[New search]
[Printable RTF version]
[Help]
Dubsky v. Drogheda Port Co. [2000] IEHC 166 (22nd February, 2000)
High
Court
Dubsky
v Drogheda Port Company
1999/883
P
22
February 2000
O'SULLIVAN
J:
INTRODUCTION
This
matter comes before me pursuant to an Order of the Supreme Court dated the 17
November, 1999 to the effect that:-
"The
matter be remitted to the High Court to determine the issue whether the
Defendant is providing an alternative compensatory feeding ground in accordance
with the terms of the Order of Mr Justice O'Sullivan herein.
BACKGROUND
The
Order of my own thus referred to is dated the 10 September, 1999 and the
crucial part thereof provides as follows:-
"IT
IS ORDERED that the Defendant its servants and/or agents do mechanically remove
spartina as set out in the said document subject to
1.
The use by the Defendant of existing access for machinery
2.
The Defendant not commencing work until Duchas agree the exact boundaries of
the removal area as set out in the said letter dated the 9 September 1999."
The
letter of the 9 September, 1999 is addressed from Duchas to the Harbour Master
who is employed by the Defendant and where relevant provides as follows:-
"We
have considered the proposal by your company to mechanically remove Spartina as
set out in the attached document.
We
are satisfied with this proposal subject to:
1.
Using existing access for machinery.
2.
To avoid damage to adjoining non-Spartina habitats, work is not to start until
Duchas agree the exact boundaries of the removal area."
The
"attached document" provided as follows:-
"Drogheda
Port Company Capital Dredging Scheme
Restoration
works proposed for Spartina infested north shore
A
full spraying programme, will be initiated in July/August 2000 in accordance
with the Spartina eradication plan and the foreshore licence.
An
area of 10 hectares of Spartina infested foreshore will be mechanically removed
by bulldozer and excavator. The Spartina grass, will be taken off the mud flat
to expose colonised mud flat as well as existing open pockets of mud flat. Only
tracked machines or wide tyred excavators will operate within the polder to
minimise the physical impact on the mud flat area. Only the surface of the mud
flat over spartina colonised areas will be scraped off in the process. This
removal process provides an immediate exposure of mud flat which will be
subject to tidal flushing and further colonisation by macrofauna.
Information
from the base line survey of the north shore indicates a high macrofuuna
availability within the main spartina infested area south of Baltray.
Macrofauna
means biomass in the main spartina infested area south of Baltray is (sic)
typically greater than twice that surveyed in the Stagreenan polder.
The
work of Spartina removal will be supervised by a suitably qualified marine
consultant (Dr Beverly Kelso-Marenco).
The
mechanical removal of Spartina will be undertaken within two weeks and would be
completed within a further three weeks."
The
Defendant has accepted at all times (correctly) that it was obliged to carry
out the foregoing "restoration works" in connection with a dredging scheme of
the estuary of the River Boyne which included the dumping of spoil on a polder
on the south bank of the river known as Stagreenan polder. In making
application for the relevant foreshore licence, the Defendant as part of its
proposal indicated in an accompanying Environmental Impact Statement that it
would ameliorate the environmental damage thus done to the Stagreenan polder by
providing an alternative compensatory feeding ground for displaced birds on the
north polder by removal of some 10 hectares of Spartina infested foreshore
therein. Subsequent consultation with Duchas produced the correspondence quoted
above.
On
the 10 September, 1999 I made the Order referred to following an application by
the Plaintiff for an interlocutory injunction restraining the Defendant from
carrying out any further works on the north polder and directing the Defendant
to reopen sluices so that water which had been excluded could be reintroduced.
On
that application I took the view that the Plaintiff was correct in her
assertion (which was not accepted by the Defendant) to the effect that the
Defendant was obliged to provide the alternative compensatory feeding ground
before the removal of the area in the Stagreenan polder or at least
contemporaneously therewith. It is for this reason that the Order of the 10
September, 1999 is expressed in mandatory terms (the work on the Stagreenan
polder having been already well advanced) and it is also for this reason that
reference is made therein to the agreement of Duchas.
