BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Northumbrian Water Ltd v Sir Robert McAlpine Ltd [2013] EWHC 1940 (TCC) (12 July 2013) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2013/1940.html Cite as: [2013] EWHC 1940 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
NEWCASTLE UPON TYNE DISTRICT REGISTRY
TECHNOLOGY AND CONSTRUCTION COURT
The Quayside Newcastle NE1 |
||
B e f o r e :
sitting as a Judge of the High Court in Leeds
____________________
NORTHUMBRIAN WATER LIMITED |
Claimant |
|
- and - |
||
SIR ROBERT McALPINE LIMITED |
Defendant |
____________________
Jonathan Mitchell (instructed by DLA Piper UK LLP) for the Defendant
Hearing dates: 17, 18 19 June 2013
____________________
Crown Copyright ©
Judge Behrens :
1. Introduction
2. The facts
2.1 The development
2.2 The Piling Works.
2.3 The investigation
On 16 January 2009 Mr Moreland was informed that the removal of concrete had revealed a connection on the eastern side of the sewer. Accordingly he attended the site in order to investigate. The sewer was entered by Mr Oxley an employee of Kilbride at manhole 5201 who progressed up sewer. Mr Oxley took a number of photographs which revealed that a circular pipe on the eastern side of the sewer. Immediately above the pipe was concrete still to be removed. There was concrete inside the pipe. This led Mr Moreland to conclude that the concrete that had come out of the pipe had set in the pipe so as to cover the pipe.
Other photographs show a connection pipe on the western side (the Co-op drain) from which concrete has been cut out.
On 9 June 2009 a further CCTV survey of the Newgate Street sewer was undertaken. The survey commenced at manhole 5304 and terminated at manhole 5201. The survey identified the eastern pipe 18.9m downstream from manhole 5304. It was a 300 mm pipe completely blocked with concrete.
2.4 The expert evidence
Dr Hardie's first report
1. the likelihood that the concrete removed from NWL's sewer was the same concrete detailed in the Concrete Design Mix; and
2. the likely curing time of the concrete once it entered the NWL's sewer.
1. The three concrete samples from the sewer are similar to each other and contain similar coarse and fine aggregate bound within a cementitious matrix. The matrix cement is typical of Portland cement paste with a GGBS (ground granulated blast furnace slag) cement replacement. Rare cenospheres, typical of PFA (pulverised fuel ash) were also recorded.
2. The three cores received from the sprinkler tank room contiguous piles are similar to each other. These comprise similar coarse and fine aggregate bound within a cementitious matrix. The matrix is typical of a Portland type cement paste with unhydrated clinker present in minor amounts. Ground granulated blast furnace slag (GGBS) is present as a cement replacement, however, cenospheres typical of pulverized fuel ash (PFA) were not observed.
3. The coarse aggregate in concrete samples from both locations contain limestone. The limestone is varied in texture, fossil density, fossil alignment, and the presence/absence of organic material. Limestone forms 100% of the coarse aggregate within the concrete from the contiguous piled wall.
4. The coarse aggregate within the concrete samples from the sewer, in addition to limestone, contains dolerite and calcareous siltstone. These two rock types were not observed in the coarse aggregate of the samples from the contiguous piled wall. From the samples examined, dolerite forms between 16% and 33% of the coarse aggregate within the concrete from the sewer and limestone forms between 36% and 68% of the coarse aggregate from the sewer concrete.
5. The matrix cement of concrete from both locations is similar, with the presence of GGBS cement replacement. Cenospheres, typical of pulverised fuel ash (PFA) were observed in trace amounts within the concrete from the sewer, but not in the concrete from the contiguous piled retaining wall within the Sprinkler Tank.
1. A mix design certificate for the Contiguous Piled Wall, of the type provided for the main piling was not available, but it is understood that the concrete was supplied through one supplier; Tarmac, from the same batch plant.
2. It is also understood that the raw materials for the concrete were consistent for the site works. It is assumed that the only difference between the concrete in the main piles and those in the Contiguous Piled Wall was the specified strength, and hence the cement content.
"It is assumed that the mix design provided has been adhered to throughout the Site Piling works from January to March 2008. It is also assumed that the cored samples received from the contiguous piled wall cast in March 2008 used the same raw materials as concrete poured at 'the Site' in January 2008. If these assumptions are correct, it is not likely that the concrete that entered the Claimant's sewer was the same concrete poured by the Defendant on or about the 23/24 January 2008."
