BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> The Secretary of State for the Home Department v Raytheon Systems Ltd [2014] EWHC 4375 (TCC) (19 December 2014) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2014/4375.html Cite as: [2014] EWHC 4375 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
THE SECRETARY OF STATE FOR THE HOME DEPARTMENT |
Claimant |
|
- and - |
||
RAYTHEON SYSTEMS LIMITED |
Defendant |
____________________
Joe Smouha QC and Emily Wood (instructed by Clifford Chance LLP) for the Defendant
Hearing dates: 8-9 December 2014
____________________
Crown Copyright ©
Mr Justice Akenhead:
The Contract
“"69.1 This Clause 69.1 sets out the rights of [Y] to terminate this Agreement for cause.
69.1.1 [Y] may terminate this Agreement by giving a Termination Notice to [Z] if one or more of the circumstances set out in Clause 69.1.2 exist, each being a Default. Such Termination Notice shall specify the Default and specify whether [Y], in accordance with paragraph 2.15 of Schedule 7.1 (Charges and Invoicing), wishes to exercise its rights to recover all or part of the Clawback Eligible Payments as described in paragraph 2.15.1 of Schedule 7.1 (Charges and Invoicing).
69.1.2 The circumstances giving rise to [Y’'s] right to terminate in the event of Default are:
(a) [Z] is in material Default which it has failed to remedy in accordance with the Remedial Plan Process;
(b) [Z] commits a material Default of this Agreement which is irremediable;
(c) [Z] commits repeated Defaults (whether of the same or different obligations and regardless of whether those Defaults are remedied), which [Y] considers, in its reasonable opinion, collectively constitute a material Default, in which case Clause 69.1.2(a) or 69.1.2(b) shall apply;
(d) [Z] has failed to Achieve a Key Milestone by the dates set out in the Implementation Plans or in accordance with any Remedial Plan which has been agreed under Schedule 8.9 (Remedial Plan Process), in which case Clause 69.1.2(a) shall apply…
(l) any Programme Milestone is not Achieved within three (3) months of the scheduled date for the Achievement of the relevant Programme Milestone.
In determining whether to exercise any right of termination pursuant to this Clause 69.1.2 [Y] shall:
(i) act in a reasonable and proportionate manner having regard to such matters as the gravity of any offence and the identity of the person committing it; and
(ii) give all due consideration, where appropriate, to action other than termination of this Agreement.""
I have underlined the last part of this clause and I will refer to this part of the Clause as the ""Process Requirements"". Clauses 69.2 to 69.4 provided for termination in other circumstances such as for convenience. Clause 69.5 provided for termination for a continuing Force Majeure Event or Relief Event.
“"74.1 The termination of this Agreement in accordance with Clause 69 or its expiry shall not affect the accrued rights of either Party.
74.2 Following the service of the Termination Notice, the Service Provider shall continue to provide the Services in accordance with the provisions of this Agreement up to and including the Exit Management Date.
74.3 Notwithstanding the termination of this Agreement for any reason, it shall continue in force to the extent necessary to give effect to those of its provisions which expressly or by implication have effect after termination.""
Clause 75 provided for payments to be made on termination, there being cross-reference to Schedule 7.2 in respect thereof.
The Arbitration
“"11. This is a complex dispute. The Agreement runs to 218 pages and cross-references nearly 60 lengthy formal and informal schedules, the ""compressed"" version of which fills three volumes. The parties’' pleadings, including Annexes, ran to almost 4000 pages. The tribunal received written witness statements from no fewer than 60 fact witnesses, often two and sometimes three per witness, and principal and reply expert reports from 8 expert witnesses, supplemented by joint reports from pairs of experts. The parties also delivered extensive written and oral opening and closing submissions. During the course of 8 weeks of hearing, the tribunal heard live testimony from over 50 of the factual witnesses and all 8 expert witnesses. In addition, there were several procedural hearings conducted before the final hearing, together with two days at the end devoted to oral closing argument.
