BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Synergy Gas Services Ltd v Northern Gas Heating Ltd [2018] EWHC 3060 (TCC) (15 November 2018) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2018/3060.html Cite as: [2018] EWHC 3060 (TCC) |
[New search] [Printable RTF version] [Help]
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (QBD)
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
SYNERGY GAS SERVICES LIMITED |
Claimant |
|
- and - |
||
NORTHERN GAS HEATING LIMITED |
Defendant |
____________________
Mr Rupert J A Beloff (instructed by D&N Solicitors) for the Defendant
Hearing dates: 22nd October and 15th November 2018
Judgment available to the parties on 12th November 2018
____________________
HTML VERSION OF JUDGMENT
Crown Copyright ©
THE DEPUTY JUDGE:
"A dispute has arisen between the parties to the sub-contract concerning the failure of the Responding Party to pay the sum of £84,760.04 to the Referring Party pursuant to the following invoices issued by the Referring Party and less interim payments made by the Responding Party in the sum of £38,068.72."
(i) the Decision was made in breach of natural justice in that the Adjudicator decided the dispute (a) on the basis of matters not raised by the parties (paragraph 4) and (b) without taking into account matters raised by Northern (paragraphs 7, 9 and following); and
(ii) Northern has "a substantial set-off Counterclaim against the Claimant for defective works" (as set out in paragraph 5) which Northern ought to be permitted to pursue to trial in the present proceedings (paragraph 6).
"Further the Defendant contends that, in the light of those other matters raised within the Witness Statement of Nadeem Ahmad dated 1st October 2018 that Defendant has further arguments upon which it would wish to raise in ordinary court proceedings as to why it should not be liable for the sums which the Adjudicator found due to the Claimant. It would be proportionate for those to be dealt with within the current proceedings rather than requiring the Defendant to issue new and separate proceedings. The Defendant avers that this is a compelling reason why matters should be disposed of at trial".
(i) At paragraph 17 of the Decision the Adjudicator identified various issues arising from the dispute. The second issue was identified as follows:
"At clauses 13.2, 13.4, 13.6 and 14.4 of the sub-contract, pre-conditions of Northern's ability to deduct or set off any sum for remedial works?"
(ii) At paragraph 41 of the Decision the Adjudicator found that:
"Clause 14.4 imposes strict obligations on Northern prior to recovery of costs incurred from Synergy in respect of alleged defects which occurred during the defects period".
And paragraph 43:
"In conclusion, clauses 13.2, 13.4 and 13.6 are not relevant to the issue, but at clause 14.4 notice is a pre-condition to deduction or set-off of any sum for remedial works during the defects liability period".
(iii) The Claimant did not specifically advance the argument that notice under clause 14.4 of the sub-contract was a pre-condition to deduction or set-off in its Referral Notice, Reply or Surrejoinder and it was not a point raised by the Adjudicator with the Parties prior to the issue of his Decision.
(iv) In the absence of any oral hearing, the Defendant was therefore denied the opportunity to address this point. It is clear from the paragraphs of the Decisions set out above that this was a point upon which the Adjudicator based his decision, if not "wholly or at least in part".
(v) Since that point was obviously material to the Adjudicator's conclusions and award it is one which he should have raised with the Parties. His failure to do so was therefore a material breach of Natural Justice and the Decision is this unenforceable.
"during the defects liability period, if Northern Gas Heating Limited decides that any work done or materials used by the Installer are defective or not in accordance with the Applicable Rules or the relevant ECO Funding contract, Northern Gas Heating Limited shall notify the Installer that such work or materials have been rejected and specified details of the alleged defect(s). Following that rejection, the Installer shall promptly, and at his own expense, made good the defect(s) to Northern Gas Heating Limited's reasonable satisfaction. If the Installer fails to do so, Northern Gas Heating Limited may employ and pay a Replacement Installer to carry out the work or provide the materials and recover all costs incurred from the Installer".
"The issues are as follows…are clauses 13.2, 13.4, 13.6 and 14.4 of the Sub-contract, pre-conditions of Northern's ability to deduct or set-off any sum for remedial works?"
"I therefore make my DECISION …
Issue 2 A clause 14.4 notice is a pre-condition to deduction or set-off any sum for remedial works during the defects liability period".
He gave his reasoning at paragraph 43 of the Decision.
"Synergy was not provided with the opportunity to inspect/remedy contrary to clause ... 14.4 of the sub-contract. In the circumstances it is denied Northern is entitled to deduct or set-off any sum". And, "Northern has not pleaded nor provided any evidence in response to Synergy's primary position … namely, Synergy was not provided with the opportunity to inspect/remedy the alleged defect in accordance with the sub-contract which is a pre-condition of Northern's ability to deduct or set-off any sum for remedial work.
"The objective which underlies the Act and the statutory scheme requires the courts to respect and enforce the Adjudicator's Decision unless it is plain that the question which he has decided was not the question referred to him or the matter in which he has gone about his task is obviously unfair. It should be only in rare circumstances that the courts will interfere with the Decision of an Adjudicator. The court should give no encouragement to the approach adopted by DML in the present case; which (contrary to DML outline submissions to which we have referred in paragraph 66 of this Judgment) may, indeed aptly be described as "simply scrabbling around to find some argument, however tenuous, to resist payment".
It is only too easy in a complex case for a party who is dissatisfied with the Decision of an Adjudicator to comb through the Adjudicator's reasons and identify points upon which to present a challenge under the labels "excessive jurisdiction" or "breach of natural justice" It must be kept in mind that the majority of the Adjudicators are not choses for their expertise as lawyers… the task of the Adjudicator is not to act as an Arbitrator or Judge… The task of the Adjudicator is to find an interim solution which meets the needs of the case…
"12. It is trite law that adjudication is a speedy process designed only to provide what is called "interim finality" on construction disputes. Parliament intended that the parties should be given a quick answer, and that quick answer should be binding on the parties until the dispute, whatever it may be, is resolved finally either by litigation or arbitration. It has been said in a case concerning what is called a statutory scheme, namely the statutory instrument entitled the Scheme for Construction Contracts (England and Wales) Regulations 1998 (SI 1998/649) by Chadwick LJ in Carillion Construction Limited v. Devonport Royal Dockyard Limited [2006] BLR 15, paragraph 86 that the "need to have the right answer has been subordinated to the need to have the answer quickly". Although made in a case under the Scheme that statement is a wide application to Adjudicators generally, whether under the Scheme or otherwise. Adjudicator's Decisions will be enforced by the Court by Summary Judgment regardless of errors of fact and/or law by the Adjudicator. Aggrieved losing parties can and should comply with the Adjudicator's decision as long as that decision was made by an Adjudicator with jurisdiction over the dispute who has conducted the adjudication fairly and in accordance with the rules of natural justice…
16. It is therefore clear that for breaches of natural justice to be sufficient to justify the Court declining to order Summary Judgment and enforcing an Adjudicator's Decision, they must be the plainest of cases; the adjudication proceedings must have been obviously unfair. Combing through what has occurred, or concentrating on the fine detail of the material before the Adjudicator, to allege a breach of natural justice, will neither be encouraged nor permitted by the Court. Adjudications are conducted very quickly, and this speed is part of the process imposed by Parliament on those who enter into construction contracts. The framework within which Adjudicators have to reach decisions has to be taken into account when complaints are made by losing parties".