BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> AMD Environmental Ltd v Cumberland Construction Company Ltd [2016] EWHC 285 (TCC) (15 February 2016) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2016/285.html Cite as: 165 Con LR 191, [2016] EWHC 285 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Rolls Building, London, EC4A 1NL |
||
B e f o r e :
____________________
AMD Environmental Ltd |
Claimant |
|
- and - |
||
Cumberland Construction Company Ltd |
Defendant |
____________________
Justin Davis (instructed by Direct Access) for the Defendant
Hearing date: 15 February 2016
____________________
Crown Copyright ©
The Hon. Mr Justice Coulson :
1. INTRODUCTION
(a) The value of the works undertaken by AMD was £464,448.34.(b) Cumberland's payless notice was inadequate and not in accordance with the 1996 Act (as amended by the 2009 Act).
(c) Cumberland was not entitled to set off any contra charges from payments due to AMD in respect of the claim.
(d) Cumberland were required to make payment to AMD in the sum of £77,993.26 plus VAT.
(e) Cumberland were to pay AMD interest in the sum of £2,044.92 up to the date of decision.
(f) Cumberland were to be primarily liable for the adjudicator's fees and expenses.
2. THE JURISDICTIONAL CHALLENGES
3. CRYSTALLISATION
(a) On 7 August 2015, he said that Cumberland "would very much like a construction court case battle with AMD";(b) On 11 August 2015 he said, for the umpteenth time, that AMD owed Cumberland money, and not the other way round.
In my view such language makes it only too clear that, as far as Mr Park was concerned, a dispute had crystallised between the parties, albeit a dispute he was confident of winning. These are not the emails of someone who considers that there was no dispute between the parties because the claim with which he was dealing in such detail was, in truth, nebulous and ill-defined. Accordingly, for all these reasons, I consider that the crystallisation argument is hopeless.
4. FAILURE TO ADDRESS MATTERS IN ISSUE
"22.1 The adjudicator must attempt to answer the question referred to him. The question may consist of a number of separate sub-issues. If the adjudicator has endeavoured generally to address those issues in order to answer the question then, whether right or wrong, his decision is enforceable: see Carillion Construction Ltd v Devonport Royal Dockyard Ltd [2005] EWCA Civ 1358.
22.2 If the adjudicator fails to address the question referred to him because he has taken an erroneously restrictive view of his jurisdiction (and has, for example, failed even to consider the defence to the claim or some fundamental element of it), then that may make his decision unenforceable, either on grounds of jurisdiction or natural justice: see Ballast PLC v The Burrell Co Ltd [2001] BLR 529; Broadwell v k3D [2006] ADJCS04/21; and Thermal Energy Construction Ltd v AE&E Lentjes UK Ltd [2009] EWHC 408.
22.3 However, for that result to obtain, the adjudicator's failure must be deliberate. If there has simply been an inadvertent failure to consider one of a number of issues embraced by the single dispute that the adjudicator has to decide, then such a failure will not ordinarily render the decision unenforceable: see Bouygues (UK) Ltd v Dahl- Jensen (UK) Ltd [2000] BLR 49 and Amec Group v Thames Water Utilities Ltd [2010] EWHC 419 (TCC).
22.4 It goes without saying that any such failure must also be material: see Cantillon v Urvasco and CJP Builders Limited v William Verry Limited [2008] EWHC 2025 (TCC). In other words, the error must be shown to have had a potentially significant effect on the overall result of the adjudication: see Keir Regional Ltd v City and General (Holborn) Ltd [2006] EWHC 848 (TCC)."
"The reports provided regarding the BMS do not identify that the issues have been caused by workmanship issues and/or issues for which AMD is responsible. I therefore do not accept that AMD should not be paid for this work which represents the expenditure of a provisional sum. In terms of quantum, the build up supports the valuation of £34,165.52 and not the revised amount claimed."
5. CONCLUSIONS