12. The evidence presented to the tribunal covered almost every aspect of the interactions between the parties over a period of more than three years. Despite its complexity, however, the many points in contention turn on three principal issues:
(a) Was [Y’'s] termination of the…Agreement lawful?
(b) If the termination was lawful, what are the financial consequences of a lawful termination by [Y]?
(c) If the termination was not lawful, what are the financial consequences of [Y’'s] repudiation of the…Agreement?”"
“"(a) Who made the decision to terminate? Was it the [HS] alone, the MPRG, or some combination of…officials including the HS acting with others…?
(b) To the extent that the decision to terminate was influenced by the MPRG’'s recommendations - and to the extent that the MPRG process was flawed or did not take into account the contractual requirements of termination for cause - was the decision to terminate fundamentally flawed and thereby unlawful?
(c) In any event, even if the decision to terminate was taken by the [HS] acting alone, as argued by [Y], did [the HS] comply with the requirements found in Clause 69.1.2 (i) and (ii)? Did [the HS], in other words, or when determining whether to exercise any right of termination pursuant to this Clause 69.1.2 act in a reasonable and proportionate manner, having regard to such matters as the gravity of any event and the identity of the person committing it, and did [the HS] give all due consideration, where appropriate, to action other than termination of the Agreement?""
“"…The tribunal agrees that both establishing an event of Default in the first part of Clause 69.1.2 and fulfilling the mandatory requirements in the second part of Clause 69.1.2 are necessary conditions to the right to terminate the Agreement for cause.""
They went on at Paragraphs 263-5 in addressing the sub-issue as to whether the requirements of Clause 69.1.2 (i) and (ii) applied solely to the decision to terminate itself or also to the decision-making process:
“"263. The introductory phrase ""in determining whether to exercise any right of termination…[Y] shall…”" is followed by the requirement to ""act in a reasonable and proportionate manner…"" and ""…give all due consideration…"". In the opinion of the Tribunal these phrases indicate a process by which a decision to terminate is reached. This part of Clause 69.1.2 is predicated on a right of termination already existing and requires [Y] to act in a certain manner when determining whether to exercise any such right. Thus assuming an event of Default giving rise to a right to terminate is established, any determination whether to exercise that right must be subjected to the further requirements set out in the second half of Clause 69.1.2. That is to say, the determination is bound to include the process by which such a decision is made.
264. This conclusion does not mean, however, that the process by which the decision to exercise the right of termination is made must be elevated into a quasi-public law exercise that includes the formal requirements of administrative law…The Tribunal…finds that there is ""no right to be heard"" as alleged by [Z].
265. Nothing in the wording found in Clause 69.1.2 (i) and (ii) gives rise to any suggestion that [Z] was entitled to an audience once the right to terminate had arisen. The duties described are expressly directed at [Y]. At that stage, so long as [Y] fulfils these duties and satisfies the other requirements of Clause 69.1.2, it may determine to exercise the right to terminate. That being said, however, the tribunal is also satisfied that the requirements in this Clause obliged the person considering whether to exercise the right of termination to address clearly the particular ground from which that right arose to determine whether it would be reasonable and proportionate to rely upon it and, in particular, to look at the ""gravity"" of any offence and the identity of the person committing it. Thus, for example, if Milestones were to be relied upon as giving rise to a right of termination, it would follow in the circumstances of this case that the person deciding whether to terminate on that basis should have reasonably addressed whether [Y] caused or contributed to the missing of those milestones. Even if [Z] had no right of audience in this decision-making, [Y] remained obliged to comply fully with the requirements in Clause 69.1.2, including taking into account whether there were mitigating circumstances that might make it unreasonable or disproportionate to exercise any right of termination, even if the existence of a material Default was established"".
“"380…the tribunal proposes to examine, firstly, the process by which the decision to terminate was taken and then, if required, the substantive grounds for termination on which the decision to terminate was taken.
381. For the purposes of the tribunal’'s analysis in the remainder of this section, it is assumed, without so concluding, that by mid-May 2010 there was a relevant Default under Clause 69.1.2 (a) - (l). In other words, it is assumed that by that date there were circumstances giving rise to a prima facie right to terminate.
