BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
High Court of Justice in Northern Ireland Queen's Bench Division Decisions |
||
You are here: BAILII >> Databases >> High Court of Justice in Northern Ireland Queen's Bench Division Decisions >> TAL Ltd v The Very Reverend D Whyte PP [2018] NIQB 92 (30 November 2018) URL: http://www.bailii.org/nie/cases/NIHC/QB/2018/92.html Cite as: [2018] NIQB 92 |
[New search] [Printable PDF version] [Help]
[2018] NIQB 92 | Ref: | HOR10788 |
Judgment: approved by the Court for handing down | Delivered: | 30/11/2018 |
(subject to editorial corrections)* |
BETWEEN:
Applicant;
Respondent.
HORNER J
INTRODUCTION
“"12.3 TAL has not drawn my attention to provisions in the Contract or otherwise whereby:
(i) The Quantity Surveyor had the authority to make an agreement binding on the Respondent regarding the Final Account.
(ii) The Respondent was obliged to pay the sum agreed by the Quantity Surveyor.
(iii) The Respondent was obliged to make a final payment before issue of the Certificate of Making Good Defects.
12.4 I therefore find that TAL’'s claim under this heading fails.”"
He then goes on to conclude that TAL fails in its claim to be paid £47,527.98 being the balance due on foot of the Final Account of £54,677.98 less agreed defects.
BACKGROUND INFORMATION
“"Under Rule 12.9 of JCT CIMAR 2005, the Arbitrator has the powers set out in 57(3) to (6) of the Arbitration Act 1996. The types of correction which may be made are set out in Section 57(3)(a) and (b). My provisional view is that this sub-section does not provide for the type of correction which the Claimant invites me to make.
In any event, paragraph 12.3(i) of my award dated 12 June 2018 was not the central point on which I found the Claim failed. Even if I had taken no account of paragraph 12.3(i), my findings at paragraph 12.4 would have been the same.”"
RELEVANT LEGAL PROVISIONS
“"68 Challenging the award: serious irregularity.
(1) A party to arbitral proceedings may (upon notice to the other parties and to the tribunal) apply to the court challenging an award in the proceedings on the ground of serious irregularity affecting the tribunal, the proceedings or the award.
A party may lose the right to object (see section 73) and the right to apply is subject to the restrictions in section 70(2) and (3).
(2) Serious irregularity means an irregularity of one or more of the following kinds which the court considers has caused or will cause substantial injustice to the applicant—
(a) failure by the tribunal to comply with section 33 (general duty of tribunal);
(b) the tribunal exceeding its powers (otherwise than by exceeding its substantive jurisdiction: see section 67);
(c) failure by the tribunal to conduct the proceedings in accordance with the procedure agreed by the parties;
(d) failure by the tribunal to deal with all the issues that were put to it;
(e) any arbitral or other institution or person vested by the parties with powers in relation to the proceedings or the award exceeding its powers;
(f) uncertainty or ambiguity as to the effect of the award;
(g) the award being obtained by fraud or the award or the way in which it was procured being contrary to public policy;
(h) failure to comply with the requirements as to the form of the award; or
(i) any irregularity in the conduct of the proceedings or in the award which is admitted by the tribunal or by any arbitral or other institution or person vested by the parties with powers in relation to the proceedings or the award.
(3) If there is shown to be serious irregularity affecting the tribunal, the proceedings or the award, the court may—
(a) remit the award to the tribunal, in whole or in part, for reconsideration,
(b) set the award aside in whole or in part, or
(c) declare the award to be of no effect, in whole or in part.
The court shall not exercise its power to set aside or to declare an award to be of no effect, in whole or in part, unless it is satisfied that it would be inappropriate to remit the matters in question to the tribunal for reconsideration.”"
“"(a) act fairly and impartially as between the parties, giving each party a reasonable opportunity of putting his case and dealing with that of his opponent; and
(b) adopt procedures suitable to the circumstances of the particular case, avoiding unnecessary delay or expense, so as to provide a fair means for the resolution of the matters falling to be determined.”" – see 8-089 of Russell on Arbitration.
“"69 Appeal on point of law.
(1) Unless otherwise agreed by the parties, a party to arbitral proceedings may (upon notice to the other parties and to the tribunal) appeal to the court on a question of law arising out of an award made in the proceedings.
An agreement to dispense with reasons for the tribunal’'s award shall be considered an agreement to exclude the court’'s jurisdiction under this section.
(2) An appeal shall not be brought under this section except—
(a) with the agreement of all the other parties to the proceedings, or
(b) with the leave of the court.
The right to appeal is also subject to the restrictions in section 70(2) and (3).
