BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Mears Ltd v Shoreline Housing Partnership Ltd [2013] EWHC 27 (TCC) (17 January 2013) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2013/27.html Cite as: [2013] BLR 181, [2013] EWHC 27 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
MEARS LIMITED |
Claimant |
|
- and - |
||
SHORELINE HOUSING PARTNERSHIP LIMITED |
Defendant |
____________________
Marc Rowlands QC (instructed by Cobbetts LLP) for the Defendant
Hearing date: 17 December 2012
____________________
Crown Copyright ©
Mr Justice Akenhead:
The Basic Facts
(a) The parties took part in a "process mapping exercise" to discuss the practicalities as to how the project was to proceed.
(b) This exercise identified that the Schedule of Rates upon which the accepted tender was based was "not complete with regard to reactive repairs or maintenance". There were, it is argued, no "appropriate rates" in the Schedule for such work and therefore Mears would have to charge for such on an individual basis based on labour and materials utilised and that the number of inspections of work completed would be higher than desirable.
(c) There were three meetings on 21 May 2009 between Mears and SHP. The "Third 21 May Meeting" was attended by Messrs Lester and Critchley for Mears and Clarke and Tomkinson for SHP and was "called specifically to discuss the Composite Codes" with regard to the reactive repairs or maintenance work discussed at an earlier meeting that day when it had been identified that these codes "had to be agreed before Mears could start work". Proposals for these Composite Codes were discussed and there was "agreement as to how to proceed": Mr Critchley would draft a document to explain how the Composite Codes would operate, this document becoming known as the Composite Codes Explanation Document ("CRED"). Mr Tomkinson was "satisfied with the figures to be used for the Composite Codes as they were derived from the Price List which was the basis for the tender and were auditable".
(d) At this meeting "Mr Lester asked Mr Clarke and Mr Tomkinson if it would be necessary to amend the R&M Contract to take account of Composite Codes" and "Mr Tomkinson (with whom Mr Clarke agreed) stated that there was no need to amend the R&M Contract and that Mears would be paid the Composite Codes (when appropriate), even though the Composite Codes were not included in the original Price List, if the CRED was agreed by both parties".
(e) The CRED was then circulated on 22 May 2009 being subsequently discussed and agreed at the Core group Meeting on 27 May 2009.
(f) SHP and Mears met again on 2 June 2009 where the agreement to use the Composite Codes (as explained in the CRED) was again recorded.
"Overview
The SHP Customer Contract Centre (CCC) has historically raised jobs by selecting a number of codes that they deem to represent the repair that the tenant has explained to them. This is a time consuming process, and as a result of limited technical knowledge within the team, is often a pointless exercise as the whole repair has to be varied anyway…
In the past, the operations team has attempted to manage and plan the service based on the front end order that is raised by the CCC. In the main this has proved unsuccessful. The misdiagnosis also results in considerable frustrations for the Craftworkers. The whole process has [led] to a fractious relationship between SPS and the CCC.
…it became evident that a new streamlined ordering process needed to be established…
Objectives
1. To develop a set of composite codes that allow call takers to raise a job quickly, allocate an appointment, and relieve the necessity for a complex schedule of rates…
3. To reinforce cost certainty on Anite and offer SHP the ability to project and control the repairs budget.
Solution
1. Establish a single code that will allow call takers to identify trade and appointment time, and give a broad description of work.
2. Ensure that this single code covers getting an operative to site, and effecting minor repairs and establishing solutions.
3. Additional codes will then be used to complete larger jobs.
4. Average additional codes by trade and priority will be included on the original order to cover this and offer SHP greater cost certainty. Unlike the original single code this average rate will be replaced with actual rates once the craftworkers are on site.
5. This average cost will be reconciled monthly with actual usage figures…"
There were then set out what were called "Initial Ordering Rates" for Emergency, Urgent and Routine works which for each of them were £35.85, £42.37 and £42.37 respectively. The "Average Additional Work Rates" were identified as "£0" in the attached tables but Pages 5 and 6 provided information about Average Additional Work Rates and as to how they were to be calculated and a "Worked Example" for Brickwork was provided.
(a) The CRED was agreed between the parties before the R&M Contract came into effect.
(b) The Composite Rates were agreed between the parties before the R&M Contract came into effect.
(c) Mears was paid on the basis of the Composite Rates after the R&M Contract came into effect for some 5-6 months.
(d) At some stage after the R&M Contract was signed, sealed and delivered in early January 2010, SHP deducted from sums otherwise due to Mears sums paid to Mears by it on the basis of the Composite Rates.
(e) The R&M Contract as signed, sealed and delivered does not permit payment to Mears on the basis of the Composite Rates.