382. This working assumption is made in order to focus initially on [Z’'s] submission that [Y] breached its duty in relation to the requirements found in the second part of Clause 69.1.2.""
“"The tribunal has found four instances in which [Y] failed to meet its obligations under Clause 69.1.2 for Agreement with respect to the exercise of any right of termination it may have had. In particular:
(a) [HS] failed to address in any adequate fashion the difficult question of whether and, if so, to what extent [Y] had caused or contributed to the Defaults on which [HS] was relying to terminate the Agreement;
(b) [HS] relied upon and deferred to the recommendation of the MPRG…[HS’'] reliance upon and deference to the MPRG’'s recommendation was flawed and similarly not compliant with Clause 69.1.2 (i) of the Agreement.
(c) [Y] invoked [Z’'s] alleged failures to remedy Defaults in accordance with the Remedial Plan Process in the Termination Letter in circumstances where [Y] had:
(i) Abused the Remedial Plan process;
(ii) Required [Z] to perform the Agreement after [Y] had rejected [Z’'s] Second Remedial Plan, thereby losing the right to terminate for [Z’'s] failure to remedy alleged Defaults in accordance with the Remedial Land Process,
(iii) Unfairly keeping [Z] in a contractual limbo for six months (although three months was subject to a standstill) during which time [Z] continued to perform under the CAP agreement; and
(d) [Y] invoked alleged Service Management failures as grounds for termination of the Agreement in circumstances in which:
(i) At least 6 of the alleged Service Management Failures did not occur and the Service Credit Cap limits giving rise to termination rights have not been exceeded (i.e. there had been no material Default);
(ii) Even if such events had occurred, they were merely ""bedding-in issues, the last of which took place 6 months prior to [Y’'s] termination of the CAP agreement”"; and
(iii) [HS] did not appear to have been advised of the existence of alleged Service Management issues, and was therefore not in a position to consider the reasonableness and proportionality of termination on the basis of Service Management failures.""
“"714…by calculating the percentage of [Z’'s] costs incurred on the whole project that had been recovered and applying the unrecovered percentage to the cost of the assets transferred to [Y]. Thus [Z] maintains that it incurred costs totalling £413,021,490. It has been paid £141,598,315 and has therefore recovered 34.3% of its costs; 65.7% are unrecovered.
715. [A witness] lists the assets included in the Asset Register and the costs allocated to those assets…He identifies the sum of £191,753,736 as attributable to the assets that were…transferred. As he explains, the assets comprise not merely hardware, software and such like, but ""[a]ll of [Z’'s] cost base (and its subcontractor costs) [that were] involved (directly or indirectly) in the provision of these Assets.
716. On the basis that the cost of the transferred assets is £191,753,736 and [Z] has recovered 34.3% of these costs through payments from Y, the remaining balance, 65.7% of £191,753,736, results in [Z’'s] claim of £126,013,801…
717. It is therefore apparent that [Z] has not followed the contractual route to arrive at Unrecovered Costs and there is reason to believe that sum claimed would not approximate with the Unrecovered Costs, calculated in accordance with Agreement.”"
“"719. That is not, of course, fatal to [Z’'s] claim. Since the tribunal has found that [Y] repudiated the contract, [Z] was released from further performance of its obligations under the Agreement, including the performance of the Exit Management provisions. As recorded above, [Z] reserved its position and therefore in transferring the assets at the request of [Y], [Z] was conferring a benefit on [Y]. The entitlement to a remedy arises from the fact that [Y] purported to exercise a right which it knew (and accepts) would entitle [Z] to additional payment, on the assumption that it had properly terminated the Agreement. However [Y] also knew that [Z] disputed the termination and that it contended that [Y] had repudiated the Agreement. Thus, as recorded above, [Z] reserved its position when agreeing to transfer the assets which are the subject of [Z’'s] Damages Claim A4. In the tribunal''s view, in these circumstances, were [Y] to retain the benefit of the Transferred Assets without payment to [Z] , this would give rise to unjust enrichment. Z is accordingly entitled to maintain a claim in unjust enrichment.""
