BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> AMEC Group Ltd v Secretary of State for Defence [2013] EWHC 110 (TCC) (08 February 2013) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2013/110.html Cite as: [2013] EWHC 110 (TCC), 146 Con LR 152 |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
AMEC GROUP LIMITED |
Claimant |
|
- and - |
||
SECRETARY OF STATE FOR DEFENCE |
Respondent |
____________________
(instructed by Reed Smith LLP) for the Claimant
Ms Sarah Hannaford QC, Mr Christopher Wilson and Ms Rachael O'Hagan
(instructed by TSol) for the Respondent
Hearing date: 19 December 2012
____________________
Crown Copyright ©
The Hon Mr Justice Coulson:
1. INTRODUCTION
"Target costs mechanisms have become common place but one which imposes a substantial overrun on one party, and then on the other party when that substantial overrun reaches a ceiling, is something which the DRB had not previously encountered."
2. THE CONTRACT
"Maximum Price Target Cost Pricing Provisions
9.1 The Authority and the Prime Contractor have agreed that the following Maximum Price Target Cost (MPTC) pricing provisions shall apply to the Works carried out under this Contract. These provisions are illustrated graphically at Part 9 to the Commercial Document.
9.2 The MPTC Pricing Provisions for the Works comprise the following as detailed in the MPTC Breakdown Schedule at Part 9 of the Commercial Document:
Design &. Construction Works 9.2.1 Target Cost £120,151,499 9.2.2 Target Profit £6,728,484 (x% of Target Cost) (5.6%) 9.2.3 Maximum Cost £139,789,223 (Target Cost + y%) (16.35162%) 9.2.4 Maximum Price £141,615,026 (Target Cost +z%) (17.86372%)
(The % figures in the above breakdown are for the purposes of establishing revised figures if Changes in the Scope of Service take place as contemplated by Condition 7.12 and 12.1)
9.2.5 A sharing arrangement for cost under-runs between the Authority and the Prime Contractor of 55/45 (the Authority's share shown first) between the Target Cost and Actual Cost ascertained in accordance with Condition 9.7 to 9.10.
9.2.6 A sharing arrangement for cost over-runs between the Authority and the Prime Contractor of 75/25 (the Authority's share shown first) between the Target Cost and Actual Costs ascertained in accordance with Conditions 9.7 to 9.10 up to the Maximum Cost, beyond which the Prime Contractor shall be liable for all costs incurred in satisfying his obligation under the Contract and whereby the share line becomes 0/100 (the Authority's share first).
9.2.7 The maximum liability of the Prime Contractor for any loss, claim or additional costs over the Maximum Price in connection with this Contract or arising from any breach of contract or under any indemnity hereunder, breach of statutory duty, in tort or otherwise at common law or otherwise howsoever arising shall not exceed the Maximum Price plus £50m (fifty million pounds sterling)
9.2.8 The Prime Contractor confirms that he estimated prices which contribute to the total cost of the MPTC Pricing Provisions, as detailed within Part 9 of the Commercial Document, represent the best estimate of the likely costs of the Works. However, both the Prime Contractor and the Authority agree that there will be no adjustment of the MPTC Pricing Provisions as a result of any increases or decreases to the estimated prices within the MPTC Pricing Provisions, at any time during the course of the Contract. This Condition shall not preclude changes to the MPTC Pricing Provisions as a result of any other provision of this contract."
"6. Condition 9.2.7 of the Terms and Conditions specify that the Prime Contractor's overall financial liability shall not exceed the Maximum Price plus £50m. This pricing agreement is to provide further clarity on who has financial liability at what part of the overall MPTC process:
The costs shown in the above diagram represent the Target and Maximum Prices as at 14th December 2008. As a principle, the Authority will require demonstration of all actual costs incurred which will contribute to the £50m liability limit."
"Assessment of Actual Costs Incurred
9.7 For the purposes of assessing Actual Costs incurred by the Prime Contractor, the Prime Contractor shall, in accordance with Condition 9.11, furnish such particulars of costs properly incurred in connection with MPTC Pricing Provisions under the Contract as may be reasonably required by the Authority. Such costs shall be allocated in accordance with the Prime Contractor's Cost Allocation Statement at Part 14 to the Commercial Document. The Prime Contractor shall permit such particulars of costs to be verified by the Authority by inspection of his books, accounts, documents and other records.