Following
the making of the Order on the 10 September, 1999 work was in fact commenced,
but not within the time stipulated in the Order and, according to the
Plaintiff, in breach thereof in other respects as well.
Following
an attempt between the parties at reaching an agreement, the matter came before
Kelly J on the 22 October, 1999 pursuant to a further Motion seeking
interlocutory relief, the terms of which are set out in an ex tempore ruling
given by Kelly J on the same date. That application sought the prohibition of
further work by the Defendant whether in purported compliance with the Order of
the 10 September or otherwise and a further interlocutory Order, once again
seeking to compel the Defendant to open the controlling sluice and to restore
the tidal inflow to Stagreenan polder.
That
application was refused by Kelly J, and the Plaintiff appealed to the Supreme
Court which on the 17 November, 1999 allowed the appeal in part and directed
the matter to be sent back in the manner to which I have already referred.
PRELIMINARY
POINTS OF CLARIFICATION
(a)
Counsel are agreed that the hearing before me, pursuant to the Supreme Court
Order, is the final determination of the case between the parties, and also
that the matter should proceed on oral evidence with cross-examination in the
usual way supplemented by the evidence already given on Affidavit in the
interlocutory application subject to the exclusion therefrom of any
inadmissible hearsay evidence.
(b)
As to the scope of the issues between the parties, there are two views, the
narrow view and the broad view.
The
narrow view of the question directed in the Order of the Supreme Court (". . .
whether the Defendant is providing an alternative compensatory feeding ground
in accordance with the terms of the said Order . . .") derives from the view
taken thereof by Kelly J in his judgment of the 22 October, 1999 wherein he
said:-
"Nowhere
in the Order of O'Sullivan J does it expressly provide that the work is to be
done to the satisfaction of Duchas but both sides have understood this to be
so. In addition the work was to be supervised by Doctor Beverly Kelso of
Marenco . . . The work is being done under the supervision of the person
nominated by the Court Order, namely Doctor Kelso, and the work has been
carried out to the satisfaction of Duchas, the National Parks and Wildlife
Service . . . (Reference is then made to a letter from Mr John Flynn of Duchas
confirming this) . . .
It
seems to me that in these circumstances the authority which is competent to
evaluate the work being carried out is satisfied with it. It does not appear to
me that I can look behind this expression of satisfaction by Duchas. The
Plaintiff might well have grounds for moving this application if she adduced
evidence to the effect that Duchas was dissatisfied. But I do not think that
the Court would be justified in setting aside the Order of O'Sullivan J unless
it was indicated that Duchas regarded the works being carried out as
substandard . . ."
The
judgment of the Supreme Court was delivered by the then Chief Justice Hamilton
CJ. The Chief Justice refers to the foregoing opinion of Kelly J and whilst it
was held that the learned trial Judge erred in law in relying on the letter
from Duchas in face of the Affidavit of the Plaintiff, the judgment does not
appear to indicate one way or another whether Kelly J's view to the effect that
the authority which is competent to evaluate the work being carried out is
satisfied with it and in the absence of evidence to the contrary (assuming
always that such evidence is appropriately given: that is by way of sworn
evidence as distinct from an exhibited letter) the Court would not be justified
in setting aside the Order of the 10 September, 1999.
The
broader view asserts that the opinion of Duchas, no matter how appropriately
evidenced, cannot take over the Court's function so that the Court must look at
the other ingredients of the Order of the 10 September, or at the very least,
at the reasonableness of the approval by Duchas of the works already done.
If
the narrow view is correct then there is little more to be said, because
evidence was given before me by Mr John Flynn who said that he is the
individual in that service who is charged with supervising the Defendant's
works, he is a Deputy Regional Manager with Duchas stationed in Mullingar and
has been with the service for thirty years. He was aware of the Order of the
Court and together with Doctor Kelso and Martin Donnelly, Harbour Master of the
Defendant, agreed the boundaries of the alternative compensatory feeding ground
(on the 23 September, 1999); agreed the method of carrying out the work
comprising scraping the surface by a digger, minimising sediment removal and
dumping the spoil on a temporary basis on a site near the road to the north. He
paid three visits to the site and as far as he could see work was proceeding
satisfactorily and in compliance with the Order of the Court.
