BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Merit Process Engineering Ltd v Balfour Beatty Engineering Services (HY) Ltd [2012] EWHC 1376 (TCC) (28 May 2012) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2012/1376.html Cite as: [2012] EWHC 1376 (TCC), [2012] BLR 364, 142 ConLR 166 |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
MERIT PROCESS ENGINEERING LTD |
Claimant |
|
- and - |
||
BALFOUR BEATTY ENGINEERING SERVICES (HY) LIMITED |
Defendant |
____________________
Miss Ruth Wilkinson (instructed by Dundas & Wilson LLP) for the Defendant
Hearing date: 18 May 2012
____________________
Crown Copyright ©
Mr Justice Edwards-Stuart:
Introduction
The Main Installation package
The letter of intent
". . .
Contract documents will be sent to you in due course. In the meantime please accept our instructions to commence the works with all due expedition and in accordance with our directions.
These instructions are given to you subject to contract (and include the provision of a Performance Bond to the Value of £80,000 or 5% of your agreed Contract Value) the conditions of which will be HY/SUBCO/1 Edition 1 July 2001 Revision, but it is agreed that if the contract is not concluded between us, subject to the following restriction, you will be entitled to re-imbursement of your actual costs, properly and exclusively incurred in complying with these instructions, but you will have no entitlement to claim loss of profit or any other consequential loss, cost or expense.
Interim payments will be made to you. The first Valuation Date will be . . .
Your entitlement to re-imbursement in complying with these instructions is limited to an amount not exceeding £500,000 (Five Hundred Thousand Pounds) unless, further instructions are given to you by [the Defendant] in writing expressly or clean this financial limit. You are also required to:
- Forward a copy of your current Employers Liability and Public Liability insurances, and the completed Acknowledgement Slip from our "Health Safety & Environment Guide for Sub-Contractors" prior to commencement of any works on site.
- . . .
All of the above requirements must be satisfied prior to commencement of any works on site. Please signify your acceptance of the terms of this instruction by signing and returning to us a copy of this letter."
(My emphasis)
It is to be noted that this letter contained no limitation as to the period for which it would remain valid.
The subsequent correspondence
"Confirming yesterday's discussion:
5% limit on liquidated damages is accepted
We will provide a 5% (GBP 80,000) bond until December 04
We will provide a milestone payment schedule by Friday 12 March
If you send through a copy of your T&Cs, we can start to review."
"Confirm all acceptable. Attached doc for your perusal. It's not yet complete as we still have loose ends to tie up with Costain so the contract specifics are still missing."
"Further to our meeting yesterday with Iain, we seem to have one outstanding item, being settlement discount being included. As I recollect we agreed on an overall cost of £1,550,000.00 for the project, but still had issues over the payment being 60 days and also the fact that we could not make any payment for anything off-site.
We agreed that we would raise the contract figure to £1,600,000.00 on the basis that £22,000.00 would accommodate your financing the project costs due to non-payment off site and £28,000.00 for the deduction of 2.5% settlement discount in order that we could make payment in 35 days from application dates agreed.
If you are now stating this causes a problem then we have no alternative but to reduce the contract price by £28,000 and revert to 60 days payment terms."
"Confirming our conversation this morning.
We accept your proposal of 30-35 day payments, with valuations of onsite materials only; at a price of GBP 1,600,000.
. . ."
This suggests that the Defendant's proposal described in the e-mail of 25 March 2004 was agreed.
"I understand that the only outstanding issue related to the 2.5% Discount Clause in the Sub-Contract is now resolved with Tony.
To confirm, the agreement reached is that the Sub-Contract Amount is £1,637,500.00 which is subject to 2.5% Discount. Payment Terms to be based on 35 days.
Therefore all remaining terms are now agreed in principle - could you please therefore confirm when we can anticipate receiving the formal sub-contract for signature.
. . ."
There was no reply to this e-mail.
"37. . . . We were only able to agree that the contract price should be £1.6 m, and that we could only apply for payment in respect of on-site materials. This price compensated us for financing the purchase of offsite materials. As to the issue of MCD, I believed that by the end of the conversation we had not reached agreement on whether the £1.6 million did or did not include any allowance for the MCD.
38. It was important to us that the £1.6 m did not include MCD because £40,000 (i.e. 2.5% MCD) would have a significant impact on the profitability of the project for us especially in the light of the reductions to the sub-contract sum already negotiated by [the Defendant]"
"Sub Contract Sum: Amend to reflect agreed amount of £1,637,500 (as attached E-Mail I Paterson to A Edwards dated 30/3/04)
. . . Employers Liability £10 m/Public Liability £5 m"
"Further to your letter . . . dated 5 April 2005, I have made the relevant amendments requested, however, some items have remained unchanged and I detail those below:
1. Contract Value remains as £1,600,000.00. The original agreed value was £1,550,000.00, however [you] were looking for payment on account of materials due to the time frame between the manufacture of the racks and delivery to site being some time. We were unable to accommodate this, also the subject of the 30/35 day payment option. In order to make a reasonable compromise it was agreed that we would increase the Contract Value to £1,600,000.00 to accommodate your financing costs and to offer a part gesture toward [you] for offering the 2.5% Settlement Discount.
2. . . .
3. Article 1.3 Page 8 Item (d) Any shortfall is covered by Site Insurances
"Further to receipt of your letter dated 22 April 2005 as referenced above, we are very concerned that the proposed Contract Value does not reflect the final agreement between yourself and our Mr T Wells and respond to the individual points using your annotation:
1. We confirm the following and attach supporting correspondence
[The relevant e-mails of March 2004 - to which I have already referred above - were then listed]
The agreed value was £1,637,500 less 2.5% discount for 30/35 day payment terms - please therefore amend.
2. Noted.
3. Do not fully understand your comment - if the intention is that any shortfall between [the Claimant] insurance level of £5 m and the stated £10 m level, is to be covered by Site Insurances, then where is this stated. We would anticipate this being documented."
The response to the remaining points in the Defendant's letter was "Noted", and one typing error was pointed out.
The insurance position
"Level of Insurance (Referred to in Condition 4 (3) and to be £5,000,000 for any one occurrence unless otherwise stated):
£10,000,000"
"We responded on 9 May 2005 explaining that we did not understand what this meant, and that we required the subcontract to document that we only needed insurance of £5m. That point was never responded to by [the Defendant]."
The party's submissions in relation to the Main Installation package
"But there is no legal obstacle which stands in the way of the parties agreeing to be bound now while deferring important matters to be agreed later. It happens every day when parties enter into so-called "heads of agreement"."
The Vacuum Drainage package
The Isis package
Conclusions