H285
BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
High Court of Ireland Decisions |
||
You are here: BAILII >> Databases >> High Court of Ireland Decisions >> Snoddy & ors v Mavroudis & anor [2013] IEHC 285 (19 June 2013) URL: http://www.bailii.org/ie/cases/IEHC/2013/H285.html Cite as: [2013] IEHC 285 |
[New search] [Help]
Judgment Title: Snoddy & ors v Mavroudis & anor Neutral Citation: [2013] IEHC 285 High Court Record Number: 2013 54 MCA Date of Delivery: 19/06/2013 Court: High Court Composition of Court: Judgment by: Laffoy J. Status of Judgment: Approved |
Neutral Citation [2013] IEHC 285 THE HIGH COURT [2013 No. 54 MCA] BETWEEN SAM SNODDY, TOM SNODDY, FERGAL BROWNE AND PAUL BROWNE APPLICANTS AND
DAVID MAVROUDIS RESPONDENT AND
DAVID O’LEARY NOTICE PARTY Judgment of Ms. Justice Laffoy delivered on 19th day of June, 2013. Factual background 2. The source of the arbitration and of this application is an agreement dated 21st August, 2007 (the 2007 Agreement) made between the applicants, therein referred to as Snoddy & Browne Partnership (the Client) of the one part and the respondent (the Architect) of the other part, whereby the Client appointed the Architect and the Architect agreed to act as architect in connection with the project identified in the 2007 Agreement on the terms and conditions attached to the 2007 Agreement, being terms entitled “Conditions of Appointment of Architect” and Appendix 1 annexed thereto entitled “Scope of Services Agreement”. The provisions in relation to payment of fees were set out in Appendix 1. Only one aspect of the terms of the 2007 Agreement is at issue on this application and that relates to one aspect only of the terms in relation to payment of fees to the Architect. The term in question appears as follows in Appendix 1:
4. The Architect was the claimant in the arbitration and the Client was the respondent. The Architect delivered his Arbitration Statement of Case on 28th March, 2011. In that document the Architect made the following claims, which are relevant to the issue before the Court:
(b) the Architect “had to carry out 524 hours additional work which was beyond the scope of that included in the unit rate” to satisfy further information requests from the planners in Carlow County Council; and (c) the Architect “was required to complete 524 hours for abnormal/additional services” relating to the requests for further information, at the contract rate of €100/hour plus VAT, and that gave an additional sum due of €52,400 plus VAT”. 5. The arbitration hearing took place between the 8th and the 10th May, 2012. The Arbitrator had the benefit of three sets of written submissions on behalf of the Client. The Court’s attention was drawn to two paragraphs in the opening written submissions. 6. The first appeared under the heading “Possible Claim based on Quantum Meruit” and, in order to understand its relevance, it is necessary to note the first clause under that heading which stated:
7. The other submission to which the Court’s attention was drawn was a submission under the heading “Abnormal/Additional Services Payment” that “applying the expressio unius est (sic) exclusio alterius doctrine, because the [Architect] had expressly added ‘plus 21% VAT’ to all other fees payable to him but had not done so in relation to abnormal/additional services, the “€100 per hour fee” for abnormal/additional services was inclusive of VAT. 8. The Client’s closing submissions, which were furnished to the Arbitrator, were also put before the Court and the Court’s attention was drawn to a submission in which it was reiterated that the Client’s opening submissions had pointed out that quantum meruit was not pleaded, and that, despite being invited to do so, the Architect had not amended his pleadings. The invitation to amend was repeated. It was stated that the Client would consider its position in relation to agreeing to authorise the Arbitrator to make an equitable award should the Architect ask for its agreement. 9. In the Client’s reply to the Architect’s closing submissions, which has also been put before the Court, the Client submitted that the Architect was not entitled to any consideration for abnormal/additional services because the work was not authorised by the Client in accordance with the contract terms. Further, the claimant had been invited to seek a remedy in quantum meruit but failed to do so. 10. The Client received the Arbitrator’s interim award on 6th December, 2012, which was an extremely comprehensive document running to 143 pages. The Arbitrator addressed the claim for abnormal/additional services as follows in the interim award:
(b) in considering “payments due” he recorded that provision again accurately (para. 310); (c) the claim for fees due in respect of the additional work was addressed in para. 480 et seq. and the Arbitrator’s determination was set out in para. 487.