In
cross-examination he accepted that he did not learn the exact terms of the
Court Order until he was in Court on the last day of the hearing before me, he
agreed to a widening of the access from the road to the compensatory site,
pointed out that an inappropriately tracked vehicle was on site on the 12
October and was satisfied that it was replaced with a suitable vehicle
promptly, disagreed that too much soil was removed in the course of scraping
off the Spartina grass and, overall, was satisfied with the works being carried
out by the Defendant.
In
my view it is quite clear that Duchas, in the person of John Flynn (the only
individual in that organisation with the relevant responsibility) is satisfied
with the work and with the boundaries referred to in the Court Order (albeit
that these may not be "exact") and despite other complaints made by the
Plaintiff such as that the work started late.
If,
therefore, the narrow view is the correct one, I would, without more, dismiss
the Plaintiff's application.
The
broader view, derives, I think, not only from the fact that the judgment of the
Supreme Court does not indicate one way or another whether the "narrow view" is
correct, but also from the fact that at page six the learned Chief Justice
indicates that there are a number of issues between the parties when he said:-
".
. . But it has to be accepted that there are disputed issues of fact in this
case, particularly the issue as to whether or not the work being carried out by
the Defendant/Respondent on the north shore is effectively damaging the
environment, damaging the area' s potential compensating feeding ground and as
to whether the work is being properly carried out."
Later,
at page nine, the phraseology which found its way into the formal Order already
cited, is used where the High Court is directed:-
".
. . to determine the issue and this is a fundamental issue to the parties
whether the Defendants are providing an alternative compensatory feeding ground
in accordance with the terms of the Order of Mr Justice O'Sullivan."
SUBMISSIONS
In
the context of this wider approach Mr Gaffney SC for the Plaintiff submitted
that the Defendants were in breach of the Order in that:-
1.
They were in delay (in the manner set out already in the Order of Kelly J, on
the 22 October 1999);
2.
The access had been widened and hard-core laid into the salt marsh;
3.
An incorrect machine had been used for a week (again as instanced in the Order
of Kelly J);
4.
The removal was not confined to the top layer but material was scooped too
deep, and also damage was done by the removal of material from and the dumping
of spoil on the salt marsh as distinct from the mud flat area;
5.
The work was not supervised by Doctor Kelso;
6.
The exact boundaries of the 10 hectare site referred to in the Order were never
agreed with Duchas;
7.
A satisfactory alternative feeding ground was not provided as can be shown both
from an analysis of the very small amounts of food available after the spartina
grass had been removed and also from bird counts of feeding birds after such
removal which show very low usage by these birds.
Mr
Connolly SC for the Defendant submitted that:-
1.
This is not an attachment or contempt motion, but rather has arisen in the
context of an application by the plaintiff to revisit the interlocutory Order
on the basis that new grounds should now justify a change therein;
2.
There is on the present application, unlike that before Kelly J, sufficient
evidence to satisfy the Court that the Order is complied with (whether on the
narrow or broad ground), and
3.
the various specific heads of complaint made by Mr GAFFNEY SC are explained or
comprise infractions which are not sufficiently serious to justify granting the
reliefs sought.
GENERAL
OBSERVATIONS
Before
moving to consider the specific heads of complaint, I would make one or two
general observations of my own as follows:-
(a)
The purpose of the Order of the 10 September was to ensure the provision by the
Defendant of a satisfactory alternative feeding ground contemporaneously with
the work on the Stagreenan polder and also to minimise the damage to that
alternative feeding ground, particularly by confining use to the existing
access, requiring the exact boundaries of the 10 hectare site to be agreed by
Duchas before work commenced, limiting vehicles to tracked or wide tyred
vehicles, limiting the work to the scraping off of only the surface, specifying
that the work would be under the supervision of a suitably qualified
professional (named in the Order) and commenced within time (this being a
temporary alternative site intended for use by over-wintering birds).
