BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Lee v Chartered Properties (Building) Ltd [2010] EWHC 1540 (TCC) (25 June 2010) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2010/1540.html Cite as: [2010] BLR 500, [2010] CILL 2896, [2010] EWHC 1540 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
LORRAINE LEE |
Claimant |
|
- and - |
||
CHARTERED PROPERTIES (BUILDING) LIMITED |
Defendant |
____________________
Lucie Briggs (instructed by Prettys) for the Defendant
Hearing dates: 18 June 2010
____________________
Crown Copyright ©
Mr Justice Akenhead:
Introduction
The Contract
The History
"Paul [Ms Lee's husband] told me that you had a conversation with Ian Reeves the other day.
If he will put in writing to you that Chartered… will not pursue any further payments for work undertaken at 3 Lyndhurst Road, I will write to you confirming that we will not action any claim against his company for monies we believe are due to us."
This e-mail was copied on that day to Chartered by the Architect. The reply from Mr Reeves of Chartered was dated 8 May 2009:
"I am happy with this based on the following. That both letters are sent to your office and that you effect the exchange and witness that the letters have been exchanged and agreed by both parties."
"I would like to respond to the allegations raised by Chartered Properties in their referral notice. I would first however like to record my surprise and disappointment that Chartered should have precipitated Adjudication action when I firmly believed that both parties had agreed to a settlement where there was no financial implication on either side. I have received no correspondence from Chartered to the effect that they were dissatisfied with the agreement, which both parties had actually agreed to by way of e-mail. I naturally assumed that as agreement in principle had been reached, a formal exchange of letters was not a top priority for either side."
The Adjudication
"There are a number of areas of concern I wish to raise prior to the adjudication process starting in earnest as these, I believe, do have an implication as to whether or not the process should continue.
In the Notice of Adjudication dated 30th September 2009, the Referring Party has failed to state when the dispute arose. I understand from the published guidelines on this matter, this document must adhere to certain mandatory statements and this Notice fails to do so.
Secondly, the Notice of Adjudication dated 30th September 2009, lists 8 items which the Referring Party alleges are in dispute. In their Notice of Adjudication dated 17th August 2009, the exact number of items and exactly the same alleged disputes were listed.
Notwithstanding the fact that the Referring Party aborted the first Adjudication process, the matter had gone far enough the matters to be looked at closely by the Adjudicator, including the service of both the Referral Notice and Response from me and a number of directions given by the Adjudicator in relation to certain matters. It is therefore my contention that the 8 items listed in this current Adjudication have been subject of a previous Adjudication.
Furthermore, of the 8 items listed as allegedly being in dispute, none are and the Notice of Adjudication fails to illustrate where any dispute has arisen.
On the basis of the above facts, I must inform you that for the 3rd time, the Referring Party has failed to follow the procedures laid down for the process of Adjudication to take place and I therefore respectfully suggest that the matter cannot proceed.
I await your reply and in the meantime reserve my position as to jurisdiction in this matter."
"Under the current timetable I am due to reach my Decision by Monday 9 November 2009. However, I would be grateful if the Parties would agree to extend this until Friday 13 2009."
Ms Lee responded on the same day confirming her agreement to an extension to Friday 13th November 2009. I understand that Chartered agreed also. However on 12 November 2009, he wrote again by e-mail to the parties in the following terms:
"As you know I am due to reach my Decision in respect of the above dispute tomorrow.
I confirm that I anticipate finalising my Decision by mid-day tomorrow in accordance with the current timetable.
However, there will still be items that require typing and then allowing for reading-over of the Decision I consider it will not be in a format to be e-mailed over to the Parties until possibly Monday.
If the Parties have any objection to this they should say so by return."
Ms Lee did not reply but Mr Reeves replied that day at 16.44 pm saying: "We have no objection, Monday will be fine."
"…that I have now reached my Decision on the matters before me.
As stated yesterday this is currently being typed and I anticipate it will be issued on Monday."
"Made the 13 November 2009 under my hand."
He found that that sums of £39,265.09 (for the final account), £6600 (VAT) and £2093.18 (interest) were due less £1730.64 to Chartered, plus £5508 costs and that these sums were due from Ms Lee, together with £21,246.75 in respect of 95% of his fees. None of these sums have been paid by Ms Lee.
These Proceedings
(a) Invalid appointment of adjudicator;
(b) No crystallised dispute;
(c) More than one dispute referred;
(d) No dispute because all claims and cross claims settled;
(e) Breach of natural justice by adjudicator;
(f) Adjudicator's decision issued out of time.
