BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Severfield (UK) Ltd v Duro Felguera UK Ltd [2015] EWHC 3352 (TCC) (24 November 2015) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2015/3352.html Cite as: [2015] EWHC 3352 (TCC), 163 Con LR 235 |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Rolls Building, London, EC4A 1NL |
||
B e f o r e :
____________________
SEVERFIELD (UK) LIMITED |
Claimant |
|
- and - |
||
DURO FELGUERA UK LIMITED |
Defendant |
____________________
Mr Adrian Williamson QC (instructed by Freeths LLP) for the Defendant
Hearing date: 10 November 2015
____________________
Crown Copyright ©
The Hon. Mr Justice Coulson:
1. INTRODUCTION
2. FACTUAL BACKGROUND
"9. PRICE
9.1 The Initial Price of this Contract Is 5,221,145.00 GBP (FIVE MILLION TWO HUNDRED TWENTYONE THOUSAND ONE HUNDRED FORTY FIVE GBP). The final Price of this Contract will be the result of applying the measurements executed by BUYER to the unitary prices indicated In Appendix II. However once the ceiling limit represented by the initial price is reached, a change order will be needed for CONTRACTOR to continue with the performance of the Works and submit further Invoices.
NOTES:
- The final Price is based on the result of the measurements executed about constructive drawing including the weights of connections and bolts.
- The previous unitary Prices should he applicable to the extensions of the Scope of this Contract and they will be based on toe measurements about drawing of Works really executed and agreed with the BUYER. Including the weights of connections and bolts.
9.2 Unless otherwise expressly stated In this Contract, the 'unitary prices are fixed and not subject to modification and include, among others, all the services, direct and indirect costs, industrial benefit, supplies of material, transport to the delivery she indicated in the Contract, packing, travel of the CONTRACTOR's own personnel, use of any equipment necessary for the completion of the Works in accordance with this Contract, including, without limitation, manufacturing and construction equipment both in the workshop and on Site, all the necessary insurances, rights and expenses, as well as all the taxes, duties, tariffs, charges and levies of any kind, or the timely and satisfactory execution of the Scope by the CONTRACTOR, with the sole exception of VAT. Consequently, the CONTRACTOR assumes the whole economic risk with regard to, but not limited to, any modification to the cost of the services and materials, construction equipment and goods, transport, duties, taxes, charges, social insurance, salary reviews or to any other aspect that affects the Scope and that may occur for any reason, unless expressly stipulated otherwise in the Contract.
If in the execution of the Works CONTRACTOR incurs direct loss and/or expenses for which he would not be reimbursed by a payment under any other provision of this Contract because the regular progress of the Works or any part of them has been materially affected by any act of default by the BUYER, the CONTRACTOR may submit a claim to the BUYER. If the CONTRACTOR makes such claim, save where this Contract excludes the operation of this clause, any amounts agreed by the parties of (the direct loss and/or expense thereby caused to the CONTRACTOR shall be taken into account in the calculation of the final Price or shall be recoverable from the BUYER as a debt; provided always that the CONTRACTOR shall:
- Make the claim in accordance to clause 31,
- In support of its claim submit to the BUYER upon request such information as is reasonably necessary to show that the regular progress has been affected.
- Submit to the BUYER such details of the loss and/or expense as the BUYER reasonably requests to enable that direct toss and/or expense to be ascertained and agreed.
…
11. FORM OF PAYMENT AND INVOICING
11.1 The Scope performed by the CONTRACTOR shall be invoiced in the following way:
Milestone | % of Price | Description |
1 |
100% |
By monthly certifications approved by BUYER. With the first invoice CONTRACTOR shall provide BUYER with the retention bond stated in clause 10, and where a certification includes supply of materials held off site the corresponding invoice shall be submitted along with a transfer of ownership as per Appendix VIII |
11.2 One (1) original of all the invoices shall be sent to the BUYER's domicile indicated in this Contract, the invoices shall indicate the origin of the supply and the operation carried out to complete the same. The CONTRACTOR shall invoice independently the services performed as part of the Scope described in the present Contract. Payment shall be made on days 5, 15 and 25 of each month by Bank Transfer at 30 days from the reception of the invoice. No payment will be made in case of any nonconformity of the invoice.