(b)
To a significant extent, in my opinion, the philosophy underlying this
particular method of making good the environmental damage to the Stagreenan
polder, is taken for granted by the Court (which is no expert in these matters
as was pointed out by Kelly J) and is not open for debate between the parties
to the litigation.
Specifically,
I do not think it is open to the Plaintiff to seek to impugn the work of the
Defendant on the basis of asserting that the alternative feeding ground is
inadequate no matter how perfectly it is carried out by reference to the Court
Order or the regime undertaken in the Environmental Impact Statement. If the
Defendant complies with the Order and the Statement then failure of the
alternative feeding ground should not result in a Court Order prohibiting the
work.
Equally,
I do not think it is open to the Defendants to say that in the light of
subsequent evidence (to the effect that the anticipated damage to the
Stagreenan polder is not as bad as was thought at first) the need for the
provision of the alternative site has reduced so that compliance with the Court
Order can be relaxed.
Both
these latter themes seemed to me to inform some of the evidence during the case
before me but I think once a project has been granted a licence on a particular
basis, then it is not open to the Court, in effect, to modify the terms of the
licence. The role of the Court is simply to ensure that those provisions are
carried out.
SPECIFIC
ISSUES
1.
Existing access
On
the first day of work (6 October, 1999) entrance was made by the Defendant's
vehicles not via the existing entrance but at a turning bay in the road
opposite or near the house of Terry O'Brien, a wood carver, (who lives
adjoining and gave evidence at the hearing before me). Mr O'Brien was angry,
communicated with the Harbour Office, and was told to write in a letter of
complaint which he did and a copy of it was produced in evidence.
Subsequently
the existing evidence was widened and stones placed on the salt marsh to
facilitate the entrance of vehicles into the alternative site.
This
evidence was not disputed. There was a clear breach of the requirement to use
the "existing access" and, in my view, a breach, at least in spirit, of the
terms of the Order to the extent that the existing access was widened without
further reference to the Court.
2.
Delay
The
evidence before me was no different in principle to that on Affidavit before
Kelly J. I concur with his views that the delay was caused by matters outside
the control of the Defendant and, of itself, is not a breach which would
justify granting the Plaintiff relief.
3.
Determination of the "exact boundaries"
This
was not done. The Defendant's witnesses accepted that a roughly triangular
shape was agreed at a meeting on the 23 September, 1999 by Doctor Kelso, the
Harbour Master, Martin Donnelly and John Flynn of Duchas. A subsequent map with
a roughly drawn rectangular shape prepared under the general supervision of
Doctor Kelso was produced with the intention of indicating (as distinct from
defining exactly) where the work of removing spartina grass should occur.
I
do not understand the Defendant seriously to contend that this complies with
the Order that Duchas would agree "the exact boundaries of the removal area".
From the point of view of the work itself, I am inclined to accept the opinion
of the three individuals who agreed the overall site of the work, that their
arrangement is acceptable in principle and poses no environmental hazard of
itself. From the point of view, however, of the Plaintiff, who was deeply
concerned with the way in which this work was being carried out, it meant that
not only was there not a prior agreement by Duchas of the "exact boundaries" of
the removal area, but there was no map with such boundaries displayed on it
which could be given to her and by reference to which she could, as she was in
my view entitled, check to see that the work was being carried out in
accordance with the Court Order.
4.
Use of unsuitable vehicles
Once
again, the evidence in relation to this was, in principle, the same as was
before my colleague Kelly J on the application of the 22 October, 1999. There
was, however, one new element; the work commenced on Wednesday the 6 October;
neither Doctor Kelso nor John Flynn attended on site until the 12th. On that
day John Flynn objected to the offending tractor and trailer which was promptly
replaced with a more suitable one. If either he or Doctor Kelso had attended at
the commencement of the work or any day before the 12 October, then this
damaging element would have been identified sooner and to that extent less
damage done by a tractor and trailer which were clearly in breach of the Court
Order. Whilst, perhaps, in the overall context, this was not a gross violation
of the Order, it does constitute, in my opinion, yet another increment of
departure from the terms of the Order which cannot be entirely overlooked.