“"The state of the evidence is not satisfactory; in particular, there is considerable uncertainty as to the sums which had already been paid in relation to the transferred Assets. However since the tribunal is attempting to assess the value of the unjust enrichment, it can only proceed on the basis of the cost to [Z] of producing the relevant assets, les the sums paid. In this connection the costs forecast by the RFM is strictly irrelevant. Nevertheless the tribunal notes two matters:
(a) It is common ground the payment structure under the Agreement was ""sculpted”" so that [Z] would be operating at a loss during the earlier part of the project. It is therefore to be expected that the costs [Z] incurred would not be matched by the payments made under the Agreement by the Authority…”"
“"725. One further concern is that [Z’'s] calculations do not seek to allocate any of the payments made by [Y] [for] the transferred assets; its calculation is simply based on an average…
726...[Y] acknowledges that [Z’'s] “"claim for Transferred Assets is not included in its primary A1 counterclaim, as that claim already includes all of the costs that [Z] has incurred in connection with the Agreement."" Nonetheless, the tribunal has considered whether the capped amount to be awarded in relation to [Z’'s] A1(i) claim must necessarily include some portion of the costs incurred to produce the Transferred Assets….The tribunal has not been assisted by either party in relation to potential overlap, but by a majority determine that if there was any such overlap the onus would have been on [Y] to show it and it has not endeavoured to do so in any of its submissions.
727. Having regard to all these submissions, the tribunal finds that, on the balance of probabilities, Z’'s calculations are broadly correct and the tribunal proposes to adopt them in its valuation of [Z’'s] Claim A4 on the basis that they fairly reflect the net value of the Transferred Assets, the benefit of which [Y] has taken.
728. Thus the tribunal accepts that the cost to [Z] of producing the assets which were transferred to [Y] was £191,753,736 and that it had already been paid 34.28% of its costs by the date of termination, leaving a net claim of £126,013,801.""
The tribunal declined to add the 15% profit uplift and by a majority at Paragraph 730 awarded the sum of £126,013,801 as damages for Claim A4.
The Law
“"(1) A party to arbitral proceedings may…apply to the court challenging an award in the proceedings on the ground of serious irregularity affecting the tribunal, the proceedings or the award…
(2) Serious irregularity means an irregularity of one or more of the following kinds which the court considers has caused or will cause substantial injustice to the applicant—
…(d) failure by the tribunal to deal with all the issues that were put to it;
(3) If there is shown to be serious irregularity affecting the tribunal, the proceedings or the award, the court may—
(a) remit the award to the tribunal, in whole or in part, for reconsideration,
(b) set the award aside in whole or in part, or
(c) declare the award to be of no effect, in whole or in part.
The court shall not exercise its power to set aside or to declare an award to be of no effect, in whole or in part, unless it is satisfied that it would be inappropriate to remit the matters in question to the tribunal for reconsideration.”"
(a) Section 68 reflects ""the internationally accepted view that the Court should be able to correct serious failures to comply with the ""due process"" of arbitral proceedings: cf art 34 of the Model Law."" (see Lesotho Highlands Development Authority v Impregilo SpA [2005] UKHL 43, Paragraph 27); relief under Section 68 will be appropriate only where the tribunal has gone so wrong in the conduct of the arbitration that ""justice calls out for it to be corrected."" (ibid).
(b) The test will not be applied by reference to what would have happened if the matter had been litigated (see ABB v Hochtief Airport [2006] 2 Lloyd’'s Rep 1, paragraph 18).
(c) The serious irregularity requirement sets a ""high threshold"" and the requirement that the serious irregularity has caused or will cause substantial injustice to the applicant is designed to eliminate technical and unmeritorious challenges (Lesotho, paragraph 28).
(d) The focus of the enquiry under Section 68 is due process and not the correctness of the Tribunal’'s decision (Sonatrach v Statoil Natural Gas [2014] 2 Lloyd’'s Rep 252 paragraph 11).