Mr Abbott's evidence
1. All of the aggregate used in the production of this concrete came from Barrasford quarry. The geology of Barrasford is limestone which overlays a dolerite deposit.
2. Limestone from Barrasford is typically supplied to concrete plants and dolerite is supplied to asphalt plants. This is because limestone is not permitted for use on road surfaces. It is not necessary to separate out the dolerite when supplying to concrete plants and it is possible that due to the variations in the thickness of the layers that the limestone will contain dolerite.
3. Mix design certificates list the materials and mix proportions of the concrete. They would not normally list the presence of contaminants such as dolerite and calcerous siltstone. These contaminants would not affect the performance of the concrete.
4. As the presence of PFA was only found in trace amounts it is possible that this occurred due to trace contamination from the plant and equipment used.
Dr Hardie's revised opinion
"Mr Abbott's witness statement introduces the possibility that aggregates, other than those specified in the mix design, might have been present as in the concrete supplied to May Gurney. This therefore infers that the assumptions made on the basis of the evidence provided may not be correct. It also suggests that there is a possibility that the concrete supplied to May Gurney may have contained aggregate types similar to those found in the concrete within the sewer.
My conclusions within the report were valid at the time of writing, given the information I was provided with at that time and the samples I examined. The facts of the examination remain the same. The interpretation of those facts, given the addition of the further information supplied, after the submission of my report, would alter my interpretation of the facts. This information raises the possibility that the coarse aggregate in the concrete for both the contiguous piled wall and the concrete from the sewer could have come from the same quarry and yet contain different components."
3. The source of the concrete in the Newgate Street sewer.
1. the location of pile 215 in close proximity to the drain apparently shown in the 1908 plan.
2. the loss of concrete when pile 215 was poured.
3. the dates when the concrete was poured and the date when the problems to the Co-op drain emerged.
3. the place where the concrete in the Newgate Street sewer was found. It is true that it was not found precisely contiguous to the exit from the drain in the 1908 plan and that some of the concrete will have had to make its way slightly upstream. However the concrete was found in substantially the same place as the exit from the drain.
4 the existence of concrete in both the Co-op drain and in the exit from the drain apparently shown in the 1908 plan.
4. The claim in negligence
1. No direct evidence has been led by NWL to show that anything that SRM did fell below the standard of reasonable care and skill.
2. The allegations made in the Particulars of Claim are all variations on the theme "failed to have proper regard for the presence of the sewer." It is not in dispute that SRM was aware of the presence of the Newgate Street sewer. There is no specific allegation in the Particulars of Claim or the Replies to the Part 18 Request which criticises any particular act or omission of SRM or those for whom it is responsible.
3. The existence of the drain was not discovered until Mr Roche made his second visit to the Discovery Museum in Newcastle on 6 March 2008. The failure to identify the drain before this did not amount to negligence.
1) It was not discovered in the extensive site investigations. It is to be noted that its presence was missed when NWL made its own CCTV survey of the sewer in 1988. Indeed all of the CCTV surveys are inconsistent with each other and cannot be relied on as being accurate.
2) The site was comprehensively redeveloped in the 1970s. It is surprising that the private drain survived that redevelopment. The consequence of the redevelopment was that its presence ceased to be identifiable to SRM when the site was surveyed prior to the redevelopment undertaken during 2008.
3) SRM has adduced sufficient evidence to show that it took all proper and reasonable care to identify the services on the site. A running plan was maintained and updated as services were discovered. In the immediate vicinity of Pile 215 are NWL's sewer, a bundle of BT cables and foul and surface water drains.
4) SRM's investigations have to be viewed against the background of a previous comprehensive redevelopment of the site in the 1970s. There was no evidence in fact known or available to SRM to put it on notice of the presence of the disused drain. Consulting maps held in a museum is not a step normally undertaken or reasonably to be expected to be undertaken. Mr Roche's investigations took place at a time when it was known that the Co-op had a problem. It is clear from both Mr Moreland and Mrs Brindley's evidence that NWL were unaware of the existence of either of the two connections shown on the 1908 plan.
