BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Fitzroy Robinson Ltd v Mentmore Towers Ltd [2009] EWHC 3070 (TCC) (26 November 2009) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2009/3070.html Cite as: [2010] CP Rep 15, 128 Con LR 91, [2009] EWHC 3070 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
Case No: HT-08-97 FITZROY ROBINSON LIMITED |
Claimant |
|
- and - |
||
MENTMORE TOWERS LIMITED (a company incorporated in Jersey) |
Defendant |
|
HT-08-129 FITZROY ROBINSON LIMITED |
Claimant |
|
And |
||
(1) GOODSTART LIMITED (2) ANGLO SWISS HOLDINGS LIMITED (both companies incorporated in Jersey) -NO 2- |
Defendants |
____________________
Mr Paul Darling QC (instructed by Mischon De Reya) for the Defendants
Hearing date: 20.11.09
____________________
Crown Copyright ©
The Honourable Mr Justice Coulson :
Introduction
a) The claimant's substantial claim for fees is based squarely upon invoices raised at the time, which were not paid by the defendants, but which have never been the subject of any withholding notices.
b) The claim was originally the subject of a CPR Part 24 application in the autumn of 2008, which application was then properly abandoned by the claimant in the light of the defendant's defence, which raised a number of issues including fraudulent misrepresentation and negligence. General points were also taken as to the calculation of the fees due.
c) The liability issues were tried in May 2009 and were the subject of the judgment noted above. The defendants' misrepresentation allegations succeeded, although their financial effect was unclear. The professional negligence allegations failed.
d) It was not possible at the earlier trial to resolve as many of the issues concerned with causation and the proper calculation of the fees as I would have liked. This was because the defendants had wholly failed to plead any case whatsoever as to the effect of their liability allegations on the claimant's fee entitlement. For this reason, I considered that the onus was on the defendants to set out a properly pleaded case as to the claimant's entitlement to fees, and my directions on 21st July 2009 reflected that approach.
(a) The defendants were to serve their quantum pleadings by 2.9.09;
(b) The claimant was to respond by 23.9.09;
(c) The defendants were to serve a reply (if they were advised that it was necessary) by 2.10.09;
(d) Disclosure of any other quantum documents was to be by 9.10.09;
(e) Witness statements were to be exchanged by 23.10.09;
(f) Experts, limited to one per party, were to meet and exchange reports by 6.11.09;
(g) Experts were to produce a written joint statement pursuant to CPR Part 35.12 by 16.11.09.
(a) The defendants were to serve their quantum pleadings by 25.9.09;
(b) The claimants were to respond by 16.10.09;
(c) A reply (if so advised) was to be served by the defendants on 23.10.09;
(d) Disclosure of any additional documents was to occur by 30.10.09;
(e) Witness statements were to be exchanged by 10.11.09;
(f) Experts reports were also to be exchanged by 10.11.09;
(g) The joint statement was to be completed by 16.11.09 as originally ordered.
(a) The defendants served their quantum pleading on 28.9.09. The points raised in that document appear to be principally matters of argument and submission, although I accept that there are points raised which may require some limited expert architectural evidence. Included in this category are issues such as the percentage completion achieved; the value of work, if any, carried out beyond Stage D; the quality of the work generally (although I am presently doubtful as to how far this point can be taken); and the nature and extent of any adjustment required under clause 16 of the contract. I am told that the defendants' new expert, Mr Miers, was involved in the production of that pleading. The pleading also demonstrates that there are few, if any, matters of primary fact in dispute.
(b) The claimant's pleading was served on 20.10.09. This broadly confirms that the quantum issues are largely matters of argument, with some issues requiring expert evidence. Mr Hudson, the claimant's expert throughout, was involved in the production of this document.
(c) The defendants have chosen not to serve a reply. On their behalf, Mr Darling sought permission at the hearing on 20.11.09 to put in a belated reply, but it was apparent that the purpose of such a document was to allow the defendants at least the opportunity to raise new points which should have been pleaded before. In view of the shortness of time before trial, I refused that application. The defendants have had more than enough time to serve a reply, had they chosen to do so.
(d) The claimant provided its list of documents relating to quantum on 3.11.09. The defendants have confirmed that they have no additional quantum documents.
(e) The defendants have also indicated that they do not wish to serve any factual evidence. The claimant has prepared some witness statements which are, I am told, confirmatory in nature, relating to issues such as the extent of the work carried out, possible overlap between one partner and the other, and the like. Those statements are in an advanced stage of completion. I gave the claimant until 4.30pm on 24.11.09 to serve such statements, and that was a final order.
(f) The experts have not met; they have not exchanged reports; and they have not produced a joint statement under CPR r 35.12.
Relevant Principles
a) The parties' conduct and the reason for the delays;
b) The extent to which the consequences of the delays can be overcome before the trial;
c) The extent to which a fair trial may have been jeopardised by the delays;
d) Specific matters affecting the trial, such as illness of a critical witness and the like;
e) The consequences of an adjournment for the claimant, the defendant, and the court.
I deal with each of these considerations in turn below.
Conduct and Reasons for Delay
a) Why Mr Miers has not yet contacted or met with Mr Hudson. It was only at the hearing on 20.11.09 that it became apparent that this lack of progress was based on Mr Brownlie's specific instructions.
b) When Mr Miers might produce his report. Mr Brownlie's statement says that Mr Miers is now involved and will produce his report "shortly" which seems to be at odds with the suggestion that he cannot be ready for the trial.
c) What preparation time Mr Miers might require for his report; for his meetings with Mr Hudson; and for the production of the joint statement. In the absence of any explanation as to how much time he might need to accomplish these tasks, by comparison with how much time was left before the trial, it is impossible for the court to conclude that Mr Miers cannot be ready for the trial.
Can The Delays be Overcome?
Is A Fair Trial Jeopardised?
Specific Matters Relating to the Parties
Consequences of Adjournment
Conclusions
1.
Note 1 [2009] EWHC 1552 (TCC) 7th July 2009. [Back] Note 2 See Macob Civil Engineerung Ltd v Morrison Construction Ltd [1999] BLR 93 [Back]