Although Ms Lee raised some procedural concerns such as allegedly late submission of evidence by Chartered and some errors in the form of Counterclaim and witness statements she accepted that nonetheless the hearing could fairly proceed. She also raised another challenge to the decision which was that the application to the RIBA for the nomination of an adjudicator was not accompanied by a copy of the Notice of Adjudication but she candidly and unequivocally withdrew that challenge. I will deal with each of these challenges in turn.
Invalid appointment of adjudicator
"Following the giving of a notice and subject to any agreement between the parties to the dispute as to who shall act as adjudicator-
…(b) if no person is named in the contract [as adjudicator], and the contract provides for a specified nominating body to select the person, the referring party shall request the nominating body named in the contract to select the person to act as adjudicator…"
(a) The first step in initiating an adjudication under the Scheme is the giving of a written notice of adjudication by the referring party, in this case Chartered, to the other party to the contract, Ms Lee.
(b) To give notice, the notice of adjudication must be communicated to the recipient. As the Scheme does not expressly specify how notice can be given, it can be delivered by hand, by post, by fax or by e-mail.
(c) It is only after notice has been given to the recipient that the referring party can request the nominating body named in the contract to select a person to act as adjudicator; if the request is made before the notice has been given to the recipient, the nomination of an adjudicator by the RIBA in this case would be invalid and it would follow that any adjudicator prematurely nominated would have no jurisdiction.
(a) The Defence pleads at Paragraph 4 that the request was hand-delivered to the RIBA approximately half an hour after 3.41 pm.
(b) Mr Reeves in his Third Witness Statement says at Paragraph 5 that he waited half an hour before taking the request to the RIBA; in timing terms, that would mean that he left his office in Kingsbury, London, NW9 to travel to Portland Place at about 4:10 pm.
(c) By an email dated 30 September 2009 and timed at 16.35 pm, Mr Reeves wrote to Mr Slegg who had been earlier nominated as adjudicator, abortively, in the following terms:
"As there has been no response from Ms Lee it is Chartered's intention to submit a fresh application to the RIBA which will be delivered by hand today together with a resubmission of notices, etc, to Ms. Lee."
(d) Chartered's letter seeking the nomination is dated 30 September 2009 with a cheque for the RIBA's fee.
(a) I bear in mind that Chartered, and Mr Reeves in particular, appear twice before 30 September 2009 to have made relatively elementary mistakes in seeking abortively to institute adjudication.
(b) Both the Defence and his Third Witness Statement contain Statements of Truth signed by him where on a not unimportant issue a materially different version of events is given in each.
(c) One can conclude that Mr Reeves' e-mail of 30 September to Mr Slegg must be factually wrong if the RIBA did receive the request for nomination on that day because the e-mail appears to have been sent from his office based computer (as opposed to a "Blackberry" device) and it is inherently unlikely that he would have been able to make it from Kingsbury to Portland Place, London W1 in the rush-hour, including parking his car within the 25 minutes that remained after the e-mail was sent and before the RIBA closed for business. Kingsbury is north of the North Circular in London and the distance must be about 9 miles.
(d) However, one can conclude that Mr Reeves was back in his office by the time of that e-mail (4.35 pm) but that is, in practical terms, wholly inconsistent with the Defence case and what he said in his Third Witness Statement that he left his office at about 4.10 pm to go to the RIBA. It is, almost, inconceivable that he could have got to and from the RIBA in 25 minutes.
(e) In the absence of proper explanations from Mr Reeves, which he should clearly be given the opportunity to give, it would not have been unreasonable to infer that Chartered must have delivered the request to the RIBA before it gave its notice of adjudication. The reason why Chartered and Mr Reeves should be given the opportunity to explain himself is that, if the inference was made, that would lead to a further inference that he had deliberately misled the Court.
Thus, there is a triable issue on this point and there can be no summary judgement in favour of Chartered accordingly and similarly there can be no final judgement in favour of Ms Lee in this regard.
No Crystallised Dispute
"1. The word 'dispute' which occurs in many arbitration clauses and also in Section 108 of the Housing … Act should be given its normal meaning. It does not have some special or unusual meaning conferred upon it by lawyers.
2. Despite the simple meaning of the word 'dispute', there has been much litigation over the years as to whether or not disputes existed in particular situations. This litigation has not generated any hard–edged legal rules as to what is or is not a dispute. However, the accumulating judicial decisions have produced helpful guidance.
3. The mere fact that one party (whom I shall call 'the claimant') notifies the other party (whom I shall call 'the respondent') for the claim does not automatically and immediately give rise to a dispute. It is clear, both as a matter of language and from judicial decisions, that a dispute does not arise unless and until it emerges that the claim is not admitted.