4. Even if the 1908 plan had been discovered in the course of the site investigations it by no means follows that it would have made any difference. When Mr Roche was asked about it he said that steps would have been taken to remove the drain. However Mr Hills, Mr Roche's line manager, was not so sure. He said that he would have assessed the situation. He would have made further enquiries which would have included a consideration of the 1970's development. A decision would have been made in the light of those enquiries.
5. The piling operation at pile 215 was not carried out negligently. It is to be noted that pile 215 did not continue to consume concrete. It was filled and then appears to have subsided and stabilised before it was redrilled to a depth of 4.5 metres so that a further 2.32 m3 of concrete could be poured. Ignoring Pile 215 the average amount of concrete consumed by each of the piles poured on 23rd January 2008 was 8.88 m3. Pile 215 initially consumed 8.84 m3 of concrete. The additional 2.32 m3 represents an additional 26.1% of concrete. Given that the piles were being sunk in made ground where voids are to be expected this is not unusual. It was not such a quantity to put the piling operatives on notice that there was a problem.
5. The claim in nuisance
1. This was an isolated escape of concrete into NWL's sewer which occurred without negligence on the part of SRM. In the absence of a claim under the rule in Rylands v Fletcher the claim in nuisance must fail. NWL place no reliance on the rule in Rylands v Fletcher.
2. A claim in nuisance can only succeed if the damage arising from the nuisance is reasonably foreseeable. It was not reasonably foreseeable that any escape of concrete from the pouring of concrete at pile 215 would result in damage to the Newgate Street sewer. SRM rely on the fact that the presence of the private drain close to pile 215 was not reasonably foreseeable.
3. There was in fact no damage to the Newgate Street sewer as a result of the escape of concrete.
1. It was accepted that NWL places no reliance on the rule in Rylands v Fletcher. However it was not accepted that this was fatal to a claim in nuisance for an isolated escape such as this. It was sufficient if there was an escape of concrete causing damage to the Newgate Street sewer.
2. It was accepted that, as a matter of law, the damage relied on to found a claim in nuisance has to be reasonably foreseeable. On the facts of this case the damage to the Newgate Street sewer was reasonably foreseeable. Two of SRM's witnesses, Mr Roche and Mr Hill accepted that it was possible that if concrete escaped it might go into a void and pass from there into a sewer or drain.
1. In Cambridge Water Lord Goff discusses Professor Newark's seminal article on the Boundaries of Nuisance and Blackburn J's judgment in Rylands v Fletcher and concludes:
It follows that the essential basis of liability was the collection by the defendant of such things upon his land; and the consequence was a strict liability in the event of damage caused by their escape, even if the escape was an isolated event. Seen in its context, there is no reason to suppose that Blackburn J intended to create a liability any more strict than that created by the law of nuisance; but even so he must have intended that, in the circumstances specified by him, there should be liability for damage resulting from an isolated escape.…
Of course, although liability for nuisance has generally been regarded as strict, at least in the case of a defendant who has been responsible for the creation of a nuisance, even so that liability has been kept under control by the principle of reasonable user--the principle of give and take as between neighbouring occupiers of land, under which 'those acts necessary for the common and ordinary use and occupation of land and houses may be done, if conveniently done, without subjecting those who do them to an action'
2. Lord Goff went on to point out that as a result of the Wagon Mound No 2 reasonable foreseeability should be a prerequisite of liability in damages for nuisance, as it is of liability in negligence. In those circumstances he went on to conclude that similar foreseeability should be a prerequisite of liability under the rule in Rylands v Fletcher. As can be seen from his speech this was in part a policy decision because he considered it more appropriate for Parliament to impose strict liability for operations of high risk.
3. Lord Goff went on to hold that on the facts of that case the damage was not reasonably foreseeable and thus the claim failed.
4. Cambridge Water was further considered by the House of Lords in Transco when it declined to abolish the rule in Rylands v Fletcher. In the course of submissions I was referred by Mr Mitchell and Mr Singer to various passages from the speeches of Lord Bingham and Lord Hoffmann.
