GLADMAN DEVELOPMENTS LTD AGAINST THE SCOTTISH MINISTERS [2019] ScotCS CSIH_34 (14 June 2019)


BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?

No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!



BAILII [Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback]

Scottish Court of Session Decisions


You are here: BAILII >> Databases >> Scottish Court of Session Decisions >> GLADMAN DEVELOPMENTS LTD AGAINST THE SCOTTISH MINISTERS [2019] ScotCS CSIH_34 (14 June 2019)
URL: http://www.bailii.org/scot/cases/ScotCS/2019/2019_CSIH_34.html
Cite as: 2019 GWD 21-332, [2019] ScotCS CSIH_34, [2019] CSIH 34

[New search] [Printable PDF version] [Help]


Page 1 ⇓
FIRST DIVISION, INNER HOUSE, COURT OF SESSION
Lord President
Lord Menzies
Lord Brodie
OPINION OF THE COURT
[2019] CSIH 34
XA72/18
delivered by LORD MENZIES
in the Appeal
by
GLADMAN DEVELOPMENTS LIMITED
Appellants
against
THE SCOTTISH MINISTERS
Respondents
Appellants: J Findlay, QC, A O Sutherland; Burness Paull LLP
Respondent: Burnet; Scottish Government Legal Directorate
14 June 2019
Introduction
[1]       This is a statutory appeal under section 239 of the Town and Country Planning
(Scotland) Act 1997 against the respondents’ refusal of an appeal against the decision of
Stirling Council to refuse the appellants’ application for planning permission in connection
with a proposed development consisting of 70 houses, a cemetery with associated
engineering works and landscaping on 11ha of land to the south of Campsie Road,
Strathblane (“the Site”).
Page 2 ⇓
2
[2]       The issues are whether the Reporter appointed by the respondents to make the
decision erred in failing, first, to decide whether the Council’s 5-year effective housing land
supply is currently being met by failing to determine whether the Council had used the
correct methodology to be used in calculating that supply, second, to take account, as
material considerations, of previous decisions made by the respondents and their appointed
reporters concerning that methodology (in particular decisions on whether the methodology
should take account of under-supply relative to previous targets), and, third, to give reasons
why she disagreed with the conclusions in those decisions in relation to the correct
methodology. Underlying the appeal is the appellants’ view that the figure for the Council’s
5-year effective housing land supply should be arrived at by taking into account under-
supply of housing in previous years.
Law and Policy Framework
[3]       Scottish Planning Policy provides for “a presumption in favour of development that
contributes to sustainable development” (paras 28 to 31) according to which planning
authorities “should ... ensure a generous supply of land for house building is maintained
and there is always enough effective land for at least five years” (para 123). While planning
decisions require to be made in accordance with the relevant local development plan “unless
material considerations indicate otherwise” (1997 Act, s 25(1)), where there is shortfall in the
5-year housing land supply, Local Development Plan (LDP) policies in that regard will not
be considered up to date (Scottish Planning Policy (2014) (SPP), para 125); further, the status
of the sustainable development presumption is elevated from a “material” (para 32) to a
“significant material” (para 33) consideration. In that situation:
Page 3 ⇓
3
“Decision-makers should also take into account any adverse impacts which would
significantly and demonstrably outweigh the benefits when assessed against the
wider policies in this SPP.” (para 33)
This latter requirement results in a “tilted balance” in favour of granting permission
(Hopkins Homes Ltd v Secretary of State for Communities and Local Government [2017] 1 WLR
1865, per Lord Carnwath at p 1887, para 59, and Lord Gill at p 1891, para 80). For discussion
of the same framework of law and policy arising in relation to different issues, see Gladman
Developments Ltd v Scottish Ministers [2018] CSIH 17 (LP (Carloway), opinion of the court,
paras 2 and 5 to 9) and in Graham’s The Family Dairy Ltd v Scottish Ministers 2019 SLT 258 (LP
(Carloway), opinion of the court, paras 2 and 3).