4. The circumstances from which it may emerge so that a claim is not admitted are Protean. For example, there may be an expressed rejection of the claim. There may be discussions between the parties from which objectively it is to be inferred that the claim is not admitted. The respondent may prevaricate, thus giving rise to the inference that he does not admit the claim. The respondent may simply remain silent for a period of time, thus giving rise to the same inference.
5. The period of time for which a respondent may remain silent before a dispute is to be inferred depends heavily upon the facts of the case and the contractual structure. Where the gist of the claim is well known and it is obviously controversial, a very short period of silence may suffice to give rise to this inference. Where the claim is notified to some agent of the respondent who has a legal duty to consider the claim independently and then give a considered response, a longer period of time may be required before it can be inferred that mere silence gives rise to a dispute.
6. If the claimant imposes upon the respondent a deadline for responding to the claim, that deadline does not have the automatic effect of curtailing what would otherwise be a reasonable time for responding. On the other hand, a stated deadline and the reason for its imposing may be relevant factors when the court comes to consider what is a reasonable time for responding.
7. If the claim as presented by the claimant is so nebulous and ill–defined that the respondent cannot sensibly respond to it, neither silenced by the respondent nor even an expressed non–admission, it is likely to give rise to a dispute for the purposes of arbitration or adjudication."
This was quoted with approval in the Court of Appeal in the same case ([2005] BLR 227) and in Collins Ltd v Baltic Quay Management (1994) Ltd [2005] BLR 63. One can safely proceed on the basis that the existence of a dispute or difference may be inferred from what is said or not said by the party in receipt of what may be termed "a claim" but there does not have to be an express rejection of a "claim" by the recipient. One needs to determine whether there is a "claim" and whether or not that claim is disputed from the surrounding facts, circumstances and evidence pertaining up to the moment that the dispute is subsequently referred to adjudication.
(a) The work had finished in about September 2008.
(b) The final account had been submitted in January 2009 and had been discussed between Chartered and Ms Lee's Architect to whom she had clearly delegated the responsibility of agreeing, disputing or deciding it.
(c) Clause 4.8 calls for the issue of a final certificate by the Architect within 28 days of receipt of the final account documentation.
(d) The fact that no final certificate had been issued before the referral to adjudication, that is within a period as long as about eight months after the submission of the final account gives rise to the clear inference that there were issues between Ms Lee's Architect and Chartered on the whole claimed net outstanding sum.
(e) The fact that an Interim Certificate was issued on 8 September 2009 in the gross sum of £262,672.66 compared with the gross final account of £325,477.83 demonstrates the extent and ambit of the dispute. It is clear also by then that there was a series of issues about deductions which Ms Lee thought she should be entitled to make against sums otherwise arguably due.
(f) Ms Lee suggests that she was not personally aware of any dispute being in existence at the time of the final notice of adjudication but she must have been aware that the final account had been submitted and she had left it to her Architect, in effect her agent, to investigate and, as appropriate, challenge at the final account. The fact that she was personally unaware of the extent and ambit of any dispute is not material in those circumstances.
(g) She also asserts that, because Chartered did not contact her about the final account or at all in the period between May and the first abortive notice of adjudication in August 2009, this in some way means that she had no opportunity to formulate any arguments or to consider Chartered's position and therefore that no claim was submitted which could be considered or rejected prior to adjudication. However this argument ignores the fact that the basic claim, based on the final account had been submitted in January 2009 and was clearly disputed by her Architect on her behalf. In any event, there was time between the first (abortive) notice of adjudication and 30 September 2009 for her, if she so wished, to review the final account and reject it (or otherwise).
More Than One Dispute Referred
No Dispute Because All Claims and Cross Claims Settled
(a) There is something commercially surprising about why in the light of the e-mails of early May 2009 Chartered went to the trouble and expense, as it did, to retain claims consultants to pursue claims which it at the very least had been prepared to abandon on terms that Ms Lee abandoned her cross claims. There seem to be material differences of fact as to the extent to which Chartered actually did try to secure the requisite claim withdrawal letters referred to in those e-mails. Although it does appear that Ms Lee had delegated the task of dealing with the final account to her Architect, it is odd that, if, as Mr Reeves asserts, he was being ignored by the Architect about the production of the requisite letters, he did not contact Ms Lee whose e-mail address he certainly had.
(b) It would be important to understand the detailed factual background leading up to the exchange of the early May 2009 e-mails to determine what assistance it provides in the interpretation of those e-mails. The fact that both Ms Lee and her Architect believed in the months after the emails that there had been an effective settlement possibly points to or hints at a state of affairs prior to the e-mails which might be supportive of her interpretation of the e-mails.