(3) Leave to appeal shall be given only if the court is satisfied—
(a) that the determination of the question will substantially affect the rights of one or more of the parties,
(b) that the question is one which the tribunal was asked to determine,
(c) that, on the basis of the findings of fact in the award—
(i) the decision of the tribunal on the question is obviously wrong, or
(ii) the question is one of general public importance and the decision of the tribunal is at least open to serious doubt, and
(d) that, despite the agreement of the parties to resolve the matter by arbitration, it is just and proper in all the circumstances for the court to determine the question.
(4) An application for leave to appeal under this section shall identify the question of law to be determined and state the grounds on which it is alleged that leave to appeal should be granted.
(5) The court shall determine an application for leave to appeal under this section without a hearing unless it appears to the court that a hearing is required.
(6) The leave of the court is required for any appeal from a decision of the court under this section to grant or refuse leave to appeal.
(7) On an appeal under this section the court may by order—
(a) confirm the award,
(b) vary the award,
(c) remit the award to the tribunal, in whole or in part, for reconsideration in the light of the court’'s determination, or
(d) set aside the award in whole or in part.
The court shall not exercise its power to set aside an award, in whole or in part, unless it is satisfied that it would be inappropriate to remit the matters in question to the tribunal for reconsideration.
(8) The decision of the court on an appeal under this section shall be treated as a judgment of the court for the purposes of a further appeal.
But no such appeal lies without the leave of the court which shall not be given unless the court considers that the question is one of general importance or is one which for some other special reason should be considered by the Court of Appeal.”"
(i) That the determination of the question will substantially affect the rights of one or more of the parties;
(ii) That the question is one which the tribunal was asked to determine;
(iii) That, on the basis of the findings of fact in the award, either the decision of the tribunal on the question is obviously wrong, or the question is one of general public importance and the decision of the tribunal is at least open to serious doubt; and
(iv) that, despite the agreement of the parties to resolve the matter by arbitration, it is just and proper in all the circumstances for the court to determine the question: see paragraph 578 of Halsbury’'s Laws of England Volume 2.
It is important to note that an application for permission to appeal must identify the question of law to be determined on stated grounds on which it is alleged that permission to appeal should be granted; see Section 69(4) of the Act.
ARGUMENTS OF THE PARTIES
THE ARGUMENTS OF TAL
(i) The finding that the QS had no authority to bind the Respondent was a finding of fact. It was up to TAL to prove as part of its claim that there was a binding authority and this included establishing that the QS had the necessary authority, actual or apparent, to enter into a binding agreement as was asserted on behalf of the Respondent.
(ii) The issue of authority of the QS in any event had been “"put into the arena”" in the arbitration and therefore there was no serious irregularity in extracting an alternative case from the submissions made to the Arbitrator.
(iii) There was no substantial injustice in any event because it did not affect the final decision of the Arbitrator. He had also determined that there was no obligation to make a final payment before the issue of the Certificate of Making Good Defects and no such certificate had been issued. Thus, the decision that there was no binding agreement was sound on more than one ground.
DISCUSSION
“"Following consideration of said Final Account the Quantity Surveyor emailed Mr Gary Whiteman for the Complainant on 4 May 2016 under subject “"SMOTH Final Account Agreement”" to confirm that the amount due to the Claimant was £54,677.98 and to seek the Claimant’'s agreement as to this figure.”"
It goes on to plead at paragraph 12:
“"On 5 May 2016 Mr Whiteman replied to the Quantity Surveyor to confirm that Figure Agreed.”"
Paragraph 13 pleads:
“"This exchange between the parties constituted an express agreement as to the value of the Claimant’'s Final Account.”"
“"The Respondent accepts that the Quantity Surveyor agreed the figure but denies that this signified that the Final Account had been agreed and maintains that the Claimant was on notice of the fact that there were defects they were contractually bound to attend to and that any Final Account was subject to rectification of the defects. No Final Account standard form signed by the parties was ever produced in this matter. The exhibited correspondence demonstrates the defects remained and put the Claimant on notice that the Respondent would seek reduction on final account in respect thereof.”"
“"The email of 4 May 2016 only confirms agreements on figures. It is not a signed Final Account. It does not absolve the Contractor’'s obligations under the JCT contract to complete and/or make good defects before a Certificate of Making Good Defects can be issued. A final valuation can then be raised and certified by a Final Certificate and the contract confirmed as fully complete.”"
“"The email of 4 May 2016 cannot be considered in isolation of the factual position as between the parties and the clear understanding between them that the defects had to be attended to. The statement of case makes an uninformed leap from 2011 to 2016 without taking an [sic] cognisance of the interparty correspondence and understanding on the core issue. It was only on 21 November 2016 that Gary Whiteman of TAL Ltd emailed to confirm that TAL were in a position for the final inspection – see file F2 TAB 5. Final inspection was never actually achieved because the defects remained outstanding.”"