[4]       How the number of years of effective supply of housing land is established requires
to be explained. The number of years is assessed annually in a planning authority’s
Housing Land Audit (HLA). HLAs provide a snapshot of the amount of land available for
the construction of housing at a particular time each year (Planning Advice Note 2/2010
Affordable Housing and Housing Land Audits, para 45). They are the measurement
through which the respondents are able to monitor planning authorities’ compliance with
the requirement for an effective 5-year housing supply. PAN 2/2010, issued to promote
greater consistency and transparency in the content of audits and the way in which they are
carried out (para 40), recognised the value of systematic collection of information to assess
the extent to which planning authorities are identifying and delivering sufficient land for
housing (para 44), and addressed the methodology and content of HLAs as follows:
Methodology and Content
51. A housing land audit should contain relevant information about the established
and effective housing land supply, allowing for monitoring and comparison with the
housing land requirement. The starting point each year will be the inclusion of:
Page 4 ⇓
4
• all land with planning permission for residential development, including the
remaining capacity of sites under construction;
• land allocated for residential development (including the residential component of
any mixed-use development) in adopted development plans (LDP); and
• other land with agreed residential potential, such as land identified for housing in
proposed LDPs or assessed as appropriate for housing following an urban capacity
study.
52. Local authorities should consider including a range of variables in an audit
including a unique site reference, site area, site capacity, site ownership, the planning
status of the site, annual completions, the greenfield or brownfield status of the land,
whether it is a windfall site, and the type of housing being provided.
53. It is good practice to ensure that individual sites can be tracked readily from one
audit to the next until such time as development is completed. If the audit is to
provide an accurate picture of housing land supply, it will be necessary to ensure
that the annual completions are recorded accurately and shown in the audit,
including the residential component of mixed-use developments and the unplanned
contribution to the housing supply made by windfall sites and conversions.
Completions on regeneration sites should be shown net of any demolitions which
have taken place. All sites completed in any given year should be listed in a separate
schedule and a comprehensive table of historical annual completions should also be
provided.
Effective Land Supply
54. Not all of the sites in the audit will be effective, and it is important that the audit
distinguishes effective, i.e. unconstrained sites, from those which are affected by
constraints which cannot be overcome in time to contribute to the housing land
requirement. The decisions and assumptions around effectiveness and programming
are crucial to the accuracy and usefulness of the data in the audit and therefore merit
careful consideration.
55. The effectiveness of individual sites should be determined by planning
authorities in the light of consistent interpretation of the following criteria and
through discussions with housing providers. The aim is to achieve a realistic picture
of the available effective land supply which can contribute to the housing
requirement so that the level of additional housing, and therefore land needed to
meet the overall requirement, can be established. To assess a site or a portion of a site
as being effective, it must be demonstrated that within the five-year period beyond
the date of the audit the site can be developed for housing (i.e. residential units can
be completed and available for occupation), and will be free of constraints on the
following basis:
ownership: the site is in the ownership or control of a party which can be expected to
develop it or to release it for development. Where a site is in the ownership of a local
Page 5 ⇓
5
authority or other public body, it should be included only where it is part of a
programme of land disposal;
physical: the site, or relevant part of it, is free from constraints related to slope,
aspect, flood risk, ground stability or vehicular access which would preclude its
development. Where there is a solid commitment to removing the constraints in time
to allow development in the period under consideration, or the market is strong
enough to fund the remedial work required, the site should be included in the
effective land supply;
contamination: previous use has not resulted in contamination of the site or, if it has,
commitments have been made which would allow it to be developed to provide
marketable housing;
deficit funding: any public funding required to make residential development
economically viable is committed by the public bodies concerned;
marketability: the site, or a relevant part of it, can be developed in the period under
consideration;
infrastructure: the site is either free of infrastructure constraints, or any required
infrastructure can be provided realistically by the developer or another party to
allow development; and
land use: housing is the sole preferred use of the land in planning terms, or if
housing is one of a range of possible uses other factors such as ownership and
marketability point to housing being a realistic option.
56. Programming of sites is an important element of the audit. Programming is an
indication of the expected annual completions on each site, taking account of the
lead-in times, the ability of the site to be developed, and the capacity of the local
housing market. The housing land audit should show the expected completions on
sites over the following five years. The contribution of any site to the effective land
supply is that portion of the expected output from the site which can be completed
within the five-year period. It will be important that the programming is also related
to the expected timing of housing land allocations in the local development plan.