(c) The e-mails properly analysed in the light of that factual background could be interpreted as meaning and confirming a full and final settlement of all claims and cross claims with any requirement, contractually enforceable, that each party formally confirms in writing that they withdraw their respective claims against each other. In effect, the e-mails on their face confirm at the very least a willingness on both parties to withdraw the respective claims against the other and that, therefore, the letters to be exchanged thereafter were at least in one sense, and possibly in all senses, a formality so that each party could have it formally on record that there had been such a settlement. The factual background might well throw important light on whether or not there was any particularly good reason why the exchange of such letters was of critical importance. If there was in the factual background no reason let alone good reason for the formal recording of the abandonment of the respective claims, it would be highly arguable that the formal recording was represented simply a contractual obligation on the part of the parties as opposed to some precondition to enable the contract to come into being. I do not think that it is fair or appropriate to proceed at this stage on a summary basis simply and solely on a syntactical analysis of the words used in the e-mails.
Breach of Natural Justice by Adjudicator
Adjudicator's Decision Issued Out of Time
"19. (1) The adjudicator shall reach his decision not later than -
(a) twenty eight day days after the referral notice mentioned in paragraph 7(1), or
(b) forty two days after the date of the referral notice if the referring party so consents, or
(c) such period exceeding twenty eight days after the referral notice as the parties to the dispute may, after the giving of that notice, agree.
(2) Where the adjudicator fails, for any reason, to reach his decision in accordance with paragraph (1)
(a) any of the parties to the dispute may serve a fresh notice under paragraph 1 and shall request an adjudicator to act in accordance with paragraphs 2 to 7; and
(b) if requested by the new adjudicator and insofar as it is reasonably practicable, the parties shall supply him with copies of all documents which they had made available to the previous adjudicator.
(3) As soon as possible after he has reached a decision, the adjudicator shall deliver a copy of that decision to each of the parties to the contract."
(a) The Scheme requires the Adjudicator to "reach his decision" within 28 days of the Referral or within 42 days if the referring party so consents; it is of course open to both parties to agree on any period longer than 28 days.
(b) The Scheme differentiates between the reaching of the decision (Paragraph 19(1) and (2)) and the delivery to the parties of a copy of that decision (Paragraph 19 (3)). This differentiation was recognised by HHJ Humphrey LLoyd QC in Barnes & Elliott Ltd v Taylor Woodrow Holdings Ltd [2004] 1 BLR 111.
(c) No particular form of delivery is specified; therefore, the decision can be delivered by hand, by fax, e-mail and when time allows by post.
(d) Paragraph 19(2) expressly legislates for what may happen where the adjudicator fails for any reason to reach his decision within the time constraints laid down.
"In his second witness statement, dated 28th March, 2000 (three days before the hearing), Mr Bloor said that, at a meeting between the parties and the Adjudicator on 4th February, 2000, he understood the Adjudicator to be saying that he would reach his decision on 9th February, 2000 and would communicate it to the parties on 11th February, 2000. If this case had been persisted in, I should have concluded that the word "forthwith" in clause 41A.5.3 meant what it said and required that the process of communicating the decision should have started immediately after the decision had been reached; i.e. that the decision has two elements: first, reaching the decision and, secondly, sending that decision to the parties. Clearly, if the decision was sent only by post, it would not be received immediately. In this case it was sent by fax on 11th February, 2000. In the absence of consent to an extension of time by the party referring the dispute (Bloor), the decision was rendered out of time. This issue and its consequences have not been decided by a court, but the Scheme lays down in paragraph 19(2) that, where the Adjudicator fails for any reason to reach his decision, any party to the dispute may serve a fresh notice for a new Adjudicator to act, i.e. a new Adjudicator must be appointed (in the absence of agreement between the parties) and the adjudication starts again."
This was quoted with approval by Lord Wheatley in the Scottish case of St Andrews Bay Development Ltd v HBG Management Ltd [2003] Scot CS 103.
"75. For what it is worth, I expressed the view in Hart (which I now repeat) that the decision in Ritchie seemed to me to be right. Adjudicators do not have the jurisdiction to grant themselves extensions of time without the express consent of both parties. If their time management is so poor that they fail to provide a decision in the relevant period and they have not sought an extension, their decision may well be a nullity, as in Ritchie. And the significance of the adjudicator's default in such circumstances should not be underestimated. For example, as demonstrated by the terms of the contract in this case, an adjudicator's failure to comply with a timetable might irredeemably deprive one party from its right to challenge a Final Certificate. I regard certainty in adjudication as vital. I respectfully agree with what Lord Nimmo Smith said in his concurring judgment in Ritchie:
"If certainty is an objective, it is not achieved by leaving the parties in doubt as to where they stand after the expiry of the 28 day period".