5.
Damage to the salt marsh area
The
Plaintiff said in evidence that on Friday the 8 October (the third day of the
works) she saw machines on the salt marsh and they were doing serious damage.
John Flynn (of Duchas) said that one-third of the spoil found its way onto the
salt marsh, whilst two-thirds was on an old stone-dumping ground. There is
clear, unchallenged, evidence that deep (some 35 centimetres deep) tracks were
made by vehicles between the Spartina extraction site and the temporary spoil
dumping site near the road and there is some evidence from local inhabitants of
work done in the salt marsh area.
I
do not think the vehicle tracks amount to a breach of the Order because I
accept Dr Kelso's evidence that for the work to be effective, vehicles had to
have access into the mud flats and therefore had to cross the intervening
terrain (which included the salt marsh in part). Whilst I accept that the
dumping of one-third of the spoil on the salt marsh area (as distinct from the
pre-existing stone dump area) is not desirable, I do not think that this is a
gross infraction. Regarding the evidence of local inhabitants, I am not
prepared to say that this was sufficiently precise as to amount to proof on the
balance of probabilities of any meaningful damage to the salt marsh area.
6.
Did the Defendants dig too deep?
The
Order specifies that "only the surface . . . will be scraped off . . .". It
does not specify the depth of the surface: it is therefore necessary, as the
Order specifies, that the work be supervised by a suitably qualified marine
consultant. The clear intent of the Order is that the grass be removed so that
the colonised mud flat and existing open pockets of mud flat be exposed but
that no more than the surface be removed because this would do environmental
damage.
The
Plaintiff herself gave evidence that on the 8 October she saw a long armed
machine "scooping" material at a point about 150 metres from the road and
depositing it in an area which she thought might have been 100 metres from the
road. Later she said that the method changed so that more stubble was left.
Declan Collins (a member of Bird Watch who works in Eircom) said that on the 7
October he saw deep tracks being formed about 45 centimetres deep and others of
the same depth he thought, with water in them and these went across the salt
marsh. Hard core was laid across the polder.
Aine
Walsh (an Environmentalist with a Masters Degree in Environmental Science from
Trinity College) said that she saw a new road on the salt marsh and that after
October the whole area was an awful mess, was mushed and flattened, squashed
and scraped.
The
top layer was removed over an area about 1 1/2 times the size of a football
field. Terry O'Brien (a wood carver who lives nearby), in addition to giving
the evidence about the entrance on the first day to which I have already
referred, said that on that occasion the holes were being dug far too deep.
Michael
Gunn, a vet, said that the plants and grass had been removed but some stubble
was left here and there. There were trenches through the area which was left
like a rugby pitch after three or four senior cup matches on a wet day.
Larry
Lenihan, who lives nearby and is a member of Bird Watch and who has
participated in several bird counts, said he refused to do a bird count this
year because there was no polder left any more.
Dr
Kelso said that she visited the site on several days and saw the work there.
The vehicle tracks were there but were to be limited if possible to one track
in accordance with her directions. She said that the machinist did not take out
scoops of earth but rather carefully scraped the surface and took several
inches at most and did so very competently.
Martin
Donnelly, the Harbour Master, said he attended at the site nearly every day
because not only was he concerned with a Court Order, but also it happened to
be on his daily round and was a mere ten minutes from his office. He confirmed
that there was only one vehicle track and said that he discussed the operation
with the driver and gave Dr Kelso's written directions to him and was satisfied
that the driver, Michael Murray, worked quite diligently and was in compliance
with the Order.
John
Flynn of Duchas would not agree that there was evidence that the excavator
bucket had scraped too much or too deeply.
My
conclusion in relation to these allegations is as follows:-
1.