57. Programming is widely recognised as a less than scientific exercise. Nonetheless
it is important that assumptions do not overestimate the likely completions, as the
audited effective supply forms the basis for the calculation of the additional housing
land requirement to be provided through the development plan. Overestimation of
the potential of the effective supply will reduce the amount of additional land
allocated and therefore reduce the flexibility available in the supply to address
market fluctuations and other constraints to the delivery of housing. Realistic
programming will demonstrate the continued availability of sites to maintain a five-
year supply and help to monitor the availability of sufficient sites to continue to meet
the housing land requirement. It will also show whether the supply includes a
Page 6 ⇓
6
sufficient range of sites to meet the varying requirements of different parts of the
housing market. House builders are discouraged from underestimating the yield
from effective sites with the aim of seeking additional land allocations, and, equally,
local authorities are encouraged to become familiar with the realities of the operation
of the housing market in their areas and not to overestimate the likely level of
completions.
58. Planning authorities should use the information from the audit process to ensure
that at all times sufficient effective land is available to meet the housing land
requirement for at least the following 5 years. Planning authorities, housing and
infrastructure providers should work together to ensure that sites identified as
effective are successfully developed within the expected timescale. Where constraints
arise, or funding commitments necessary to delivery of the site are delayed, the
status of the site should be reviewed as part of the next housing land audit.
Non-Effective or Constrained Sites
59. Where sites which form part of the established housing land supply are identified
as non-effective, the audit should identify the nature of the constraint and the
necessary action and time required for resolution of the constraint to allow house
building. Planning authorities, housing and infrastructure providers should work
together to ensure constraints inhibiting the development of sites are removed,
particularly where the site is needed or expected to contribute to the housing land
requirement during the life of the development plan. In a small minority of cases it
may prove impossible to remove development constraints. Where this occurs, the
site should be removed from the audit of housing land supply.
Land with Agreed Potential
60. Land with agreed potential includes any land which is not formally identified in
an adopted development plan or which does not have planning permission. It can
include land identified for housing in proposed local development plans or assessed
as appropriate for housing following an urban capacity study. Careful consideration
should be given as to whether to include such sites in the audit, although inclusion
will not pre-empt subsequent consideration of the status of the site by the planning
authority when finalising a development plan or determining a planning application.
If a site ultimately is rejected by these processes, it should not be included in the next
audit.
[5]       On 17 February 2016, the respondents published their “Draft Planning Delivery
Advice: Housing and Infrastructure” (“the Draft Advice”). Under the heading “How should
the 5 year effective housing land supply be calculated?”, this document stated (para 22):
The baseline for determining whether there is a 5 year supply of effective housing
land is the Housing Supply Target (HST). The HST should be expressed as a total
figure to be achieved over the development plan period under consideration,
although an annual figure may also be set out.”
Page 7 ⇓
7
[6]       The Housing Supply Target (SPP, para 115) is a policy view, set out in the LDP, of
the number of homes the authority has agreed will be delivered over the periods of the
development plan and local housing strategy, taking into account wider economic, social
and environmental factors, issues of capacity, resource and deliverability; requires to be
reasonable, should properly reflect the Housing Need and Demand Assessment (HNDA)
estimate of housing demand in the market sector, and should be supported by compelling
evidence.
The Draft Guidance went on, at para 23:
Below is an example of how the 5 year effective land supply should be calculated. It
is taken from the Heads of Planning Scotland Planning Performance Framework. See:
PPF4 Guidance: Annual report template and guidance notes v4. February 2015.
Table 1: 5 Year Effective Land Supply
5-year effective housing
5-year effective land
land supply (units)
supply (years)
[over]
X5
=
5-year housing supply
target (units)
This calculation will give a numerical shortfall or surplus. For example, if the
Housing Land Audit shows a 5 year effective housing land supply of 9500 effective
units, but the local development plan has a 5 year housing supply target of 10000
units:
9500/10000 = 0.95 x 5 = 4.75 years effective housing land supply. In this case there is a
numerical shortfall in the 5 year effective housing land supply of 500 units has
emerged.
It further stated (para 75) that:
As part of the Housing Land Audit process, information on completions can be
used to identify how much land remains available. Completion rates should not
automatically be used as an indicator for additional land release. Where past
completions are lower than expected, it does not always follow that additional land
needs to be allocated for housing. A balance needs to be struck to ensure that low
levels of anticipated completions (arising from wider factors including market
Page 8 ⇓
8
conditions) do not artificially inflate the level of additional land release required.
Solutions may lie in unlocking allocated sites which remain constrained through
more proactive intervention such as the provision of infrastructure.
