BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Dawes v Treasure and Son Ltd [2010] EWHC 3218 (TCC) (10 December 2010) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2010/3218.html Cite as: [2011] BLR 194, [2010] 2 CLC 907, 134 Con LR 133, [2011] Bus LR 676, [2011] 6 EG 104, [2010] EWHC 3218 (TCC) |
[New search] [Printable RTF version] [Buy ICLR report: [2011] Bus LR 676] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
MARTIN DAWES |
Claimant |
|
- and - |
||
TREASURE AND SON LIMITED |
Defendant |
____________________
Adrian Hughes QC (instructed by Contract & Construction Consultants (Southern) Ltd) for the Defendant
Hearing date: 26 November 2010
____________________
Crown Copyright ©
Mr Justice Akenhead:
Introduction
The Background
The Course of the Arbitration up to the Settlement
Item | Value | |
1 | The £75,000.00 in respect of the Electrical Installation for the Main House | £75,000.00 |
2 | The £18,748.12 in respect of the Site Services | £18,748.12 |
3 | Retention on the Site Services and the Music School | £191,321.20 |
4 | Prime cost not yet claimed | £145,085.05 |
5 | Overheads | £634,360.74 |
6 | Cost of the claim | £58,455.00 |
7 | Management costs including the management costs in relation to VAT | £60,195.60 |
8 | Insurance fee in respect of the Main House | £949.20 |
9 | Garden antiques fee in respect of the Landscaping | £1,883.32 |
10 | Estate services fee | £5,239.88 |
11 | Contract fee on all items apart from item 3 | £99,991.69 |
Total | £1,291,229.80 |
Item | Amount | Alternative amount |
Claimed items from above | £1,291,229.80 | £1,291,229.80 |
Alternative case - addition of profits | £162,256.90 | |
Interest | £148,400.00 | £167,348.41 |
VAT | £238,810.22 | £270,521.14 |
GRAND TOTALS | £1,678,440.02 | £1,891,356.25 |
"2. By way of brief overview Mr Dawes contends that the Adjudicator's Award was wrong and has overcompensated Treasure by up to £869,195 which sum Mr Dawes seeks to be paid back to him by Treasure by way of Defence and/or Cross Claim in these proceedings together with the interest on the sums Mr Dawes is repaid and appropriate cost award [sic].
3. In addition Mr Dawes does not accept that the works are complete and/or had been properly constructed by Treasure. The quality of Treasure's work is part of Mr Dawes' Defence and Cross Claim in these proceedings [this of course is subject to discussion and further information].
16…the certificates of making good defects should not have been issued by the Architect since the day they were issued defects existed in the works carried out by Treasure. Mr Dawes does not know why certificates of making good defects were issued by the Architect but would invite the Arbitrator to rule in due course that the certificates were improperly and invalidly issued. Annexed hereto are Schedules of the defects which still exist in Treasure's work. These Schedules are served pursuant to the Arbitrator's directions order…
21…Treasure is put to strict proof that the work instructed by the Architect is apparently to be valued as an architect's instruction because it is Mr Dawes' case that the work instructed by the Architect post practical completion is work of remedying defects in Treasure's work or competing Treasure's incomplete works…Insofar as the Arbitrator finds that works instructed by the Architect are works of remedying Treasure's defective work or completing Treasure's incomplete work then Mr Dawes invites the Arbitrator to declare that those works are not to be the subject of any further payments by Mr Dawes…the agreement contended for by Treasure…does not allow Treasure to be paid for remedying their own defects or completing their own incomplete work.
42… neither the certificates of practical completion nor the certificate of making good defects should have been issued by the Architect. In the premises therefore no retention is due to Treasure and the entire sum of £191,321.20 is not due to Treasure from Mr Dawes and in so far as it has already been paid to Treasure it falls to be repaid. In particular the reason and basis for the issue of the certificate of making good defects is wholly unknown to Mr Dawes not least because as at the date of issue of the same numerous defects remained at the premises and were being attended to by Treasure, as particularised in the Schedules annexed hereto…
AMENDED CROSS CLAIM
68 The contents of the Amended Defence hereinabove are repeated.
69 Mr Dawes reclaims the sums paid to Treasure in the Adjudication, namely:
- the Prime Costs Not Yet Claimed sum of £127,612.57
- overheads in the sum of £634,360.74
- management costs in the sum of £12,695.60
- contract fee of 76,197.33
- any VAT overpaid
- the interests of £78,327.92
Total £869,195 plus VAT
In the alternative the Learned Arbitrator is invited to decide the amount over-awarded to Treasure by the Adjudicator and to award the same by way of repayment to Mr Dawes, and/or to determine the sums properly due to Treasure in this arbitration and to so declare."
