' solicitors needed to obtain expert evidence.(2) To provide the necessary expert evidence, the expert required investigations in the form of excavation to view the construction of the building and also required plans of the building so that the relevant design and construction could be investigated.
(3) The claimants' solicitors properly sought the information from the defendants and obtained some information in October 2008, with drawings only being obtained by the defendants from archives and sent to the claimants' solicitors on 30 April 2009.
(4) The claimants' solicitors issued the claim form on 22 December 2008 and by April 2009 the investigations had not been completed so that the expert could produce a considered report. This, it seems, was only obtained in late May 2009, the investigations having been carried out in April/May 2009.
(5) By the end of April, the claimants' solicitors were therefore not in a position where they could properly make allegations of professional negligence against the defendants or the architects or could properly make allegations against the contractors.
(6) I consider that, in the words of Steele v Mooney, the claimants' solicitors behaved sensibly and responsibly in not wishing to serve the claim form until they were in a position where they knew whether they had a viable particularised claim against a particular party.
(7) Whilst I accept that there is an element of change of wording and emphasis between Mr Preston's first and second statements, I do not consider that the important underlying facts of the position of the claimants in April 2009 have been changed. This is not a case where the claimants sought further time merely to provide some particulars of quantum or some expert evidence of secondary importance. Rather they needed to provide a viable particularised claim. The reference to the reason being a need to particularise the claim has, in my judgment, to be read in this way where they needed expert evidence and the expert could not properly form conclusions without investigations and seeing documents.
(8) The claimants properly informed the defendants in October 2008 that they were investigating the defects. As raised in argument, under paragraph 6 of the Pre-Action Protocol for Construction and Engineering Disputes, the claimants should have applied for directions on the issue of the claim form. Whilst this would have been a proper and sensible way to proceed, I do not consider that breach of this provision of the Pre-Action Protocol should determine the matter, particularly where the general position is that such breaches are relevant only to matters of costs and, indeed, the contrary was not pressed in argument.
(9) This is a case where some limitation periods for primary causes of action are very likely to have passed between December 2008 and now, so as to give the defendants accrued limitation defences. However, experience of this type of case indicates that there are often arguments as to secondary causes of action which are not statute barred or as to later knowledge which affects the operation of limitation periods. Whilst this is a matter of considerable importance in balancing the factors, I do not consider that the position on limitation is of such strength to overcome the other factors that weigh in the claimants' favour.