There was always going to be a mess given the nature of the work;
2.
It was inevitable that deep vehicle tracks would be created across the surface
of the terrain (including in part the surface of the salt marsh) and I accept
that every reasonable effort was made by the Defendant to minimise this and it
seems to have been successful in achieving a single vehicle track rather than
several. That being the case, it must follow to some extent that the single
tracks would be particularly deep.
3.
Dr Kelso, while maintaining that the surface was scraped (as distinct from
scooped) also acknowledged that it is not possible to keep a completely uniform
level.
In
my view there may well have been departures from an optimum depth but overall I
consider that the amount of spoil removed with the Spartina grass has been kept
within reasonable limits. My impression is that as the work progressed, more
stubble remained. In this context I am bearing in mind that the work was always
going to be messy, the terrain is uneven and boggy and to that extent
difficult. I do not think that the Plaintiff has established on the balance of
probabilities that the Defendant is in breach of the Order in this regard.
Is
the Defendant providing an alternative compensatory feeding ground?
The
evidence in relation to this falls into two categories, namely, a scientific
assessment of the bird food available in the alternative site, and a count of
birds actually feeding thereon.
(a)
Has bird food been provided?
Dr
James Wilson (a distinguished Zoologist specialising in marine biology) gave
evidence of samples taken and of his conclusion that the food available in the
alternative site is approximately one-tenth of what he would expect. Commenting
on the difference between his results and those of Dr Kelso, he emphasised that
numbers of individual animals is less important than the amount of biomass
shown in the results. On the basis of biomass, his results were virtually the
same as those of Dr Kelso. He employed a one centimetre sieve (whereas Dr Kelso
employed a half centimetre sieve). He agreed with Dr Kelso's evidence that the
half centimetre sieve was in accordance with UK standard practice but this
practice, he pointed out, was directed to identifying suitable habitats whereas
his study was concerned with assessing the amount of food (biomass) available
for the birds. In this latter aspect, his report was very similar to that of Dr
Kelso and showed very much reduced biomass.
Dr
Kelso, for her part, relied on the UK standard practice, and sought to explain
the difference between her results (which showed higher numbers of food items
available for the birds in the alternative site after the work that was done
than did Dr Wilson's study) by reference to her use of the smaller sieve size.
She remained perplexed, however, as to the divergence in their results. A
suggestion was made to her that perhaps her samples came from outside the area
worked on by the Defendant (this suggestion assumed plausibility when various
maps were compared and her sample locations appeared to be outside the work
area) but she rejected this on the basis that she had clear photographs to show
that her samples were taken within the work area.
Dr
Wilson's explanation to the effect that biomass is the critical determinant in
the context of assessing food availability seems to me to make sense. I would
hesitate to come to a firm conclusion on this basis alone, but for it is worth,
my view is that there is, as yet, a low or reduced amount of biomass in the
alternative site.
(b)
The bird counts
Michael
Gunn (a vet) produced bird counts for December and January. All experts agree
that one can ignore the plover (both golden and green (lapwing)) as they are
mainly present as roosters as distinct from feeders (although some low
percentage of these can be feeding). These counts show that the alternative
site is not favoured by varieties of feeding birds which are, however, present
in areas outside the alternative sites and adjacent thereto. This suggestion
was accepted by Oscar Merne, an acknowledged ornithological expert who has been
employed with Duchas for thirty years. The overall thrust of his evidence was
that the feeders displaced from the Stagreenan polder could be accommodated
elsewhere in the estuary and that the cleared alternative site was much less
critical than was originally thought. In his view the Boyne Estuary had extra
capacity for an influx of red shank at winter time which has happened on
occasions before and the provision of an alternative site on the north polder
was not critical.
Dr
Partridge (a doctor in marine biology) gave evidence that the redistribution of
the key species (for example red shank) was taking place from the Stagreenan
polder to elsewhere in the estuary. The increased use of the cleared area
provided additional feeding albeit a small amount.