[7]       The Draft Guidance was subsequently withdrawn by the respondents on
29 November 2017, effective 1 December, but according to the open letter issued by the
Chief Planner, there remained “a strong policy position on planning for housing which is set
out in Scottish Planning Policy (SPP) and supported by PAN 2/2010”.
[8]       In general terms the equation used to establish the number of years of effective
supply divides the actual 5-year effective supply by the annual HST. Prior to Stirling
Council’s 2017 HLA, previous completions were subtracted from the Housing Land
Requirement, which figure was then divided by the years remaining in the LDP to provide a
figure for the annual HST, to be used in the equation described (2016 HLA, p 5). The HLR
figure from which the completions would be subtracted was the number of new homes to be
built (based on the LDP’s HST) plus the “generous margin” specified in the LDP, ie 10 to
20% on the HST, depending on local circumstances, to ensure a generous supply of housing
land (SPP, para 116). In 2016, both calculations were discussed: taking into account previous
under-supply by subtracting completions from the HLR produced a supply of 3.9 years;
without the subtraction it was 4.9 years (p 16). The former method was adopted. The 2017
HLA, issued on 30 June 2017, used only the latter method. It said that the Council had
decided to use the calculation method specified in the Planning Performance Framework,
which itself referred (p 21) to paragraph 55 of PAN 2/2010 (supra). It recognised that the
precise method of calculating the number of years of effectively supply was disputed, that
there was a variety of approaches at both local and national levels of government and in the
private sector, and that there was no finalised guidance from the respondents in place
(page 14). Using its method, it arrived at a figure of 5.3 years’ effective supply of housing
Page 9 ⇓
9
land. Accordingly, absent a shortfall on the 5-year supply, in any planning applications for
housing, the sustainable development presumption would only be a material as opposed
to a significant material consideration, LDP policies in relation to the supply of housing
land would be considered up to date, and there would be no tilted balance in favour of
permission. The appellants challenge the conclusion that there was no such shortfall on the
basis that previous completions should have been taken into account.
[9]       The equivalent issue also arose in the course of the preparation of Stirling Council’s
latest LDP in relation to the setting of the Housing Supply Target for the plan period. There
was a shortfall in delivery for the previous LDP of 540 homes. On 24 November 2017, the
respondents’ Reporters issued their report on the proposed LDP 2 (“the Examination
Report”). In this it was stated that paragraph 75 of the Draft Guidance (supra):
does not actually exclude previous under performance in relation to completions
rates from being used as an indicator for additional land release. I find that
paragraph 75 cautions against ensuring that low completion rates do not artificially
inflate the level of additional land release required, but requires that a balance be
struck between low completions rates and the wider factors that contribute to such
low rates, and the level of additional land release required.” (Issue 3, p 48, para 18)
The Reporters recommended that previous completions should be taken into account in LDP
2. LDP 2 in the form in which it was adopted by the Council in October 2018 did take
account of past completions in arriving at a figure for the HST for the plan period.
Stirling Council Decision
[10]       The appellants applied to Stirling Council for planning permission for the proposed
development at the Site. On 7 November 2017, the Council refused permission on the basis
that the application was contrary to the Development Plan and there were no material
considerations that would support any other conclusion. The Council considered that the
development would be contrary to Primary Policies 1 (Placemaking), 2 (Vision and Spatial
Page 10 ⇓
10
Strategy), 7 (Historic Environment) and 9 (Managing Landscape Change), and Policies 1.1(b)
(Site Planning), 1.5 (Green Belts; and the Council’s Supplementary Guidance, SG03, on
Green Belts), 2.1 (concerning Vision and Spatial Strategy and Sustainable Development) and
2.10 (Housing in the Countryside), of the 2014 LDP and proposed 2016 LDP. On the basis
that they would result in over-development of the settlement edge, and would not protect or
enhance the historic environment, the Council also considered that the proposals would be
contrary to guiding sustainable development principles in the SPP (para 29). In particular,
the decision letter noted that the scale of the residential development was beyond that
supported by its green belt and housing in the countryside policies, and would not provide
significant economic and social support to the local area in terms of Primary Policy 2.
