BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Level 1 Raised Flooring Ltd v JM Construction (SW) Ltd [2023] EWHC 2841 (TCC) (12 SEptember 2023) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2023/2841.html Cite as: [2023] EWHC 2841 (TCC) |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS IN LIVERPOOL
TECHNOLOGY AND CONSTRUCTION COURT (KBD)
Liverpool L2 2BX |
||
B e f o r e :
____________________
LEVEL 1 RAISED FLOORING LIMITED |
Claimant |
|
- and - |
||
J M CONSTRUCTION (SW) LIMITED |
Defendant |
____________________
Ms Jennie Gillies (instructed by Endeavour Partnership LLP)
for the Defendant
Hearing date: 9th August 2023
____________________
Crown Copyright ©
Introduction – Claimant's application to enforce an adjudication decision
Background and relevant chronology
"(i) What is the value of the work undertaken by (the Defendant) at the date of termination?
(ii) Is (the Claimant) entitled to make a deduction in respect of corrective works and, if so, how much?
(iii) Is (the Claimant) currently entitled to payment and, if so, how much?"
(i) £163,415.79 [95/180];
(ii) £6,618.48 [123/188];
(iii) (a) In principle there is an overpayment of £67,042.84 [124/188];
(b) The termination provisions of the contract do not provide for payment to be made at the time of the adjudication [124/189];
(c) If the termination was valid (in accordance with clauses 6.4, 6.5 or 6.6 of the contract), the Claimant is entitled to follow the procedure set down in clause 6.7, removing any requirement for further payments to be made to the Defendant and preparing an account which itself will determine the total amount due in either direction [125/190];
(d) Consequently, if the termination was valid, "in the absence of an express provision which requires a valuation of the Works and entitles (the Claimant) to obtain payment at the date of the termination, there is no current entitlement to payment", there was no immediate entitlement to payment under the contract and it was not necessary, in consequence, to address the Defendant's points as to cross claims or invalidity of termination [126/190; 126/191; 127/191].
Legal Principles
The Claimant's case
The Defendant's opposition
"it would be contrary to principle and established authority for the court to effectively force a party who has the benefit of an award in its favour as far as a balance being due to it, thereafter to have to commence a further adjudication (to which there is no defence) for the purpose of obtaining an order for payment from the adjudicator before returning to the court if necessary, for further enforcement proceedings."
Discussion
Conclusion
District Judge John Baldwin
12th September 2023
--------------------------------------------------
Note 1 The adjudicator has 16th November 2021 [3/141] [Back]