11. A claim for interest was also dealt with in the award. The Architect contended that there was an error in the determination of the interest due and by letter dated 17th January, 2012, the Client’s solicitor agreed to the award being amended to properly reflect the award insofar as it related to interest. In the same letter the Client’s solicitors requested the Arbitrator to interpret the award so as to address the issue which is the subject of this application. 12. The issue had previously been raised in a letter dated 20th December, 2012 from the Client’s solicitors to the Arbitrator dated 20th December, 2012. Having referred to the findings in the award in relation to the quantum of fees due from the Client to the Architect for additional services, the Client’s solicitors requested that the Arbitrator give an interpretation to the phrase “. . . a written instruction was not a condition precedent to an entitlement to payment . . .” in para. 485 of the award in the context of the relevant contract provision, as set out in para. 251 of the award. In relation to that request, by letter dated 7th January, 2013 to both parties to the arbitration, the Arbitrator stated that he could not consider the request for interpretation without the agreement of the Architect as required by Article 33(1)(a) of the Model Law. That agreement was not forthcoming. 13. Finally, one matter is adverted to in the grounding affidavit sworn by the third named applicant, Fergal Browne, on 28th February, 2013, the significance of which is not clear. Mr. Browne is a solicitor in the firm Fergal Browne & Company, Solicitors, which firm is on record for the Client in this matter. Mr. Browne has averred that on 21st September, 2012, the partnership of the four named applicants ended. He has referred to an exhibit which is supposed to be a notice in relation to that event published in Iris Oifigiúil. However, I can see no reference to the Snoddy Browne Partnership in the issue of Iris Oifigiúil exhibited, which was the issue of Friday, 1st February, 2013. Whatever the significance of the partnership having ceased to exist, my understanding is that Fergal Browne & Co. are acting for all of the applicants (referred to as the Client, on this application), and, indeed, Mr. Browne has averred that he has “discussed all events surrounding the case with the other members of the former partnership” and he has “their authority to act as their solicitor” on this application. The application
(b) orders – (i) directing the Architect to agree to the Arbitrator giving an interpretation of the award; (ii) directing the Arbitrator to make such an interpretation; and (iii) granting liberty to the Client to apply for an order setting aside the award or part of the award during a period not exceeding three months from receipt of the Arbitrator’s interpretation. The legislation invoked 17. The first provision of the Model Law invoked is Article 34(2)(a)(iii). Article 34 regulates applications for setting aside arbitral awards. Paragraph (1) provides that recourse to a court against an arbitral award may be made only by an application for setting aside in accordance with paragraphs (2) and (3) of the Article. The provision of paragraph (2) which the Client invoked provides as follows:
(a) the party making the application furnishes proof that: (i) . . . (ii) . . . (iii) the award deals with a dispute not contemplated by or not falling within the terms of the submission to arbitration, or contains decisions on matters beyond the scope of the submission to arbitration, provided that, if the decisions and matters submitted to arbitration can be separated from those not so submitted, only that part of the award which contains decisions on matters not submitted to arbitration may be set aside; . . ..”
20. Article 28(3) of the Model Law was also cited in submissions to the Court and, as recorded earlier, it had been referred to in the Client’s opening written submissions to the Arbitrator, Article 28 deals with rules applicable to the substance of the dispute, primarily, the law to be applied. Article 28(3) provides:
Analysis of basis of Client’s claim for relief 23. However, the Arbitrator did make an award for additional services in favour of the Architect on the basis of payment of €82.46 per hour for 500 hours. Therefore, both the number of hours covered by the award and the charge rate per hour differed from what was provided in the 2007 Agreement. It was submitted that, accordingly, part of the award must have been made on a basis other than the application of the contractual principles. The Client’s submission was that the Arbitrator applied the quantum meruit principle which it was submitted is an equitable principle. However, the parties, and, in particular, the Client had not expressly authorised the Arbitrator to decide the claim on the basis of equitable principles in accordance with Article 28(3) and, in fact, although invited so to do, the Architect had not amended his pleadings to make such a claim. 24. Therefore, it was submitted that in that part of the award the Arbitrator dealt with the claim for additional services in a manner which was not contemplated by and did not fall within the terms of the submission to arbitration. In other words, the Arbitrator exceeded his authority on the reference to him. That brought the matter within the parameters of Article 34(2)(iii), it was submitted. 