9.8 Actual Costs properly incurred against the MPTC Pricing Provisions shall include but shall not be limited to:
9.8.1 Wages and salaries constituting a direct charge to the Works preformed under the Contract;
9.8.2 Materials intended for incorporation in the Works performed under the Contract;
9.8.3 Overheads and administration charges appropriate to the Contract;
9.8.4 Sub-contractor and supplier costs within the Supply Chain for which invoices have been received by the Prime Contractor since the date of the last Milestone Payment which, in the reasonable opinion of the Prime Contractor, are anticipated to be paid to the said sub-contractor and/or supplier before satisfactory completion of the Milestone being claimed."
"Assessment of Final Price Payable
9.11 The Final Prices Payable to the Prime Contractor for carrying out the Works covered by the MPTC Pricing Provisions shall be based upon the Actual Costs in each case properly incurred and verified in accordance with Conditions 9.7 to 9.9. The Prime Contractor shall submit to the Authority, annually from date of award of contract and within 2 Months of completion of the Works, a Certified Cost Statement as per the sample attached at Schedule 5 detailing all costs incurred in providing Works under the Contract.
9.12 The Final Price Payable in respect of the Works shall be calculated as follows:
9.12.1 If the Actual Costs determined in accordance with Conditions 9.7 to 9.8 are equal to the finally adjusted Target Cost, then the Prime Contractor shall be paid the finally adjusted Target Price (i.e., finally adjusted Target Cost plus finally adjusted Target Profit);
9.12.2 If the Actual Costs determined in accordance with Conditions 9.7 to 9.8 are less than the finally adjusted Target Cost, the Prime Contractor shall be paid a sum equal to:
9.12.2.1 The Actual Cost determined in accordance with Conditions 9.7 to 9.8;
9.12.2.2 The finally adjusted Target Profit; plus
9.12.2.3 45% of the difference between the finally adjusted Target Cost and the Actual Cost determined in accordance with Conditions 9.7 to 9.8.
9.12.3 If the Actual Cost determined in accordance with Conditions 9.7 to 9.8 is greater than the finally adjusted Target Cost then the Prime Contractor shall be paid a sum equal to:
9.12.3.1 The finally adjusted Target Cost; plus
9.12.3.2 The finally adjusted Target Profit; plus
9.12.3.3 75% of the difference between the finally adjusted Target Cost and the Actual Costs determined in accordance with Conditions 9.7 to 9.8
PROVIDED that the Final Price Payable to the Prime Contractor shall not exceed the contractually agreed Maximum Price.
…
9.15 The Final Price Payable excludes the following:
9.15.15 Any costs incurred by the Prime Contractor by reason of any default or breach on the part of the Prime Contractor and without prejudice to the generality of the foregoing;
9.15.16 Any sum allowed or paid by the Prime Contractor in respect of liquidation damages;
9.15.17 Any sum allowed or paid by the Prime Contractor as damages for breach of contract;
9.15.18 Any sums allowed or paid to the Authority resulting from any loss or damage caused to the Authority, its employees or agents as a result of a default by the Prime Contractor.
9.15.19 All costs relating to remedial work as a consequence of defects in the Prime Contractor's Works as a result of negligence or gross error, or of defects noted by the DEPM in reviewing and inspecting Works submitted for final inspection, or of construction defects becoming apparent during the Defect Liability Period for which the Prime Contractor is responsible to make good."
(a) Condition 9.2.5 provided that any cost under-runs between the Target Cost and Actual Cost were to be shared 55/45 between the respondent and the claimant;
(b) Condition 9.2.6 provided that cost over-runs between the Target Cost and the Actual Costs up to the Maximum Price were to be shared 75/25 between the respondent and the claimant;[1]
(c) Condition 9.2.6 also provided that the claimant was liable for all costs beyond the Maximum Price;
(d) Once the Maximum Price plus £50 million had been reached, then Condition 9.2.7 and paragraph 6 of schedule B of the JEOIPS combined to pass the liability to pay back to the respondent. As noted below, that construction is not now disputed. The remaining issue is whether what was payable by the respondent pursuant to this provision was all costs, or merely actual costs, as defined in the contract.