(a) Clauses 12.3 and 12. 4 stated:
"12.3 No change to this contract, unless provided for by the conditions of contract, has effect unless it has been agreed, confirmed in writing and signed by the Parties.
12.4 This contract is the entire agreement between the parties."
(b) Clauses 50, 51 and 52 provided for payment to of "Defined Cost" and Clause 53 providing for a system whereby there was to be a pain/and gain sharing arrangement between the parties.
These Proceedings
"Estoppel by representation
35A. SHP is estopped from withholding the Deductions. SHP represented that it promised to pay the sums as correctly calculated under the CRED at the meeting on 27 May 2009. Alternatively SHP represented by its conduct that it would pay the sums as correctly calculated under the CRED. Mears will also rely on the representations set out in paragraph 36 below. Mears suffered a detriment as set out at paragraph 37 to 40 below by relying on the representations.
Estoppel by convention
35B. Further and or alternatively, the parties at all material times until 25 January 2010 conducted themselves on the common assumption that the Composite Codes would be used as set out in the CRED and that Mears would be paid the Composite Codes where appropriate (as defined in the CRED). It would be unjust or unconscionable for SHP to now deny that assumption.
Misrepresentation
35B. Further and or alternatively, Mears relied on the representation of Mr Tomkinson and Mr Clarke that the R&M Contract did not have to be amended even though the Composite Code would be used as set out at paragraph 10C above.
35C. If Mears had been told that Shoreline would rely strictly on the R&M Contract as signed then it would not have agreed to enter into the R&M Contract, unless the Price List included with the R&M Contract was amended to include the Composite Code.
35D. In the premises Mears claims damages for the misrepresentation made by Mr Tomkinson and Mr Clarke at the Third 21 May Meeting."
"Mears will rely, inter alia, on the following representations:
1) SHP represented that it agreed to use the Composite Codes as set out in the CRED. Mears will rely particularly (but not exclusively) on the meetings between the parties on 27 May 2009;
2) SHP represented that there was no need to amend the R&M Contract to include the Composite Code. Mears will rely particularly (but not exclusively) on the Third 21 May Meeting as set out in paragraph 10A to 10C above; and
3) SHP originally paid for the Works in accordance with the Composite Code between 20 July 2009 and 25 January 2010 having audited various jobs which contained Composite Codes, and whilst SHP challenged some costs and or codes it did not challenge the Composite Codes, when used in accordance with the CRED.
"Further, Mears can no longer charge what it would have been entitled to charge for the Works under the R&M Contract due to the passage of time. This is on account of, inter alia:
1) the R&M Contract provides that works not provided for on the SOR [Schedule of Rates] (being works which were included in the Composite Codes) would be paid for on the basis of quotations, compensation events and then agreeing prices before the works were completed or alternatively the relevant elements of the works would have been paid on the basis of codes for labour, materials plus fee; in the premises it is not possible to agree the price of 13,605 orders for Works as the work has now been undertaken;
2) the fact that the Works have been covered up or the subject matter of the Works have been subsequently altered or re-used, and
3) It is not now possible to ascertain the full detail of the individual items of the Works particularly given that there are 13,605 orders for Works for the period 20 July 2009 to 25 January 2010 and there are up to 8000 properties or thereabouts across which the works could have been carried out, such that making arrangements to access alone would be disproportionate."
"This is a request for detailed evidence and it is not necessary to understand Mears' case. In the premises it is not an appropriate request for further information. Without prejudice to the previous two sentences, at this stage, Mears is not able to provide copies of all relevant documents as this will include a review of all relevant day books, e-mail accounts and notes. Mears will provide the relevant disclosure in accordance with the court timetable."
In relation to the Estoppel by Representation allegations in Paragraph 35 and 36, in answer to Request 5 ("Please state with precision each clear and unequivocal representation of fact (as opposed to future intention, or promise to do something in the future), which was false, relied upon"), the answer was:
"SHP represented that there was no need to amend the R&M Contract (which included the Price List) on account of the agreement to use the Composite Codes. Given SHP's case is now that it would be necessary to amend the R&M Contract (which included Price List) for Mears to be paid under the Composite Codes, the representation was false."
In relation to Estoppel by Convention, in answer to Request 12 ("…please state the date on and manner in which such [common] assumption was so shared") Mears pleaded:
"The assumption as to the fact that there was no need to amend the R&M Contract was expressly shared between the parties in the third meeting on 21 May 2009. The common assumption that Mears would be paid the Composite Code was expressly stated at the process mapping days, meetings on 21 May 2009 and at the meetings on 27 May 2009 and 2 June 2009."