25. A comparison of those submissions with what the Arbitrator actually did in the award, in my view, indicates that the claim does not stand up to scrutiny. The Arbitrator correctly identified the quantum of the Architect’s claim for additional work under the terms of the 2007 Agreement. He correctly identified the provision that the services were to be authorised and agreed in writing by both parties before commencement. He found that the additional services in respect of which the Architect claimed had not been specifically authorised in writing by the Client. He determined that this did not preclude him from making an award in respect of this element of the claim in favour of the Architect, holding that the provision was not a condition precedent to an entitlement to payment, which obviously refers to the Architect’s contractual entitlement to payment, which is what he was considering. The Arbitrator also determined the quantum of the claim by reference to what he considered to be the Architect’s entitlement under the contract. As regards the charge rate per hour, on the basis of the submission of the Client, he expressly found that the quoted rate of €100 per hour, that is to say the rate stipulated in the 2007 Agreement, was inclusive of VAT, not exclusive of VAT as the Architect had claimed. Accordingly, the charge rate of €82.64 per hour which he applied was the rate of €100 exclusive of VAT at the rate of 21%. As regards the number of hours for which the Architect should be paid fees in respect of additional services, he did so on the basis of what was a reasonable estimate of the time it would take to do the work in question on the basis of the evidence and, in particular, the evidence of the Client’s expert. 26. Therefore, it is patently clear that the Arbitrator determined that element of the Architect’s claim by application of the terms of the 2007 Agreement and in accordance with what he considered to be correct contractual principles. 27. The Arbitrator may have been wrong in the application of contractual principles and, in particular, he may have been wrong in his finding that the agreement in writing of the Client to the additional services before commencement was not a condition precedent to the Architect’s entitlement to payment for those services. What I propose considering now is what the scope of the provisions of the Model Law which the Client has invoked is. The objective of so doing is to determine, if the Arbitrator erred in making the award in relation to the additional services, and no view will be expressed in this judgment on that point, whether the Client is entitled to any of the reliefs claimed. 28. Before doing so it is pertinent to record that at the hearing counsel for the Client outlined the options open to the Court as follows:
(b) to suspend the setting aside and to remit the matter to the Arbitrator for the period to allow the Arbitrator to consider the matter in accordance with Article 34(4); or (c) to direct the Architect to agree to the Arbitrator interpreting that element of the award in accordance with the Client’s request. Scope of articles of Model Law invoked 30. As a preliminary, it is important to note that s. 8 of the Act of 2010 provides that judicial notice shall be taken of the travaux préparatoires of the United Nations Commission on International Trade Law and its working group relating to the preparation of the Model Law and that the travaux may be considered when interpreting the meaning of any provision and shall be given such weight as is appropriate in the circumstances. 31. The very limited jurisdiction which this Court has under the Act of 2010 and the Model Law to set aside an arbitral award is outlined in Mansfield’s note on Article 34 (at p. 213) as follows:
32. Sub-paragraph (a) of paragraph (2) of Article 34 sets out four circumstances in which an award may be set aside at the suit of a party to the arbitration, who proves that one or more of such circumstances exists. The circumstance with which the Court is concerned in this case is the third circumstance, that is to say, the circumstance set out in Article 34(2)(a)(iii). Mansfield’s commentary on that provision is that it is a ground –
33. It is generally recognised that the excess of authority ground in Article 34(2)(a)(iii) of the Model Law is modelled on the corresponding provision in the New York Convention, Article V(1)(c). As was pointed out by Lord Steyn in Lesotho Highlands Development v. Impregilo SpA [2006] 1 AC 221, s. 68 of the UK Arbitration Act 1996 was modelled on the New York Convention and on the Model Law. In considering the application of that statutory provision, Lord Steyn considered Article V(1)(c) of the New York Convention stating (at p. 236):
35. As regards Article 34(4), as is pointed out by Mansfield (at p. 219), the travaux suggest that the power to remit an award “would enable the arbitral tribunal to cure certain defects which otherwise would necessarily lead to a setting aside of the award”. I consider that counsel for the Architect was correct in her submission that the Court’s jurisdiction to remit under Article 34(4) is dependent upon the Court being satisfied that a ground has been proved for setting aside the award. That has not happened in this case. Therefore, the Court has no power to set aside under Article 34(4). 36. As regards Article 33 of the Model Law, it confers no jurisdiction on this Court to compel a party to an arbitration to seek, or an arbitrator to give, an interpretation of a specific point or part of an award. In any event, by seeking an order compelling the Architect to agree to the Arbitrator giving an interpretation, in reality, as counsel for the Architect submitted, the Client is attempting to re-visit the merits of the Arbitrator’s award. Having regard to the analysis of the Client’s claim conducted earlier, the aspect of the award with which the Client takes issue could not be regarded as requiring interpretation because there is no ambiguity in it. In my view, it does not require clarification. Conclusion and order |