(e) Section 68 should not be used to circumvent the prohibition or limitations on appeals on law or of appeals on points of fact (see, for example, Magdalena Oldendorff [2008] 1 Lloyd''s Rep 7, Paragraph 38, and Sonatrach Paragraph 45).
(f) Whilst arbitrators should deal at least concisely with all essential issues (Ascot Commodies NV v Olam International Ltd [2002] CLC 277 Toulson J at 284D), courts should strive to uphold arbitration awards (Zermalt Holdings SA v and Nu Life Upholstery Repairs Ltd [1985] 2 EGLR 14 at page 15, Bingham J quoted with approval in 2005 in the Fidelity case [2005] 2 Lloyds Rep 508 paragraph 2) and should not approach awards “"with a meticulous legal eye endeavouring to pick holes, inconsistencies and faults on awards with the objective of upsetting or frustrating the process of arbitration"".
(g) As to Section 68(2)(d):
(i) There must be a ""failure by the tribunal to deal"" with all of the ""issues"" that were “"put”" to it.
(ii) There is a distinction to be drawn between “"issues”" on the one hand and “"arguments”", “"points”", “"lines of reasoning”" or “"steps”" in an argument, although it can be difficult to decide quite where the line demarking issues from arguments falls. However, the authorities demonstrate a consistent concern that this question is approached so as to maintain a “"high threshold”" that has been said to be required for establishing a serious irregularity (Petrochemical Industries v Dow [2012] 2 Lloyd’'s Rep 691 paragraph 15; Primera v Jiangsu [2014] 1 Lloyd’'s Rep 255 paragraph 7).
(iii) While there is no expressed statutory requirement that the Section 68(2)(d) issue must be “"essential”", “"key”" or “"crucial”", a matter will constitute an “"issue”" where the whole of the applicant’'s claim could have depended upon how it was resolved, such that “"fairness demanded”" that the question be dealt with (Petrochemical Industries at paragraph 21).
(iv) However, there will be a failure to deal with an “"issue”" where the determination of that “"issue”" is essential to the decision reached in the award (World Trade Corporation v C Czarnikow Sugar Ltd [2005] 1 Lloyd’'s Rep 422 at paragraph 16). An essential issue arises in this context where the decision cannot be justified as a particular key issue has not been decided which is critical to the result and there has not been a decision on all the issues necessary to resolve the dispute or disputes (Weldon Plan Ltd v The Commission for the New Towns [2000] BLR 496 at paragraph 21).
(v) The issue must have been put to the tribunal as an issue and in the same terms as is complained about in the Section 68(2) application (Primera at paragraphs 12 and 17).
(vi) If the tribunal has dealt with the issue in any way, Section 68(2)(d) is inapplicable and that is the end of the enquiry (Primera at paragraphs 40-1); it does not matter for the purposes of Section 68(2)(d) that the tribunal has dealt with it well, badly or indifferently.
(vii) It matters not that the tribunal might have done things differently or expressed its conclusions on the essential issues at greater length (Latvian Shipping v Russian People’'s Insurance Co [2012] 2 Lloyd’'s Rep 181, paragraph 30).
(viii) A failure to provide any or any sufficient reasons for the decision is not the same as failing to deal with an issue (Fidelity Management v Myriad International [2005] 2 Lloyd’'s Rep 508, paragraph 10, World Trade Corporation, paragraph 19). A failure by a tribunal to set out each step by which they reach its conclusion or deal with each point made by a party is not a failure to deal with an issue that was put to it (Hussman v Al Ameen [2000] 2 Lloyds Rep 83).
(ix) There is not a failure to deal with an issue where arbitrators have misdirected themselves on the facts or drew from the primary facts unjustified inferences (World Trade Corporation at paragraph 45). The fact that the reasoning is wrong does not as such ground a complaint under Section 68(2)(d) (Petro Ranger [2001] 2 Lloyd’'s Rep 348, Atkins v Sec of State for Transport [2013] EWHC 139 (TCC), paragraph 24).