Practice
"3.There was no dispute as to the principles applicable to a claim for summary judgment. Counsel agreed the recent convenient summary by Lewison J in Nigeria v Santolina Investment [2007] EWHC 437 (Ch):
1. The court must consider whether the defendant has a "realistic" as opposed to a "fanciful" prospect of success.
2. A "realistic" defence is one that carries some degree of conviction. This means a defence that is more than merely arguable.
3. In reaching its conclusion the court must not conduct a "mini-trial".
4. This does not mean that the court must take at face value and without analysis everything that a defendant says. In some cases it may be clear that there is no real substance in factual assertions made, particularly if contradicted by contemporaneous documents.
5. However, in reaching its conclusion the court must take into account not only the evidence actually placed before it on the application for summary judgment, but also the evidence that can reasonably be expected to be available at trial.
6. Although a case may turn out at trial not to be really complicated, it does not follow that it should be decided without a fuller investigation into the facts at trial than is possible or permissible on an application for summary judgment. Thus the court should hesitate about making a final decision without a trial, even where there is no obvious conflict of fact, where reasonable grounds exist for believing that a fuller investigation into the facts of the case would add to or alter the evidence available to a trial judge and so affect the outcome of the case."
Discussion
(a) There was in fact (if not in law) an agreement that the CRED and the Composite Codes should apply and be applied and that there were perceived advantages to both parties in so doing.
(b) There was a draft contract around at the time of this agreement which took place in May, possibly going into June, 2009; at the very least there were detailed terms upon which Mears had tendered which were to form the basis of the contract.
(c) On Mears' evidence, it was told and both parties proceeded on the basis that there was or would be no need to amend the R&M Contract terms to reflect the CRED and the Composite Codes and that Mears would be paid on the basis of Composite Codes.
(d) The R&M Contract was not amended to reflect this but for the first six months of the Contract operation Mears was paid on this basis. There may be explanations yet to come from SHP as to why it did pay, although those are not particularly well evidenced, albeit I was told that it was only when SHP first did a six monthly check, possibly in the assessment of the pain/gain allowances, that it discovered what it believed were discrepancies.
"(i) the parties have established, by their construction of their agreement or a common apprehension as to its legal effect, a convention basis; (ii) on that basis the parties have regulated their subsequent dealings; (iii) one party would suffer detriment if the other were to be permitted to resile from that convention".
The convention is broadly a "common assumption" which must be "expressly shared between" the parties, the party alleging the estoppel must have conveyed "to the other party an understanding that he expected the other party to rely upon it and that "reliance must have occurred in connection with some subsequent mutual dealings between the parties".
"The doctrine of estoppel is one of the most useful and flexible in the armoury of the law. But it has become overloaded with cases…It has evolved during the last 150 years in a sequence of separate developments…At the same time it has been sought to be limited by a series of maxim…All these can now be seen to merge into one general principle shorn of limitations. When the parties to the transaction proceed on the underlying assumption - either of fact or of law - whether due to mistake or misrepresentation makes no difference - neither of them will be allowed to go back on that assumption when it would be unfair and unjust to allow him so to do. If one of them does seek to go back on it, the courts will give the other such remedy as the equity of the case demands".
At Paragraph 10.04, the authors identify later cases in the House of Lords which accept broadly that doctrine. They do go on, however to identify some difficulties "despite such powerful authority".
"For the doctrine to be invoked, the assumption at issue must be shared…First, one party must have acted so that 'across the line' between it and the other party, a belief or expectation is created in the mind of the other party. Second, the conduct required for there to be a 'crossing of the line' is mutually 'manifest conduct' all course of dealing which although not a contract must be 'something very close to it'...the estoppel may be negatived by the terms of any contract between the parties, the most obvious being the presence of an entire agreement clause. Further, there is some debate as to whether estoppel by convention can arise from pre-contractual negotiations, the fact that negotiations are on foot making it unlikely that there will be a sufficient common assumption...
It follows that an estoppel by convention will only rise in limited circumstances..."
"First, A makes a false representation of fact to B…Second, in making the representation, A intended or knew that it was likely to be acted upon. Third, B, believing the representation, acts to its detriment in reliance on the representation. Fourth, A subsequently seeks to deny the truth of the representation. Fifth, no defence to the estoppel can be raised by A".
They go on to say at Paragraph 9.04 that the "weight of authority favours the view that estoppel by representation is a rule of evidence rather than of substantive law. The doctrine does not, in itself, amount to a cause of action."
"The representation must be one of fact which is untrue. A representation as to future intention does not give rise to an estoppel by representation. Hence a promise to do something in the future does not trigger the operation of the doctrine even where detrimental reliance has taken place. If such representations are to have legal effect, it must be in contract, waiver, proprietary estoppel or promissory estoppel/equitable forbearance".
Decision