"…For the avoidance of doubt, all offers previously made are now withdrawn.
The present Arbitration divides into 2 parts. The first part is the claims made by Treasure in the amended Statement of Case and the Respondent's claim for defects. The second part is the Respondent's reclaim for money. An offer in relation to the first part is set out below. No offer is made in relation to the second part, but Treasure accept that an overall account will need to be taken when the position in relation to previous payments by Hayley Dawes is taken into account…
The offer in relation to the claims made in the amended Statement of Case and the defects is set out below:
1. The amount claimed in the amended Statement of Case was £1,678,444.02 with am alternate amount claimed of £1,891,256.25. Treasure will deduct the £800,000 which Mr Dawes is seeking from the lower of these two figures and waive the £162,256.90 extra from the additional claim. The net amount to go forward for the overall reckoning is, therefore, £878,444.02. From this figure nothing is to be deducted in relation to defects but the Respondent's claim to defects is settled at the same time…"
"It is very disappointing that you have not even acknowledged the letters we have written to you in relation to offers. Our client is keen to settle the dispute…The offers made by our client have not been met with any reciprocal offers from your client or any productive way forward.
To demonstrate our client's genuine attempt to resolve all the issues, our client is prepared to make a further and final offer which is time-limited. This offer does not reflect, in any way whatsoever, the underlying merits of our client's position-it just reflects a desire to move forward.
This offer is a Calderbank offer and is to be read by analogy with a Claimant's Part 36 offer under the CPR and to have the same consequences.
The Claimant will settle all of the claims and counter claims in the Arbitration for the sum of £400,000 plus VAT. A payment has been made for and on behalf of the Respondent in the sum of £1,018,000, net of VAT and net of the Adjudicator's fees (which the Court ordered to be borne by your client in any event). If this offer is accepted, it will involve a payment by the Claimant to the Respondent of £618,000 together with such VAT as is applicable.
1. The proper amount of VAT shall be determined by HMRC…
2. The sum in paragraph 1 includes all claims for interest to a date which is 28 days from the date of this offer.
3. To avoid any arguments about the meaning of this offer, both liability for and quantum of costs up to date which is 28 days from the date of this offer, shall be determined by the Arbitrator. Similarly, the Arbitrator shall determine the liability for his fees and expenses up to date which is 28 days from the date of this offer.
4. This offer is open for a period of 28 days from date of this offer on the terms in this letter provided it has not previously been rejected, superseded or replaced. Thereafter it may not be accepted…"
"We refer to your offer dated 15th October 2008.
We confirm that it is accepted.
We would suggest that a consent order to be prepared by you confirming the terms of the settlement.
We would suggest that the order confirms the payment of £618,000 in 14 days as we see no reason for the payment of that principal sum to be delayed while the consideration on VAT and costs are on going."
Events after the Settlement
"Concerning current business, I think there is nothing for me to do until I return to the office later this month. Concerning "the other dispute", I have expressed my willingness to continue as appointed, also assuring the parties that I would be prepared to resign if the parties agreed to it. But the effect of the arbitration agreement between the parties is clear: until such time as I am invited to take steps in this matter I may do nothing; but I am the appointed arbitrator and shall remain so unless my authority is revoked, or I am removed by the court, or I resign, or I die".
The Contract and the CIMAR Rules
"…if any dispute or difference as to any matter or thing of whatsoever nature arising under this Contract or in connection therewith…it shall be referred to arbitration in accordance with clause 9B and the JCT 1998 edition of the Construction Industry Model Arbitration Rules (CIMAR)"
"9B.1 .1 Where pursuant to article 9A either Party requires a dispute or difference to be referred to arbitration then that Party shall serve on the other Party a notice of arbitration to such effect in accordance with [CIMAR] Rule 2.3… and an arbitrator shall be an individual agreed by the parties or appointed by the person named in the Appendix in accordance with Rule 2.3…
.3 After an arbitrator has been appointed either Party may give a further notice of arbitration to the other Party and to the Arbitrator referring any other dispute which falls under article 9A to be decided in the arbitral proceedings and Rule 3.3 shall apply thereto."