11.3 Payments to be made by the BUYER to the CONTRACTOR in accordance with this Contract shall be subject to the CONTRACTOR complying with all its obligations according to the Contract. Furthermore, such payments shall in no case be deemed as the approval and acceptance of the Scope. Therefore, any payments to the CONTRACTOR of the invoices submitted merely constitute advanced payments of the Contract Price, the payment of which is conditional upon the final demonstration of the fitness of the Scope for the purpose foreseen in the Contract.
11.4 The BUYER is entitled to set off any payments owed to the CONTRACTOR with any amount owed by the CONTRACTOR to the BUYER under this Contract.
11.5 All Invoices must compulsorily make express mention of the Contract number, otherwise they will be returned to the CONTRACTOR.
Contract Nr. 8370100105
Internal Cost Code: 8370001-001/5010
The invoices shall be made out and sent to:
DURO FELGUERA UK Ltd
Carrington CCGT Construction Site
Manchester Road 132 – M31 4AY Manchester – UK
England company number: 7889106
VAT No. GB-137233135
For the attention of Ms. Gema Santos
11.6 With the issuance of the first invoice CONTRACTOR shall submit the following information:
- Their names or the name of their business or company.
- Their UTR,
- The partner's name if they're a partnership.
- Their National Insurance number (if you know it) if they're a sole trader.
- The partner's UTR or National Insurance number If they're a partnership (or, if the partner's a company, that company's UTR or company registration number).
- Their company registration number if they're a company.
The failure of the CONTRACTOR to comply with the above mentioned obligation shall entitle the BUYER to withhold any payment that may be owed to the CONTRACTOR until the information has been effectively and correctly delivered."
3. RELEVANT LEGAL PRINCIPLES
"104. — Construction contracts.
(1) In this Part a "construction contract" means an agreement with a person for any of the following—
(a) the carrying out of construction operations;
(b) arranging for the carrying out of construction operations by others, whether under sub-contract to him or otherwise;
(c) providing his own labour, or the labour of others, for the carrying out of construction operations.
(2) References in this Part to a construction contract include an agreement—
(a) to do architectural, design, or surveying work, or
(b) to provide advice on building, engineering, interior or exterior decoration or on the laying-out of landscape,
in relation to construction operations…
(5) Where an agreement relates to construction operations and other matters, this Part applies to it only so far as it relates to construction operations. An agreement relates to construction operations so far as it makes provision of any kind within subsection (1) or (2).
105. — Meaning of "construction operations".
(1) In this Part "construction operations" means, subject as follows, operations of any of the following descriptions—
(a) construction, alteration, repair, maintenance, extension, demolition or dismantling of buildings, or structures forming, or to form, part of the land (whether permanent or not);
(b) construction, alteration, repair, maintenance, extension, demolition or dismantling of any works forming, or to form, part of the land, including (without prejudice to the foregoing) walls, roadworks, power-lines, [electronic communications apparatus], aircraft runways, docks and harbours, railways, inland waterways, pipe-lines, reservoirs, water-mains, wells, sewers, industrial plant and installations for purposes of land drainage, coast protection or defence;
(c) installation in any building or structure of fittings forming part of the land, including (without prejudice to the foregoing) systems of heating, lighting, air-conditioning, ventilation, power supply, drainage, sanitation, water supply or fire protection, or security or communications systems;
(d) external or internal cleaning of buildings and structures, so far as carried out in the course of their construction, alteration, repair, extension or restoration;
(e) operations which form an integral part of, or are preparatory to, or are for rendering complete, such operations as are previously described in this subsection, including site clearance, earth-moving, excavation, tunnelling and boring, laying of foundations, erection, maintenance or dismantling of scaffolding, site restoration, landscaping and the provision of roadways and other access works;
(f) painting or decorating the internal or external surfaces of any building or structure.
(2) The following operations are not construction operations within the meaning of this Part—
(a) drilling for, or extraction of, oil or natural gas;
(b) extraction (whether by underground or surface working) of minerals; tunnelling or boring, or construction of underground works, for this purpose;
(c) assembly, installation or demolition of plant or machinery, or erection or demolition of steelwork for the purposes of supporting or providing access to plant or machinery, on a site where the primary activity is—
(i) nuclear processing, power generation, or water or effluent treatment, or
(ii) the production, transmission, processing or bulk storage (other than warehousing) of chemicals, pharmaceuticals, oil, gas, steel or food and drink;
(d) manufacture or delivery to site of—
(i) building or engineering components or equipment,
(ii) materials, plant or machinery, or
(iii) components for systems of heating, lighting, air-conditioning, ventilation, power supply, drainage, sanitation, water supply or fire protection, or for security or communications systems,
except under a contract which also provides for their installation;
(e) the making, installation and repair of artistic works, being sculptures, murals and other works which are wholly artistic in nature."