(x) A tribunal does not fail to deal with issues if it does not answer every question that qualifies as an “"issue”". It can “"deal with”" an issue where that issue does not arise in view of its decisions on the facts or its legal conclusions. A tribunal may deal with an issue by so deciding a logically anterior point such that the other issue does not arise (Petrochemical Industries at paragraph 27. If the tribunal decides all those issues put to it that were essential to be dealt with for the tribunal to come fairly to its decision on the dispute or disputes between the parties, it will have dealt with all the issues (Buyuk Camlica Shipping Trading & Industry Co Inc v Progress Bulk Carriers Ltd [2010] EWHC 442 (Comm), paragraph 30).
(xi) It is up to the tribunal how to structure an award and how to address the essential issues; if the issue does not arise because of the route the tribunal has followed for the purposes of arriving at its conclusion, Section 68(2)(d) will not be engaged. However, if the issue does arise by virtue of the route the Tribunal has followed for the purposes of arriving at its conclusion, Section 68(2)(d) will be engaged.
(xii) Whether there has been a failure by the tribunal to deal with an essential issue involves a matter of a fair, commercial and commonsense reading (as opposed to a hypercritical or excessively syntactical reading) of the award in question in the factual context of what was argued or put to the tribunal by the parties (and where appropriate the evidence) (Ascot Commodities v Olam [2002] CLC 277 and Atkins, paragraph 36). The Court can consider the pleadings and the written and oral submissions of the parties to the tribunal in this regard.
(h) In relation to the requirement for substantial injustice to have arisen, this is to eliminate technical and unmeritorious challenges (Lesotho, paragraph 28). It is inherently likely that substantial injustice would have occurred if the tribunal has failed to deal with essential issues (Ascot, 284H-285A).
(i) For the purposes of meeting the “"substantial injustice”" test, an applicant need not show that it would have succeeded on the issue with which the tribunal failed to deal or that the tribunal would have reached a conclusion favourable to him; it necessary only for him to show that (i) his position was “"reasonably arguable”", and (ii) had the tribunal found in his favour, the tribunal might well have reached a different conclusion in its award (Vee Networks Limited v Econet Wireless International [2005] 1 Lloyd’'s Rep 192, paragraph 40).
(h) The substantial injustice requirement will not be met in the event that, even if the applicant had succeeded on the issue with which the tribunal failed to deal, the Court is satisfied that the result of the arbitration would have been the same by reason of other of the tribunal’'s findings not the subject of the challenge.
The Challenges
“"3.1 the legal consequences of the fact that [Z] did not comply with the contract provisions, as it was required by the [Agreement] to do, in order to be entitled to contend that failure to achieve contractual Milestones was other than the sole responsibility of [Z]…and
3.2 although it is common ground that the Tribunal had to judge the reasonableness and proportionality of the termination for cause pursuant to Clause 69.1.2(i) the tribunal failed to make any assessment of the nature and seriousness of any relevant Default(s) on the part of [Z] which prima facie entitled a termination for cause, in order to consider whether, in light of the same, it was objectively reasonable and proportionate to terminate the Agreement.”"
“"4.1 that the calculation of compensation should follow the method agreed by the parties in accordance with express provisions;
4.2 that the assessment of compensation should not exceed the amount that would have been recoverable had the agreement been performed according to its terms.
4.3 that [Z] should not be permitted to recover sums on a global basis without any consideration of its own actual or possible breaches of contract.""
The Liability Challenges
“"The tribunal is expressly not finding that a full and proper consideration of [Z’'s] complaints against [Y] in June and July 2010 would have necessarily caused [HS] not to decide on termination for cause. It is the tribunal’'s finding that [HS] was not, in fact, fully or even adequately informed of [Y’'s] possible complicity in the Programme delays on which [HS], like MPRG, intended to rely for termination. She was not, therefore, able to do what Clause 69.1.2 (i) required. What may have seemed reasonable to [HS] on 7 and 8 July was deficient because of her limited insight into the history of the Agreement and the possible causes of delay.""