"3.3 After an arbitrator has been appointed, either party may give a further notice of arbitration to the other and to the arbitrator referring any other dispute which falls under the same arbitration agreement to those arbitral proceedings. If the other party does not consent to the other dispute being so referred, the arbitrator may, as he considers appropriate, order either:
(i) that the other dispute should be referred to and consolidated with the same arbitral proceedings, or
(ii) that the other dispute should not be so referred…
3.5 In relation to a notice of arbitration in respect of any other dispute under Rules 3.2 or 3.3, the arbitrator is empowered to:
(i) decide any matter which may be a condition precedent to bringing the other dispute before the arbitrator;
(ii) abrogate any condition precedent to the bringing of arbitral proceedings in respect of the other dispute…
3.11 Where an arbitrator has ordered concurrent hearings or consolidation under the foregoing rules he may at any time revoke any orders so made and may give further orders or directions as are appropriate to have a separate hearing and determination of the matters in issue…
14.4 The parties shall promptly inform the arbitrator of any settlement. Section 51 (Settlement) then applies."
"(1) If during arbitral proceedings the parties settle a dispute, the following provisions apply unless otherwise agreed by the parties.
(2) The tribunal shall terminate the substantive proceedings and, if so requested by the parties and not objected to by the tribunal, shall record the settlement in the form of an agreed award…
(5) Unless the parties have also settled the matter of the payment of the costs of the arbitration, the provisions of this Part relating to costs (sections 59 to 65) continue to apply."
The Issues
(a) Did Mr Salisbury become functus officio, apart from issues relating to costs, either immediately upon or shortly after the settlement between the parties or at least after the 1st Costs Award?
(b) If he retained jurisdiction, was he right to find that the settlement effectively compromised amongst other things all claims for defects raised in the arbitration proceedings?
The Law
"Once a valid appointment has been made, it continues until such time as a final award on all issues, including costs is made, at which point the arbitrators cease to have any jurisdiction. The mere fact that the parties settle their dispute before the award has been made does not of itself discharge the appointment of the arbitrators. Thus, if one of the parties breaks the settlement agreement, the other party may request the arbitrators to proceed to an award without seeking their reappointment [Itex shipping Pte Ltd v China Ocean Shipping Co, The Jing Hong Hai [1989] 2 LL Rep 522 is quoted]. It has long been the practice for any settlement reached by the parties to be incorporated into a consent award to avoid problems of this type, and that practice has been given statutory recognition by s 51 of the Arbitration Act 1996."
(a) Paragraph 6-024 of Russell on Arbitration (23rd Edition) says:
"Power to make an agreed award. Many cases settle before reaching the stage of the final award. Where the parties settle their dispute in the course of the arbitration, s.51 of the Arbitration Act 1996 enables the tribunal to issue an award recording the terms agreed. Section 51 is an "opt out" provision so it applies unless the parties have agreed that it should not. The section apparently does not apply where the parties settle part only of their dispute…"
(b) Foskett's The Law and Practice of Compromise (7th edition) states at Paragraph 32-04 in dealing with settlement in arbitration:
"It has been suggested [in Russell] that s.51 does not apply where the parties do not settle the whole of the dispute. Notwithstanding that suggestion, a tribunal may embody a settlement of part only of a reference in an award relating to that part under s.47 of the 1996 Act."
(a) Primarily, as arbitration is, usually, a consensual process, one must look to the contract between the parties pursuant to which the arbitrator has been appointed to determine what the parties have agreed, expressly or by implication, about when an arbitrator's jurisdiction becomes exhausted.
(b) The settlement of a dispute after it has been referred to arbitration but before any final award does not generally, and certainly does not necessarily, bring to an end to the jurisdiction. Section 51 suggests that even if the dispute is settled there remains a jurisdiction to terminate the substantive proceedings and to resolve issues of costs or indeed any other matters remaining in dispute at that time. That jurisdiction is not expressed to be statutorily limited.