"63. It follows that the statute contemplated a position where one agreement related to both construction operations under section 105(1) and operations which were excluded by section 105(2).
64. It also follows that the right to refer disputes to adjudication under section 108, the entitlement to stage payments under section 109, the provisions as to dates of payment under section 110, the provisions as to notice of intention to withhold payment under section 111, the right to suspend performance for non payment under Section 112 and the prohibition of conditional payment provisions under section 113 will only apply to the Subcontract in this case, insofar as the Subcontract relates to construction operations."
"109 — Entitlement to stage payments.
(1) A party to a construction contract is entitled to payment by instalments, stage payments or other periodic payments for any work under the contract unless—
(a) it is specified in the contract that the duration of the work is to be less than 45 days, or
(b) it is agreed between the parties that the duration of the work is estimated to be less than 45 days.
(2) The parties are free to agree the amounts of the payments and the intervals at which, or circumstances in which, they become due.
(3) In the absence of such agreement, the relevant provisions of the Scheme for Construction Contracts apply…
110A Payment notices: contractual requirements
(1) A construction contract shall, in relation to every payment provided for by the contract—
(a) require the payer or a specified person to give a notice complying with subsection (2) to the payee not later than five days after the payment due date, or
(b) require the payee to give a notice complying with subsection (3) to the payer or a specified person not later than five days after the payment due date.
(2) A notice complies with this subsection if it specifies—
(a) in a case where the notice is given by the payer—
(i) the sum that the payer considers to be or to have been due at the payment due date in respect of the payment, and
(ii) the basis on which that sum is calculated;
(b) in a case where the notice is given by a specified person—
(i) the sum that the payer or the specified person considers to be or to have been due at the payment due date in respect of the payment, and
(ii) the basis on which that sum is calculated.
(3) A notice complies with this subsection if it specifies—
(a) the sum that the payee considers to be or to have been due at the payment due date in respect of the payment, and
(b) the basis on which that sum is calculated…
(5) If or to the extent that a contract does not comply with subsection (1), the relevant provisions of the Scheme for Construction Contracts apply.
(6) In this and the following sections, in relation to any payment provided for by a construction contract—
"payee" means the person to whom the payment is due;
"payer" means the person from whom the payment is due;
"payment due date" means the date provided for by the contract as the date on which the payment is due;
"specified person" means a person specified in or determined in accordance with the provisions of the contract.
110B Payment notices: payee's notice in default of payer's notice
(1) This section applies in a case where, in relation to any payment provided for by a construction contract—
(a) the contract requires the payer or a specified person to give the payee a notice complying with section 110A(2) not later than five days after the payment due date, but
(b) notice is not given as so required.
(2) Subject to subsection (4), the payee may give to the payer a notice complying with section 110A(3) at any time after the date on which the notice referred to in subsection (1)(a) was required by the contract to be given.
(3) Where pursuant to subsection (2) the payee gives a notice complying with section 110A(3), the final date for payment of the sum specified in the notice shall for all purposes be regarded as postponed by the same number of days as the number of days after the date referred to in subsection (2) that the notice was given.
(4) If—
(a) the contract permits or requires the payee, before the date on which the notice referred to in subsection (1)(a) is required by the contract to be given, to notify the payer or a specified person of—
(i) the sum that the payee considers will become due on the payment due date in respect of the payment, and
(ii) the basis on which that sum is calculated, and
(b) the payee gives such notification in accordance with the contract,
that notification is to be regarded as a notice complying with section 110A(3) given pursuant to subsection (2) (and the payee may not give another such notice pursuant to that subsection).
111 Requirement to pay notified sum
(1) Subject as follows, where a payment is provided for by a construction contract, the payer must pay the notified sum (to the extent not already paid) on or before the final date for payment.
(2) For the purposes of this section, the "notified sum" in relation to any payment provided for by a construction contract means—
(a) in a case where a notice complying with section 110A(2) has been given pursuant to and in accordance with a requirement of the contract, the amount specified in that notice;
(b) in a case where a notice complying with section 110A(3) has been given pursuant to and in accordance with a requirement of the contract, the amount specified in that notice;
(c) in a case where a notice complying with section 110A(3) has been given pursuant to and in accordance with section 110B(2), the amount specified in that notice.