3. THE AWARD / THE MAJORITY VIEW
(a) The contract conditions and paragraph 6 of JEOIPS repeatedly referred to and used the phrase "actual costs" (see paragraph 39 of the award);
(b) If condition 9.2.7 referred to all costs, howsoever incurred, not actual costs, then large parts of the clause were superfluous (see paragraph 40 of the award);
(c) Conditions 9.2.6 and 9.2.7 must be read together. When they were, it was clear that the reference to additional costs in condition 9.2.7 must mean actual costs (see paragraph 41 of the award);
(d) The claimant's contrary construction would have some very unusual results. It would mean, for example, that the claimant would not be liable for the costs caused by its own breaches of contract, and that instead the respondent would be liable to pay such costs (see paragraph 42(1) of the award);
(e) The claimant's construction would mean that many express provisions of the contract would become inapplicable once the cap of Maximum Price plus £50 million was reached. This would include the claimant's express obligation to remedy defects in its own work, and at its own cost, set out at condition 4.13 (see paragraph 42(2) of the award);
(f) The payment mechanisms in the contract related to the payment of actual costs and were inconsistent with an obligation to pay any costs, howsoever incurred (see paragraph 42(3) of the award).
4. THE AWARD / DISSENTING VIEW
"Why would the Authority agree to pay AMEC anything over Maximum Price plus £50 million? The answer must be to protect the Authority and the project from AMEC being financially unable to complete the Contract, having absorbed £50 million of loss (in addition to any other losses incurred before the maximum was reached)…From AMEC's point of view another reason would be that AMEC could be unable to get financing or comfort from its bankers for such a project with all its inherent risks, unless there was some safety valve which would ensure that its losses were capped at £50 million."
5. THE APPLICABLE LAW
5.1 Section 69 of the Arbitration Act 1996
"(1) Unless otherwise agreed by the parties, a party to arbitral proceedings may (upon notice to the other parties and to the tribunal) appeal to the court on a question of law arising out of an award made in the proceedings.
An agreement to dispense with reasons for the tribunal's award shall be considered an agreement to exclude the court's jurisdiction under this section.
…
(3) Leave to appeal shall be given only if the court is satisfied—
(a) that the determination of the question will substantially affect the rights of one or more of the parties,
(b) that the question is one which the tribunal was asked to determine,
(c) that, on the basis of the findings of fact in the award—
(i) the decision of the tribunal on the question is obviously wrong, or
(ii) the question is one of general public importance and the decision of the tribunal is at least open to serious doubt, and
(d) that, despite the agreement of the parties to resolve the matter by arbitration, it is just and proper in all the circumstances for the court to determine the question."
In the present case, I consider that the pre-conditions at s.69(3)(a) and (b) above are fulfilled. I also take the view that, if either of the grounds in (c) are made out, the provision at (d) would not operate to prevent the granting of leave to appeal.
5.2 'Obviously Wrong'
"…leave should not normally be given unless it is apparent to the judge upon a mere perusal of the reasoned award itself without the benefit of adversarial argument, that the meaning ascribed to the clause by the arbitrator is obviously wrong. But if on such perusal it appears to the judge that it is possible that argument might persuade him, despite first impression to the contrary, that the arbitrator might be right, he should not grant leave; the parties should be left to accept, for better or for worse, the decision of the tribunal that they had chosen to decide the matter in the first instance."
"This is not however to say that, even in a one-off case, an arbitrator is to be allowed to cavort about the market carrying a small palm tree and doing whatever he thinks appropriate by way of settling the dispute. What it does amount to is that the Courts will normally leave him to his own devices and leave the parties to the consequences of their choice. They will only intervene if it can be demonstrated quickly and easily that the arbitrator was plainly wrong."
"What is obviously wrong? Is the obviousness something which one arrives at…on first reading over a good bottle of Chablis and some pleasant smoked salmon, or is 'obviously wrong' the conclusion one reaches at the twelfth reading of the clauses and with great difficulty where it is finely balanced. I think it is obviously not the latter."
5.3 Questions of General Public Importance
5.4 The Relevance of a Dissenting View
"The difference of view between the experienced arbitrators in this case provides, of itself, ground for contending that the decision of the majority is 'at least open to serious doubt'."