5. In paragraph 6 of his speech Lord Bingham said:
I would be willing to suppress an instinctive resistance to treating a nuisance-based tort as if it were governed by the law of negligence if I were persuaded that it would serve the interests of justice to discard the rule in Rylands v Fletcher and treat the cases in which it might have been relied on as governed by the ordinary rules of negligence. But I hesitate to adopt that solution for four main reasons. First, there is in my opinion a category of case, however small it may be, in which it seems just to impose liability even in the absence of fault. In the context of then recent catastrophes Rylands v Fletcher itself was understandably seen as such a case. With memories of the tragedy at Aberfan still green, the same view might now be taken of Attorney General v Cory Bros & Co Ltd, Kennard v Cory Bros & Co Ltd [1921] 1 AC 521 even if the claimants had failed to prove negligence, as on the facts they were able to do. I would regard Rainham Chemical Works Ltd (in liq) v Belvedere Fish Guano Co Ltd [1921] 2 AC 465, [1921] All ER Rep 48, and Cambridge Water Co Ltd v Eastern Counties Leather plc [1994] 1 All ER 53, [1994] 2 AC 264 (had there been foreseeability of damage), as similarly falling within that category.
6. In paragraphs 9 and 10 of his speech Lord Bingham made it clear that the rule in Rylands v Fletcher is a sub-species of the law of nuisance. There must be an escape from one tenement to another. It does not include a claim for death and personal injury since such a claim does not relate to any right in or enjoyment of land. In order to succeed under the rule in Rylands v Fletcher it has to be established that the thing the Defendant has brought on to his land is something which "... will naturally do mischief if it escape out of his land', 'something dangerous ...'. The practical difficulty in many cases is to determine whether the thing brought on to the land satisfies that test. He concluded paragraph 10 in the following way:
Bearing in mind the historical origin of the rule, and also that its effect is to impose liability in the absence of negligence for an isolated occurrence, I do not think the mischief or danger test should be at all easily satisfied. It must be shown that the defendant has done something which he recognised, or judged by the standards appropriate at the relevant place and time, he ought reasonably to have recognised, as giving rise to an exceptionally high risk of danger or mischief if there should be an escape, however unlikely an escape may have been thought to be.
7. In paragraph 27 of his judgment Lord Hoffmann explained the novelty of the rule in Rylands v Fletcher in this way:
Rylands v Fletcher was therefore an innovation in being the first clear imposition of liability for damage caused by an escape which was not alleged to be either intended or reasonably foreseeable. I think that this is what Professor Newark meant when he said in his celebrated article, 'The Boundaries of Nuisance' (1949) 65 LQR 480 at 488, that the novelty in Rylands v Fletcher was the decision that 'an isolated escape is actionable'. That is not because a single deluge is less of a nuisance than a steady trickle, but because repeated escapes such as the discharge of water in the mining cases and the discharge of chemicals in the factory cases do not raise any question about whether the escape was reasonably foreseeable. If the defendant does not know what he is doing, the plaintiff will certainly tell him. It is the single escape which raises the question of whether or not it was reasonably foreseeable and, if not, whether the defendant should nevertheless be liable. Rylands v Fletcher decided that he should.
8. In paragraph 33 he explained the decision in Cambridge Water in the following way:
Rylands v Fletcher established that, in a case to which the rule applies, the defendant will be liable even if he could not reasonably have foreseen that there would be an escape. But is he liable for all the consequences of the escape? In Cambridge Water Co Ltd v Eastern Counties Leather plc [1994] 1 All ER 53, [1994] 2 AC 264 the House of Lords decided that liability was limited to damage which was what Blackburn J had called the 'natural', ie reasonably foreseeable, consequence of the escape. Lord Goff of Chieveley, in a speech which repays close attention, took the rule back to its origins in the law of nuisance and said that liability should be no more extensive than it would have been in nuisance if the discharge itself had been negligent or intentional. Adopting the opinion of Professor Newark, to which I have already referred, he said that the novel feature of Rylands v Fletcher was to create liability for an 'isolated' (ie unforeseeable) escape. But the rule was nevertheless founded on the principles of nuisance and should not otherwise impose liability for unforeseeable damage.
6. Mitigation
7. Conclusion
1. that the concrete that was found in the Newgate Street sewer on 8 March 2008 was the same concrete as was poured by May Gurney at pile 215 on 23 January 2008.
2. that the claims in negligence and nuisance fail.
3. that NWL did not fail to mitigate its loss.