“"(ii) … the exchange between the parties dated 4 May 2016 following the Claimant’'s submission of its Final Account on or about 2011, constitutes an express agreement as to the value of the Final Account, namely £54,677.98.
(iii) That payment has not been forthcoming by the Respondent in respect of the Final Account for a period of almost 5 years.”"
“"2. The Respondent does not accept that the exchange of 4 May 2016 constitutes and [sic] express agreement or that the Final Account was agreed at £54,677.98. The Claimant’'s Response Para 7 submits that the Parties are now in agreement that the value of the claimant’'s Final Account is £54,677.98”".
It is set out within the Respondent’'s response that the “"4 May 2016 email can only be considered in the context of other correspondence and conduct and the Final Account was at all times subject to the making good of the defects.”"
“"3. TAL had in fact agreed that any final payment was subject to all defects being made good and the Architect being been able to issue a Certificate of Making Good Defects. TAL had a contractual responsibility to make good defects. TAL’'s failure to properly attend to defects identified within the rectification period and the reappearance of some of these defects prevented the Certificate of Making Good Defects being issued and frustrated the closure of the contract and the formation of a Final Valuation.”"
“"[28] First, unlike the position under the old law, intervention under S.68 is only permissible after an award has been made. Secondly, the requirement is a serious irregularity. It is new concept in English arbitration law. Plainly a high threshold must be satisfied. Thirdly, it must be established that the irregularity caused or will cause substantial injustice to the applicant. This is designed to eliminate technical and unmeritorious challenges. It is also a new requirement in English arbitration law. Fourthly, the irregularity must fall within the closed list of categories set out in paragraphs (a) to (i).”" (Emphasis added).
“"In any event, paragraph 12.3(i) of my award dated 12 June 2018 was not the central point on which I found that the Claim failed. Even if I had taken no account of paragraph 12.3(i) my finding at paragraph 12.4 would have been the same.”"
The Arbitrator had found that TAL had failed to satisfy him that TAL was entitled to rely on any contractual provision to receive a final payment before the issue of the Certificate of Making Good defects. It is common case that no such Certificate was issued. Accordingly, on one limb of the Arbitrator’'s decision no sum could become due and owing in respect of the final account.
“"The authorities on S.68 of the Act were extensively reviewed by Tomlinson J in ABB AG v Hoctief Airport GmbH [2006] 2 Lloyd’'s Rep 1. I agree with the conclusions Tomlinson J came to on the base of these decisions. He held that their effect is that an applicant under Section 68 is a high hurdle to overcome; there will only be a serious irregularity if what has occurred is far removed from what could reasonably be expected from the arbitral process (P.17). If the issues in question have been put into the arena, there is no serious irregularity in extracting an alternative case from the submissions of the parties (P.18, citing Warborough Investments v Robinson [2003] EGLR 149). It is not a ground for intervention that the court considers that it might have done things differently or expressed its conclusions on the essential issues at greater length (P.19). If a party had a fair opportunity to address its arguments on all of the essential building blocks of the Tribunal’'s conclusion, the fact the Tribunal did not refer back to the parties its analysis of the material before it and the conclusion it reached on it does not constitute a serious irregularity resulting in a substantial injustice (P.21).”"
(a) A Final Account had been agreed. (Indeed no Final Account standard form which had been signed by the parties had ever been produced.)
(b) A Certificate of Making Good Defects had been issued.
In its final submission the Respondent states:
(a) that the exchange of correspondence on 4 May 2016 did not constitute an express agreement or that the Final Account was agreed at £54,677.98; and
(b) the email of 4 May 2016 has to be considered in the context of other correspondence and conduct and that the Final Account was at all times subject to the making good of the defects.
THE SECTION 69 APPEAL
(i) The Arbitrator ascertains the facts; this process includes the making of findings on any fact which are in dispute;
(ii) The Arbitrator ascertains the law; this process comprises not only the identification of all the material rules of statute in common law, but also the identification and interpretation of the relevant parts of the contract, and the identification of those facts which must be taken into account when the decision is reached.
(iii) In light of the facts and the law so ascertained, the Arbitrator reaches his decision.
(a) That David Beswick was an agent of TAL.
(b) As an agent of TAL he had the actual authority to reach this agreement.
(c) If he did not have actual authority then he had ostensible authority or apparent authority to reach such an agreement.
(d) He had some other authority on the basis of the Contract to conclude a deal on behalf of the Respondent.
On the case put forward by TAL, there is no mention of the QS’'s authority to contract on behalf of the Respondent at all. Therefore, TAL is in no position to complain about the Respondent’'s denial that there was any agreement on the Final Account. The Arbitrator in the circumstances of this particular arbitration and given the respective cases that were made in the Statement of Case and the Response and Counterclaim was entitled to reach the conclusion he did. It was not the Arbitrator’'s responsibility to direct the proofs of either party.
CONCLUSION