At first blush, Z’'s argument (that the tribunal was there making it clear that this was an important failure of the process and therefore in effect leading to non-compliance with the condition precedent Process Requirements) is not unattractive. However, the tribunal makes much of the fact that Z was alleging significant contributions to the delays by Y (see for instance Paragraph 410 of the award) but also of the fact that reports on submissions to HS consistently avoided any suggestion of Y either causing or contributing to the delays (see for instance Paragraph 412). The tribunal does not however consider whether it was factually justified for those making submissions to HS not suggesting that Y caused or contributed to delays. Put another way, the tribunal attributes a failure to comply with the conditions precedent to a failure to address possible (and one presumes something more than fanciful) contributions to causing delay by Y, primarily by employees or other agencies, but it does not consider what might be considered to be a very obvious material issue, which was Y’'s case that Z was wholly or substantially responsible for all the delay. Put yet a third way but rhetorically: could HS or those advising HS be criticised as not complying with the Process Requirements if all the delay was in fact caused and contributed to only by Z?
The Quantum Challenges
“"…there can also be no justification, even if a restitutionary remedy is available, for recovery in excess of the contract limit. Such recovery would itself be unjust since it would put the innocent party in a better position than he would have been in if the contract had been fulfilled. In deciding any quantum meruit regard must be had to contract as a guide to value put upon the services and also to ensure justice between the parties.""
This substantive argument is one well-known in the TCC (and indeed other courts) to the effect that, if the services or thing provided by a supplier is something which was to be supplied under a contract prices and values for which had been agreed, but the contract for one reason or another is not or is no longer enforceable, then the quantum meruit or reasonable price is often to be determined by reference to what the parties had otherwise agreed.
“"What monetary award (if any) is [Z] entitled to either on the basis of (i) the provisions of the Agreement; or (ii) [Y’'s] alleged unjust enrichment, representing the value of the Transferred Assets that were transferred… at [Y’'s] request following termination of the Agreement?""
(a) The issue was very broadly defined in the list of issues actually annexed to the award (see above).
(b) It is clear that Z’'s approach through its evidence on costs was based on the assumption that the delay, disruption and inefficiency were not the fault and responsibility of Z. For instance, Mr Boulton, Z’'s quantum expert in his First Report (Volume 1 Paragraph 2.4) said that he had ""assumed that Z’'s case that [others including Y] were responsible for the majority of delays and problems on the programme is correct"". He was later to say in the Second Joint Quantum Expert report (Paragraph 5.10) that it was for the tribunal to determine Z’'s case and evidence ""that the wrongful acts or omissions of [Y] caused delay and additional costs for [Z] and this eroded the margin that [Z] would otherwise have achieved."" Mr Quinn, a witness called by Z who had prepared Z’'s claims, under cross-examination said (or possibly under questioning from the tribunal) that it would be a ""very, very difficult, if not impossible task"" to assess the financial effect of individual the faults or delays on the part of Z"" and that he had not done that exercise (Day 40 Transcript, page 11).
(c) It was thus clear that, generically at least, Y was raising before the arbitrators the unsatisfactory nature of the cost exercise in not addressing the extent to which Z was responsible for the delay, disruption and inefficiency which had occurred.
(d) The real argument comes down to an even narrower point, namely whether the various points about whether any cost-based claim should have taken into account the delays, disruptions and inefficiencies on the part of Z, were or were sufficiently clearly related by Y to the Transferred Assets Claim, A4. It seems to be accepted at the very least that they were raised in relation to Claim A1, albeit that in the result the arbitrators felt that it was unnecessary to address these points because, at least in relation to Claim A1, there had apparently been acceptance by Y’'s expert that at least the amount of the contractual cap was due (Paragraph 707).
(e) One therefore needs to consider whether the issue was sufficiently raised in relation to Claim A4. It is abundantly clear from the award itself that there was a close correlation between the A1 and A4 Claims because both were based on overall cost and an analysis of what costs had not been recovered by Z from Y to date. That can be seen by comparison of what the arbitrators say between Paragraph 694 and 708 in relation to Claim A1 and what they say about Claim A4.