Discussion on Jurisdiction
(a) Mr Salisbury would undoubtedly still have retained jurisdiction if there had been an issue between the parties as to whether there was any settlement at all. He would still have been the arbitrator to resolve the underlying disputes which would include ruling upon a defence that the claim had been settled.
(b) Unless and to the extent that the terms of the settlement itself or of the building contract (in this case) were such as to preclude or limit his jurisdiction, there should be no limitation on his jurisdiction.
(c) Section 51(2) of the Arbitration Act primarily envisages a final settlement of the whole dispute. That is why it talks about the arbitrator terminating the substantive proceedings or the production of a consent award. There is no room for an implication, at the very least in this case, that the arbitrator's jurisdiction ceases save simply and only to deal with costs. Obviously, to the extent that the parties' dispute has in fact and in law been settled, the arbitrator can not go behind that.
(d) The parties did not proceed as if the arbitrator had no jurisdiction after the settlement. Of course, it is true that the parties accepted that he still only had costs to deal with but clearly they proceeded on the basis that he had jurisdiction at the very least to do that. They did not think it necessary to agree a consent award or to invite the arbitrator to do anything formal to "terminate the substantive proceedings". In my view, he retained a full jurisdiction and will continue to do so until he produces his final award on costs or until his final award (of whatever sort) is issued.
(e) In this case, the CIMAR Rules, agreed by the parties, expressly give a party a right "after an arbitrator has been appointed" to refer another dispute to the same arbitrator and he has the right in effect to consolidate it with the existing arbitral proceedings. That is what in practice the arbitrator did in relation to the issue as to whether Mr Dawes's defects claim was effectively encompassed by the settlement. Treasure's Notice of Arbitration No 2, issued on 2 March 2010, successfully sought to do that.
(f) By incorporating the CIMAR Rules and by having regard to Clause 9B.1.3 of the Conditions of Contract, the parties were not expressly or by implication limiting the arbitrator from dealing with or preventing a party from referring another dispute. There is no time related restriction or term in those Rules which would prevent the arbitrator from dealing with such further dispute within jurisdiction. The only conceivable restriction would be if all facets of the dispute including costs and interest had been resolved then it would be the case that the arbitrator would have ceased to have jurisdiction. That is not the present case because he retained the jurisdictional obligation at least on dealing with costs.
(g) It is suggested that, by issuing the 1st Costs Award, the arbitrator put himself in a position whereby he accepted in effect that he had terminated the substantive proceedings because he had moved on to deal with, as it is argued, the only remaining issue which was costs. That is a fallacious point, in my judgement, because the jurisdiction, which he retained, was complete and full save and in so far as it had been circumscribed or effectively removed by the settlement agreement.
Discussion on the Settlement Agreement
(a) The settlement is contained in the letters of 15 October and 12 November 2008. The factual matrix is to be found mainly within the pleadings which had been exchanged in the arbitration in the period leading up to the settlement.
(b) A useful place to start is to consider what the jurisdiction of the arbitrator was at the time of the settlement in relation to defects. It would have been impossible, jurisdictionally, for him to have refused an amendment to the Cross Claim to add the extra over costs to be claimed for the defects specifically pleaded in Mr Dawes's Schedules.
(c) In any event, Mr Salisbury was clearly required to decide if and the extent to which the matters pleaded in these Schedules were culpable defects on the part of Treasure. That would have involved a finding that the defects involved or did not involve breaches of contract on the part of Treasure and what work was required to put them right. Those are key elements of Mr Dawes' Cross Claim and indeed his Defence. The arbitrator would also have been required to determine what remedial works were required to put right any defects which were the fault or responsibility of Treasure.
(d) Although the numerous defects put forward by Mr Dawes were deployed to support various defences to Treasure's claims, they were undoubtedly also expressly deployed as "Cross Claims" to secure a repayment of sums said to have been overpaid as a result of the adjudicator's decision. He expressly pleaded in Paragraph 3 of the Defence that the "quality of Treasure's work is part of Mr Dawes' Defence and Cross Claim", he annexed Schedules of "the defects which still exist in Treasure's work" (Paragraph 16 of the Defence), and by Paragraph 68 of the Amended Cross Claim expressly repeated the contents of the Amended Defence.