In
cross-examination, he acknowledged that the method of providing an alternative
food source (by clearing Spartina grass from the north polder as indicated in
the Environmental Impact Statement) did not accord at any time with his view.
He thought that very few birds used the Spartina area and he insisted that his
bird counter (Tom Cooney) was experienced but acknowledged that mention was
made in the bird count that the Spartina cleared area was part of a larger area
(with the inference, I thought, that feeders favoured the adjacent areas rather
than the cleared area).
I
formed the distinct impression that the ornithologists were not particularly
enthusiastic about the attractions of the alternative site as a compensatory
food resource for birds displaced from the Stagreenan polder, nor indeed did it
seem to me that they were unduly exercised by the reduction or loss thereof as
a food source given its context (comprising less than 10% of the entire) in the
overall Boyne Estuary.
In
this context they were prepared to concede, as it were, that there was some
advantage by way of increased food resource in the removal of the Spartina
grass, but it had its limits and on balance, I think the evidence showed that
feeding birds favoured the areas adjoining the cleared areas rather than
otherwise.
My
conclusion under this heading, namely, as to whether the Defendants are
providing an "alternative compensatory feeding ground" is somewhat mixed: in
principle they are carrying out the surface scraping work of removing the
Spartina grass in tolerable compliance with their obligations as set out in the
Environmental Statement, in the document attached to the Duchas letter of the 9
September, 1999 and, accordingly, with the Order of the 10 September, 1999. On
the other hand, insofar as it is relevant to this application, my impression is
that this particular method of compensating the loss to the Stagreenan polder
has not worked very well but that this is something which arises because of the
unsuitability of this methodology originating in the Environmental Impact
Statement (at least in the view of the ornithologists who gave evidence in
Court) rather than any serious failure on the part of the Defendants to
implement that methodology.
CONCLUSIONS
The
Defendants are in breach of the Order of the 10 September 1999 in a number of
ways indicated in this judgment. These breaches, when viewed in the context of
damage to the environment, seem to me to fall rather more on the technical side
than on the substantial side. By this I mean that the initial entry by way of
the wrong access, the subsequent widening of the access and building of the
hard-core track, the delay in time and the failure to agree the "exact
boundaries" of the ten hectare site and the use for six days of the
inappropriately wheeled vehicle and the incursion, such as it was, of work into
the salt marsh are all breaches which, whilst of course they have impacted on
the environment, have not done so to a degree which is grossly disproportionate
to the inevitable impact which the works were always going to have even if they
were carried out with punctilious observance of the spirit and letter of the
Court Order and, behind it, the methodology set out in the Environmental Impact
Statement.
Given
that I have held that there was no unduly deep removal of the surface it seems
to me to follow that any under-achievement in terms of food supply of the
Spartina cleared site arises not because of the failure of the Defendant to
comply with the Order and the Environmental Impact Statement, but because of
the limitations of the philosophy underlying that Statement, at least in the
opinion of the experts who appeared in Court.
In
my view, the Defendant should continue to be restrained from carrying out or
continuing the work referred to in the Order of the Supreme Court until such
time as a map is agreed by Duchas which sets out the exact boundaries of the
ten hectare removal site referred to in the Order of the 10 September 1999. I
would expect this map to be available within a matter of days from this date
and a prompt application made by the Defendant on production thereof for the
lifting of this extended interlocutory Order so that the work of providing an
alternative feeding ground should be recommenced as soon as possible. The
provision of this alternative source has at all times been as a temporary
resource for over-wintering feeding birds. I would expect that on the
Defendant's application an indication would be available to the Court as to a
reasonably efficient time frame within which the entire ten hectare site would
become available, the production of this time schedule to be prepared under the
supervision of Dr Kelso and, of course, the continued work to be in this as in
all other respects, in compliance with the Order of the 10 September 1999.
© 2000 Irish High Court
BAILII:
Copyright Policy |
Disclaimers |
Privacy Policy |
Feedback |
Donate to BAILII
URL: http://www.bailii.org/ie/cases/IEHC/2000/166.html