Reporter’s Decision
[11]       The respondents’ Reporter dismissed the appeal and refused planning permission by
letter of 25 July 2018 (“the decision”). The Reporter identified (para 2) the key issue as being
whether there was a shortfall in the 5-year effective housing land supply, which may have
justified approval despite the Site being within the green belt and the spatial strategy of the
LDP. The issues in the appeal to this court arise from the Reporter’s treatment of the
question of whether the 5-year effective supply was being met. It is therefore worth setting
out the Reporter’s conclusions on this matter in full:
“14. The requirement on councils to maintain a five years’ effective housing land
supply is emphasised in Scottish Planning Policy and is reflected in both the adopted
and the proposed local development plans. Currently, the appropriate methodology
for calculating whether there is a five years’ effective housing land supply is a matter
of considerable dispute, principally between local planning authorities and those
with an interest in building new houses or in securing planning permission for
residential developments. Advice on the appropriate methodology which had been
published in draft by the Scottish Government in February 2016 was withdrawn in
November 2017. In doing so, the Chief Planner drew attention to the existing policy
position in Planning Advice Note 2/2010.
Page 11 ⇓
11
15. That advice note confirms that the annual housing land audit is the established
means of monitoring housing land. It provides a snapshot of the amount of housing
land available for housing construction at the particular time, and it also
demonstrates whether sufficient effective housing land is available to meet the
requirement for maintaining a continuous five year supply. In preparing the annual
audit, planning authorities are encouraged to consult widely with the house-building
industry. I note that Stirling Council did so, and reached agreement on the future
programming of construction on all of the sites included in the 2017 annual audit.
16. The council’s conclusion was that the audit confirmed that the effective housing
land supply exceeded the five years’ requirement. I note that the methodology it
applied broadly reflected that contained in the Scottish Government’s draft delivery
advice which has now been withdrawn. However it has not yet been replaced with
an alternative methodology. I also consider that it is clear from Planning Advice
Note 2/2010 that the responsibility for undertaking the annual audit rests with the
planning authority and, while it is expected to consult widely, it is not required to
obtain agreement to its conclusions. In these circumstances I am not in a position to
contradict the council’s conclusion that its 2017 annual housing land audit confirms
that the commitment to maintaining a five years’ effective housing land supply is
currently being met.
17. For the avoidance of doubt, I do not consider that the conclusions of the reporter
who recently examined the proposed local development plan are of direct relevance
to the determination of this planning application. Her task in assessing how much
housing land should be allocated for housing development in the next Stirling local
development plan to cover the period to 2027 was different from that which is before
me. My task in this appeal is to decide whether there is currently (or at least at the
base date of the 2017 audit) a shortfall in the effective housing land supply for the
next five years which might justify granting planning permission. The findings of the
2018 annual audit will reflect the changes which have occurred, and different
conclusions may then be drawn.
Submissions
Appellants
Ground 1
[112]       The Reporter abdicated her responsibility to determine whether or not there was a
shortfall in the five year effective housing land supply. While as a matter of planning
judgment she may have been entitled to accept the Council’s methodology as reasonable, on
a fair reading of the decision, the Reporter simply considered herself bound by the Council’s
Page 12 ⇓
12
findings. That was not an exercise of judgment; it was a misdirection and an erroneous
fettering of her responsibility as decision maker. The respondents’ contention that the
Reporter would have reached the same conclusion on the basis that she considered the
application did not contribute to sustainable development was an impermissible invitation
to the court to make a planning judgment as to the weight that would be applied to the lack
of an effective 5-year supply.
Ground 2
[13]       The Reporter failed to take account of the decisions of reporters and the respondents
in previous planning appeals or, in the alternative, if she did take them into account, she
failed to explain why she disagreed with them in relation to the correct methodology.
Policies should be consistently applied and previous decisions concerning matters of
national policy are capable of being material considerations, that is, “like cases should be
decided in a like manner”. Three recent decisions, one of which was accepted and adopted
by the respondents, concerning the methodology, and in particular whether it should take
account of past completions, were clearly material in view of the withdrawal of the Draft
Advice on the appropriate methodology. The Reporter came to a different conclusion on the
methodology from other Reporters, including the Examination Reporters, and the
respondents. The issues in those decisions were sufficiently closely related to the present
appeal that she should have had regard to them and explained why she was not following
them or why they were distinguishable.