(e) Mr Dawes was therefore in any event making claims in respect of the defects. He was undoubtedly seeking some financial recompense by reason of the fact that there remained, as he alleged, culpable defects in Treasure's work. He was seeking to cover himself fully in his pleading. The alternative claims in Paragraph 69 ("In the alternative the Learned Arbitrator is invited to decide the amount over-awarded to Treasure by the Adjudicator and to award the same by way of repayment to Mr Dawes, and/or to determine the sums properly due to Treasure in this arbitration and to so declare") clearly invite the arbitrator in effect, possibly amongst other things, to find that defects existed and take them into account in deciding or determining what sum was due to Treasure.
(f) Much of the Defence in so far as it raises defects does not refer to the defects as such in the Schedules because the Schedules are said to relate to defects which remained as at the date of the Amended Defence and Cross Claim. Much of the defence seeks to challenge various claims upon the basis that Treasure should not be paid for various works which involved putting right defects. An example is Paragraph 21 set out above. It is true that at least one defence, relating to retention not being due because defects were not put right, did relate to the scheduled defects. However the Schedules were not, and certainly not obviously, only deployed for defensive purposes.
(g) I put to Mr Marrin QC in argument the proposition that, if Mr Dawes had expressly raised a specific defence of abatement by reason of defects, he would not be enabled later in separate proceedings, arbitration or court, to pursue a separate claim for damages for such defects. He was, properly, minded to accept that proposition, albeit that he argued that that was not this case. I do not accept that in practice that there is much difference. The reality is that the only real reason that there were no remedial works costings against the defects was, as is now clear, that Mr Dawes's expert had not completed the exercise.
(h) It is argued that, apart from the absence of costings, a number of the "Faults" or "Defects" do not contain explanations as to why, it was alleged, Treasure was at fault. However, they were all (in Paragraph 16 of the Defence) said to be defects "in Treasure's work". Many generic complaints were in any event made, for instance Defect No. 12 ("Door magnets out of alignment") or Fault No. 13 ("Defective render panel to north side entry porch…"). The fact that on their face a number of the defects appear, at least superficially, to be design complaints, which would not obviously or necessarily be the responsibility of a contractor which did not undertake the design obligation is immaterial because Mr Dawes, rightly or wrongly was seeking to attribute blame for them against Treasure.
(i) Mr Hughes QC argued that his client's consultants' earlier offer letter of 25 July 2008 (not accepted by Mr Dawes) provided some material factual background because it demonstrated that Treasure regarded the pleaded position of Mr Dawes as involving a "claim for defects" and the offer expressly was amongst other things to settle his "claim for defects". It is difficult to see how this could be relevant factual background in that specific way because the offer was not accepted. In the light of my findings, it is not material in any event.
(j) The essential part of the offer to settle in Treasure's consultants' letter dated 15 October 2008 is: "The Claimant will settle all of the claims and counterclaims in the Arbitration…" In context, an important part of the counterclaim was a Cross Claim for defects. The Claimant was offering to settle on a basis that involved settlement of the claim for and in respect of the defects. Put another way, if the offer was accepted, Mr Dawes could not properly deploy those defects in another way in later proceedings against Treasure.
(k) The offer was accepted unconditionally and therefore Mr Dawes has settled his claims for those defects as against Treasure.
Decision
(a) Whilst I am prepared to allow Counsel's fee in full for the hearing (both parties had Leading Counsel), there must be a substantial overlap between Counsel's pre-hearing fees and Mr McArtney's time.
(b) It is of note that Mr McCartney does not indicate that his firm actually charges his time at £220 per hour but merely that this is a "Grade A equivalent" rate. I would be surprised if rates at that level were actually charged.
(c) For a case of this sort, particularly when CCC had been heavily involved in the adjudication and the arbitration, a charge involving no more than 40 hours was reasonable.
(d) Some time and cost was wasted in my view in providing a whole lever arch file of arbitration witness statements which was wholly unnecessary; all that was needed was one line in a witness statement saying that the witness statements dealt in detail with each of the defects put forward by Mr Dawes.
(e) Thus allowing 40 hours at £150 per hour for Mr McCartney's time and £15,000 for Counsel's fees and some limited expenses, one comes to £21,000.
This should be payable within 14 days.