(3) The payer or a specified person may in accordance with this section give to the payee a notice of the payer's intention to pay less than the notified sum.
(4) A notice under subsection (3) must specify—
(a) the sum that the payer considers to be due on the date the notice is served, and
(b) the basis on which that sum is calculated.
It is immaterial for the purposes of this subsection that the sum referred to in paragraph (a) or (b) may be zero.
(5) A notice under subsection (3)—
(a) must be given not later than the prescribed period before the final date for payment, and
(b) in a case referred to in subsection (2)(b) or (c), may not be given before the notice by reference to which the notified sum is determined.
(6) Where a notice is given under subsection (3), subsection (1) applies only in respect of the sum specified pursuant to subsection (4)(a).
(7) In subsection (5), "prescribed period" means—
(a) such period as the parties may agree, or
(b) in the absence of such agreement, the period provided by the Scheme for Construction Contracts.
(8) Subsection (9) applies where in respect of a payment—
(a) a notice complying with section 110A(2) has been given pursuant to and in accordance with a requirement of the contract (and no notice under subsection (3) is given), or
(b) a notice under subsection (3) is given in accordance with this section,
but on the matter being referred to adjudication the adjudicator decides that more than the sum specified in the notice should be paid.
(9) In a case where this subsection applies, the decision of the adjudicator referred to in subsection (8) shall be construed as requiring payment of the additional amount not later than—
(a) seven days from the date of the decision, or
(b) the date which apart from the notice would have been the final date for payment,
whichever is the later.
(10) Subsection (1) does not apply in relation to a payment provided for by a construction contract where—
(a) the contract provides that, if the payee becomes insolvent the payer need not pay any sum due in respect of the payment, and
(b) the payee has become insolvent after the prescribed period referred to in subsection (5)(a).
(11) Subsections (2) to (5) of section 113 apply for the purposes of subsection (10) of this section as they apply for the purposes of that section."
(a) In Caledonian Modular Limited v Mar City Developments Limited [2015] EWHC 1855 (TCC), at paragraph 37, I said:
"…if contractors want the benefit of these provisions, they are obliged, in return, to set out their interim payment claims with proper clarity. If the employer is to be put at risk that a failure to serve a payless notice at the appropriate time during the payment period will render him liable in full for the amount claimed, he must be given reasonable notice that the payment period has been triggered in the first place.";
(b) In Henia Investments v Beck Interiors Limited [2015] EWHC 2433 (TCC) Akenhead J said:
"…the document relied upon as an Interim Application … must be in substance, form and intent an Interim Application stating the sum considered by the Contractor as due at the relevant due date and it must be free from ambiguity. In this context, the Interim Application should be considered in the same light as a certificate. If there are to be potentially serious consequences flowing from it being an Interim Application, it must be clear that it is what it purports to be so that the parties know what to do about it and when."
4. ANALYSIS: THE SUM DUE AND THE CLAIM NOW MADE
(a) The payment notice has to set out the sum due;(b) The payment notice has to set out the basis on which that sum is calculated;
(c) The payment notice must be set out with proper clarity and be free from ambiguity (see paragraph 24 above).
5. COUNTERCLAIM
6. ABUSE OF PROCESS
"Right to discontinue claim
38.2
(1) A claimant may discontinue all or part of a claim at any time.
(2) However –
(a) a claimant must obtain the permission of the court if he wishes to discontinue all or part of a claim in relation to which –
(i) the court has granted an interim injunction; or
(ii) any party has given an undertaking to the court;
(b) where the claimant has received an interim payment in relation to a claim (whether voluntarily or pursuant to an order under Part 25), he may discontinue that claim only if –
(i) the defendant who made the interim payment consents in writing; or
(ii) the court gives permission;
(c) where there is more than one claimant, a claimant may not discontinue unless –
(i) every other claimant consents in writing; or
(ii) the court gives permission.
(3) Where there is more than one defendant, the claimant may discontinue all or part of a claim against all or any of the defendants…
38.4
(1) Where the claimant discontinues under rule 38.2(1) the defendant may apply to have the notice of discontinuance set aside.
(2) The defendant may not make an application under this rule more than 28 days after the date when the notice of discontinuance was served on him…
38.7
A claimant who discontinues a claim needs the permission of the court to make another claim against the same defendant if –
(a) he discontinued the claim after the defendant filed a defence; and
(b) the other claim arises out of facts which are the same or substantially the same as those relating to the discontinued claim."
7. CONCLUSIONS