[14]       The Reporter failed to deal with the relevant conclusions of the Examination
Reporters, which had been raised by the appellants; in particular, the conclusions on the
methodologies for calculating the effective housing land supply and any shortfall. It is at
Page 13 ⇓
13
least arguably illogical to suppose that a different methodology should be used for housing
need in development plan terms, on the one hand, and development management, on the
other. Whether under-supply and past completions should be taken into account affected
the whole area and should not change depending on the facts and circumstances of the
planning application. The respondents do not refer to any particular decisions in support of
the assertion that there were decisions indicating that past completions should not be taken
into account. If the Reporter took account of any such decisions, for which there was no
basis in the evidence, that would have been unfair and would give rise to a further ground
of challenge.
Respondents
Ground 1
[15]       Whether or not there was a 5-year supply of effective housing land was a matter of
planning judgment for the Reporter, as was the methodology to be used in calculating it in
the circumstances of a particular case. The Reporter, in exercising her judgment in respect of
both of these matters, did not act wholly unreasonably, which is the applicable standard of
review. The methodology was in accordance with the Draft Advice published by the
respondents; the withdrawal of the Draft Advice did not imply that the method proposed
was inappropriate.
[16]       As the appellants accept, the Reporter was correct that the conclusions of the
Examination Reporters were not of direct relevance to the application. The Reporter knew
that the proposed development plan process was considering the appropriate future
allocation. The new LDP would require to allocate sufficient land for housing to ensure a 5-
year supply when it was adopted. The Examination Reporters had identified the Site as a
Page 14 ⇓
14
possible housing land allocation, but concluded that it should not be allocated within the
forthcoming LDP, notwithstanding that she was considering recommending additional sites
to meet the housing land supply requirement. It was a matter of planning judgement in the
circumstances whether to include past under-delivery.
[17]       The Reporter did not abdicate her responsibility to make a decision on whether the 5-
year supply was met: she accepted that it was on the basis of the 2017 Housing Land Audit
and the submissions of the Council. She did give reasons, on which she was entitled to place
considerable weight: she acknowledged that the methodology was a matter of dispute, that
the 2017 HLA was recent and had been agreed, and that the evidence provided by the
appellants (including the previous appeal decisions) did not contradict it.
Ground 2
[18]       Each planning appeal required to be determined on its own facts and circumstances.
The extent to which previous decisions were relevant material considerations was limited.
Only if the issue and the facts were sufficiently closely related did any regard require to be
had to a previous decision. The extent of the material consideration that required to be
taken into account as a result of the appellants’ submissions in relation to previous decisions
was that the methodology was a matter of dispute. The appellants’ three examples are not
sufficiently closely related to amount to relevant material considerations that required a
detailed explanation distinguishing them from the present appeal. Further, there are dozens
of decisions in which the respondents or a Reporter have required to decide whether there
was a 5-year effective supply, and to determine the appropriate methodology. In the cases
of DLA Delivery Ltd v Secretary of State for Communities and Local Government [2018] EWCA
Civ 1305 and Hallam Land Management Limited v Scottish Ministers [2014] CSIH 110A, the
Page 15 ⇓
15
policies which were required to be consistently applied were clearly more closely related to
the relevant previous decisions in terms of the particularity of the policies under
consideration and being within the same planning authority area. DLA implied that a
decision-maker was required to take into account his previous decisions if the issues were
sufficiently similar, even if they were not specifically brought to his attention.
[19]       In any event, it was clear that the evidence on effective supply presented to the
Reporters in the other appeals was materially different to the equivalent evidence in the
present appeal. Other previous decisions did reach different conclusions in relation to the
methodology, for example, PPA-200-2035: Tower Farm, Torrance. This court cannot
consider all the different decisions in relation to this general matter and discern an
established consistent approach that required to be distinguished if it is not being followed.
Regardless, the three decisions referred to did not create a precedent; indeed, they also
recognised that there was no definitive method endorsed by the respondents. In particular,
the Reporter in the Murieston Road Appeal concluded that whether there needed to be a
standard methodology and, if so, which one, is largely a policy matter for the respondents.
She also recognised that an up to date HLA is a very important tool in establishing the
effective land supply. In that appeal, the latest agreed HLA was 3 years out of date and in
those circumstances she could not agree that it was the only definitive assessment of the
effective supply. Similarly, in PPA-400-2071: Wellhead Farm, the Reporter also noted that
the latest HLA agreed between the Council and Homes for Scotland was 3 years out of date.