76. Accordingly, on the basis of these reported decisions I derive the following principles.
(a) There is a two-stage process involved in an adjudicator's decision, which is expressly identified in clause 41A. Stage 1 is the completion of the decision. Stage 2 is the communication of that decision to the parties, which must be done forthwith (see Bloor and Barnes & Elliott). Thus I reject Mr Steynor's argument that a decision is not a decision until it is communicated: that seems to me to be contrary to clause 41A, and also contrary to the authorities cited above.
(b) An adjudicator is bound to reach his decision within 28 days or any agreed extended date (see Barnes & Elliott and Ritchie).
(c) A decision which is not reached within 28 days or any agreed extended date is probably a nullity (see Ritchie).
(d) A decision which is reached within the 28 days or an agreed extended period, but which is not communicated until after the expiry of that period will be valid, provided always that it can be shown that the decision was communicated forthwith: see Bloor and Barnes & Elliott."
I respectfully agree with these observations.
"80. 4.4 Issue 9 - Was a copy of the decision delivered to each of the parties as soon as it was reached?
81. The decision was not delivered to each of the parties as soon as it was reached. There were three reasons why the decision was not delivered to the parties on the day it was reached on Friday 8 December 2006 but was instead received on Thursday 14 December 2006. Firstly, the adjudicator imposed a pre-condition that the decision would not be released until MM paid his fees; secondly, the adjudicator implemented that condition and did not release the decision for 5 days whilst awaiting payment; and thirdly, the adjudicator failed to send the decision by fax, despite his direction that all communications in the adjudication should be sent in this way, but only sent it by first class post so that it arrived one day after it had been sent. In the context of the scheme rules, "delivery to each of the parties" means getting the decision into their hands rather than dispatching it to them.
82. It follows that the decision was not delivered in compliance with rule 19(3) since it was not delivered as soon as possible after it had been reached nor was it delivered prior to the end of the 42-day period whose last day was 13 December 2006. There was a delay of five days or three working days in delivering it. There was no reason in principle for the adjudicator to delay delivering his decision as soon as he has reached it even if the time for delivery has not passed. The delay was caused by his breach of rule 12(a) in imposing a pre-condition of the release of his decision that MM should first pay his fees and then enforcing this pre-condition and by his failure to comply with his own stipulated procedure whereby all communications to and from the parties should initially be by fax. However, when the decision has been reached within the relevant 28-day or 42-day period, it is incumbent on the adjudicator to deliver it as soon as it has been finished and certainly to deliver it before the relevant period of 28 or 42 days has expired.
4.5 Issue 10 - What is the effect on the validity and enforceability of the decision of the answers given to issues (7) - (9)?
83. There are now a long line of decisions in the Technology and Construction Court that have held that a decision that is not delivered promptly by the most rapid available means of delivery is invalid. These decisions include Bloor Construction (UK) Ltd v Bowmer & Kirland (London) Ltd, St Andrew's Bay Developments Ltd v HBG Management Ltd, Barnes & Elliott Ltd v Taylor Woodrow Holdings Ltd, Ritchie Brothers (PWC) Ltd v David Philip (Commercials), Hart Investments Ltd v Fidler & Others and Cubitt Building & Interiors Ltd v Fleetglade Ltd.
84. The rationale for the principle I have already summarised and which is derived from these authorities is as follows:
(1) Adjudication is intended to be a rapid and informal means of resolving disputes on a temporary basis.
(2) To that end, the scheme rules, and all other adjudication rules, provide that the adjudicator must deliver his decision promptly.
(3) Given the rationale for adjudication in its present rapid form, the rules are to be construed as being mandatory. They are rules which the adjudicator is obliged to comply with.
(4) So as to comply with this rationale, the adjudicator should use the most rapid means of delivery that are reasonably available. This will ordinarily involve use of email or facsimile facilities.
(5) Any delay after the end of the relevant adjudication period in delivering the decision must be minimal and, if the decision has been reached before the end of that period, it should be delivered within that period.
(6) Any failure to comply with the requirement of prompt and rapid delivery will render the decision unenforceable and, probably, a nullity.
85. There was no good reason for the adjudicator to have delayed in providing his decision to the parties after Friday 8 December 2006. It follows that since I agree with, and adopt, these principles, the decision of the adjudicator, even if it had been reached within the adjudicator's jurisdiction, is unenforceable and, probably, a nullity…"
Again, I broadly agree with the rationale expressed by the learned judge
Reservation of Jurisdiction
Decision