In F Ltd v M Ltd [2009] EWHC 275 (TCC), another case where there was a dissenting view, I said at paragraph 16:
"…a comment or observation in a dissenting opinion, to the effect that an important point has been decided by the majority without reference to the parties, will be a factor to which the court will attach weight in dealing with an application under Section 68. Depending on the circumstances, such an observation may have considerable weight, although it is unlikely that it could, on its own, prove determinative."
That was a case concerning irregularity rather than a point of law, but the same general considerations must apply.
5.5 'Major Intellectual Aberration'
"It could properly be said that, if all the other criteria were established it would often, but not invariably, be unjust for an obviously wrong decision on an important question of law not to be put right by the court. That could be thought to be even more so if the chosen highly respected arbitrator had simply had a major intellectual aberration."
Although that passage was specifically concerned with s.69(3)(d) of the 1996 Act, the phrase 'a major intellectual aberration' has subsequently been described as "a useful way of bringing to mind that the error on which we are concerned, if there be an error, must be an obvious one": see paragraph 8 of the judgment of Arden LJ in HMV UK v Propinvest Friar Limited Partnership [2011] EWCA Civ 1708.
6. DOES THIS APPLICATION RAISE A QUESTION OF GENERAL PUBLIC IMPORTANCE?
(a) This was originally drafted as a one-off contract, for use on this particular project;
(b) Two or three other contracts in similar form have subsequently been let over the ten year period since this contract was first agreed;
(c) The vast majority of the contracts let by the respondent are on standard form contracts, particularly the NEC 3 form, which does not contain the sort of complex shifting back and forth of the basic liability to pay manifest here.
7. IS THE MAJORITY VIEW OBVIOUSLY WRONG?
8. IS THE DISSENTING VIEW SERIOUSLY ARGUABLE?
(a) At paragraph 56, the dissenter says that the respondent had "no interest" in actual costs once the Maximum Price was reached. That ignores all of the contract provisions relating to milestone payments and Final Payment, which apply once the Maximum Price was reached and which all say in terms that what matters is actual cost. It also ignores the point that, since the respondent was coming back on risk at Maximum Price plus £50 million, the respondent would inevitably be very interested in what was actual cost and what was cost that was due to the claimant's default, and therefore (at least ordinarily) irrecoverable.
(b) Critically, the observation in paragraph 56 as to the respondent's lack of interest in actual cost in this situation wholly ignores the proviso to clause 6 of section B of the JEOIPS document (paragraph 8 above) which expressly states that "the Authority will require demonstration of all actual costs incurred which will contribute to the £50 million liability limit." I consider that the respondent's emphasis on actual costs could not be plainer, and to conclude, in the face of those words, that it is 'implausible' that the respondent required the claimant to certify the actual costs once the Maximum Price had been reached, is wrong.
(c) Paragraph 57 talks about certainty and suggests that it is implausible to argue that the claimant's bankers would have thought that the £50 million would be limited to actual costs, so that on this basis the claimant's losses would in fact have had to have exceeded £50 million before the safety valve was triggered. But again, the answer to that is simple: that is what the contract expressly provided. Moreover, certainty is a two-way street. If the claimant was entitled to all costs incurred above Maximum Price plus £50 million, no matter how badly it performed, then in one sense it might be regarded as having an incentive to perform badly. In those circumstances, there would be no corresponding certainty for the respondent at all.
(d) Paragraph 58 appears to make a virtue of the size of the £50 million figure and then concludes that it could not mean actual costs because they would not be easy to establish. Again, with great respect to the dissenter, that simply ignores all of the contractual provisions which repeatedly say that the claimant needed to demonstrate actual costs (however hard or easy they may be to establish).
(e) Paragraph 59, which at first I did not understand, (because it refers to the last sentence of condition 9.2.6 when in fact condition 9.2.6 is just one sentence) is in truth circular. It is suggesting that condition 9.2.7 is there to bail out the claimant and that therefore, in some way, questions of actual costs no longer matter. The conclusion does not follow: even if the clause is a bail-out, that does not mean that it was intended to make recoverable every penny spent by the claimant, no matter how improperly or unreasonably.
9. CONCLUSIONS
Note 1 Although Condition 9.2.6 referred to MaximumCost, the DRB noted at paragraph 32 of their award that this must be an error and the reference should have been to MaximumPrice. Neither party argued to the contrary at the hearing. [Back]