BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Berry Piling Systems Ltd v Sheer Projects Ltd [2012] EWHC 241 (TCC) (21 February 2012) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2012/241.html Cite as: 141 ConLR 225, [2012] EWHC 241 (TCC) |
[New search] [Printable PDF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
BERRY PILING SYSTEMS LIMITED |
Claimant |
|
- and - |
||
SHEER PROJECTS LIMITED |
Defendant |
____________________
Miss Alexandra Bodnar (instructed by Contract and Construction Consultants Ltd) for the Defendant
Hearing dates: 2 February 2012
____________________
Crown Copyright ©
Mr Justice Edwards-Stuart:
Introduction
(1) Whether the adjudicator reached a conclusion about Sheer's counterclaim wholly or partly on the basis of an argument that was raised for the first time by the adjudicator in the Decision itself.
(2) Alternatively, if Berry is entitled to summary judgment, whether enforcement of the judgment should be stayed on the ground that by reason of its financial circumstances Berry may be unable to repay the amount if Sheer is successful in the arbitration.
The facts
"Water seeping into Sheer's excavations.
2 Piles missing.
1 Pile having a gap at high level."
"Berry contends that it is not responsible for any effects of the seepage of water because in its quotation of 22 October 2010 it made Sheer responsible for any dewatering that may be required."
"4.066 | However, Sheer does not detail the alleged effects on the programme. |
4.067 | At paragraph 4.1, 4.4, 4.5, 6.1.6 and 6.1.7 of the Response and in the Counterclaim at paragraphs 1, 2.2, and 3.1 Sheer makes further reference to delays to Sheer's work caused by Berry. |
4.068 | There is some support of (sic) Sheer's claims against Berry for delays at Documents 17 and 18 and at Tab 7 of the Response. |
4.069 | However, [Sheer] has failed to provide any proper analysis of the alleged delays to its works caused by Berry. |
4.070 | There is no information as to how Berry actually affected the Completion Date of Sheer's work and not even the simplest attempt at any critical path analysis or even a simple narrative explaining how Berry actually critically affected Sheer's progress. |
4.071 | Sheer has not addressed the issue raised by Berry at paragraph 3.4, page 5, that it was working below the water table level and that Berry stated that Secant piling would not prevent seepage and ingress of water and that the Contract made [Sheer] responsible for dewatering. |
4.072 | Berry has failed to prove to what extent, if any, Sheer caused critical delays to the completion of Sheer's work. |
4.073 | Having watched the video with the Response of the flow of water through the piles I note that it was significant at one particular leak. There appears to be no reason why that water could not have been directed to a storage tank from which it could be pumped away without flooding the excavations or developing (sic) Sheer's work. |
4.074 | Sheer has failed to proven (sic) that Berry caused any critical delays to the completion of Sheer's work." |
I should explain that in the two places where I have shown "Sheer" in square brackets the adjudicator had actually written "Berry". Both parties accepted that these were obviously clerical errors and that I should read the relevant paragraphs as corrected. Since the error formed part of his reasons, but not of the decision itself, I consider that the parties were right to do so.
The application for a stay of execution
Interest and costs
Conclusion