(f) Y’'s Statement of Reply and Defence to Counterclaim pleads:
(i) At Paragraph 4 (in its Overview) that Z seeks to claim ""on the basis that it was entitled to claim all of the costs incurred…[and] makes no attempt to identify the causal consequences of any matters for which it blames [Z] [but instead] its Claim is put forward on a wholly global basis… (Paragraph 4.1).
(ii) Under a Heading ""[Z’'s] ""Global"" or ""Total Costs"" Claim, Y asserted that Z did not ""attempt to…apportion the loss allegedly suffered between the Delaying events"" and as a result its claim was a ""global"" or a ""total cost"" claim in the sense that the global sum has been put forward as the measure of damage resulting from more than one causative event which are said to be the responsibility of [Y] and that the ""events have been ""rolled up"" with no attempt to apportion the loss between them"" (Paragraph 7.1 and 7.2).
(iii) At Paragraph 65.74.3, specifically in relation to Claim A4, Y pleaded that it denied that “"[Z] is entitled to recover a greater sum as an award for unjust enrichment than it would have recovered pursuant to the provisions of the Agreements or that it was reasonable for [Z] to have incurred costs in excess of those recoverable under the Agreement.""
(g) In its (extensive) Closing Submissions, Y addressed quantum in some detail (with particular detail provided in Appendix E). At Paragraph 43.19, albeit addressing Claim A1, it said:
“"[Z’'s] updated expectation loss claim [A1] ignores the fixed-price nature of the Agreement and is based upon unsupported an unstated assumptions. Instead of attempting to properly assess the position it would have been in if termination had not occurred, [Z] simply claims all its costs on a global basis (whether recoverable under the Agreement or not) and an assumed level of profit. [Z] justifies its approach on the entirely unrealistic assumption that [Y] was responsible for the preponderance of ""delays and problems"" encountered and that these were the sole cause of [Z’'s] failure to achieve the profit that it had hoped for.""
(h) In Appendix E, Y addressed the quantum of Z’'s Counterclaim in some detail. At Paragraph 16, it addresses Z’'s A1 Claim asserting that it was a ""global claim"" about which there were legal objections which they had addressed in Appendix C which dealt with delay (C Paragraph 16.4 and 16.5). At Paragraph 16.7 Y says that the claim ""makes no attempt to take into account the history of the performance of the parties prior to termination, does not attempt to assess any losses allegedly caused by any individual [Y] breaches but instead makes a global claim"". It is clear that, in relation to Claim A1 at least, Y was challenging the quantum based on cost on grounds which included that it was objectionable on the basis that it was a global claim, which amongst other things, included costs which were attributable to Z’'s own failings.
(i) In Appendix E, Y addressed the Claim A3 for unjust enrichment saying that it was unjustified as being ""either legally misconceived or unsupported by the evidence"" and ""an attempt…to avoid the consequences of the negotiated terms of the Agreement it freely entered into”" (at paragraph 19.3).
(j) At Paragraph 20, Y made submissions about Claim A4 in relation to Transferred Assets. It refers to Mr Boulton’'s assumption in his costings that Y was responsible for the problems and delays (Paragraph 20.5). It sets out how Z calculates its claim (Paragraph 20.10) with a starting point of the total costs incurred by Z at the Termination Date, less what sums had been paid at that time by Y and in effect criticise it as being a claim ""on a global basis"" (Paragraph 20.13). Y goes on to criticise this approach because it ""fails to identify how the Unrecovered Costs it claims are ""in respect of the Assets Transferred"""" (Paragraph 20.14).
(k) It follows that it was or should have been clear to the arbitrators that Claim A4 was being challenged as a ""global cost”" claim which was said to be unjustified and unsound in effect at least in large part because it assumed, wrongly, that all the problems of delay, disruption and inefficiency were attributable to Y. I say ""wrongly"" because there was a mass of evidence from both sides as to the fault and responsibility for the delay, disruption and inefficiency which had occurred up to the date of termination, with both parties blaming the other. That was something which the arbitrators decided either consciously or subconsciously (in relation to this Claim A4) that it was unnecessary to bear in mind.
Decision and Consequences