The 2016 HLA he referred to was not agreed and he had concerns about its robustness and
credibility. In PPA-320-2118: Hornshill Farm Road, there was no up to date agreed HLA, the
accuracy of the latest HLA was disputed and the LDP was out of date.
Page 16 ⇓
16
Decision
[20]       As noted above (para [10]), the Reporter identified only one key issue in this appeal,
namely whether there was a shortfall in the five years’ effective housing land supply which
might justify approval of the proposed housing development, despite the appeal site’s
location within the green belt and the spacial strategy of the local development plan. Both
parties agreed that this was indeed the key issue, and that the Reporter was correct to
identify it as such.
[21]       The dispute between the parties before this court (and between the appellants and
the Council before the Reporter) focussed on the proper methodology for assessing whether
there was a shortfall in the five years’ effective housing land supply, and if so, the extent of
such shortfall. The appellants maintained before the Reporter, and before this court, that the
correct methodology was to take account of past completions and any past under supply
when determining whether there was a 5-year supply of effective housing land. The
position adopted by the Council before the Reporter was that past under supply and
completions should not be taken into account when assessing the 5-year effective land
supply.
[22]       The differences in methodology may be significant as was recognised by the
Council in its Housing Land Audit 2016. Page 16 of that document sets out the two
alternative methodologies in table 9a and 9b, together with a commentary on methods of
calculation, as follows:
Page 17 ⇓
Table 9a Five Year Effective Land Supply
Period 1 Phase 1 Requirement
4083
Period 1 Phase 2 Requirement
2010/11 2011/12 2012/13 2013/14
2014/15 2015/16 2016/17 2017/18 2018/19 2019/20
2020/21 2021/2022
2022/2023
Actual Completions
Programmed Completions
344
306
247
321
322
368
258
260
393
562
552
531
578
Total Completions
1908
5 Year Effective Programming
2025
Housing Land Requirement
5 Year Effective Land Supply Target
Years
3.9
Supply
Gain/Shortfall
Units
2605
-580
Completions and Programmed Completions for
Development Plan Period
Predicted Gain/Shortfall Units
1993
2023/2024
552
6076
5594
-482
Table 9b Five Year Effective Land Supply
Period 1 Phase 1 Requirement
4083
Period 1 Phase 2 Requirement
2010/11 2011/12 2012/13 2013/14
2014/15 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 2021/2022 2022/2023
Actual Completions
Programmed Completions
344
306
247
321
322
368
258
260
393
562
552
531
578
Total Completions
1908
5 Year Effective Programming
2025
Housing Land Requirement
5 Year Effective Land Supply Target
Years
4.9
Supply
Gain/Shortfall
Units
2080
-55
Completions and Programmed Completions for
Development Plan Period
Predicted Gain/Shortfall Units
1993
2023/2024
552
6076
5594
-482
SPP requires that planning authorities maintain a 5 year supply of Effective Land at
all times. The precise method of calculation is disputed, with varying approaches
being demonstrated across Scotland at both the local and national level. At time of
publication there was no finalised guidance from the Scottish Government in place.
This audit presents both the previous approach used by this authority to calculate
the supply and the approach utilised by the Scottish Government when reporting
figures through the Planning Performance Framework (PPF).
Table’s 9a and 9b highlight the significant differences in approach, with a full year’s
supply differing between the methods and leads to a shortfall of either 55 units or
580. In any event the Stirling Council is not maintaining a 5 year supply, albeit that
the approach used by the PPF is extremely close to a 5 year supply. However, the
Council has published a Proposed LDP which identifies further land for
development. As outlined in section 3 many of these sites have not been included in
this audit, it is therefore important to note that supply over the next 5 years is likely
to increase and the Proposed Plan ensures a 5 year supply at adoption.
The calculation method used in Table 9a has been used for the current plan period.
As the LDP 2014 is still in place as the adopted plan, this is the methodology that is
used to assess compliance with SPP 2014. The calculation in Table 9b is provided for
Page 18 ⇓
18
information only at this point, pending updated guidance on this matter from the
Scottish Government and the examination of the Proposed Plan.”
[23]       It will be seen from the above that in their 2016 Housing Land Audit the calculation
methodology used was that in Table 9a, which resulted in a shortfall of 580 units and an
effective housing land supply of 3.9 years. In their 2017 Housing Land Audit the Council
changed their methodology and effectively adopted the method of calculation shown in
Table 9b. This method of calculation, which left out of account previous under supply,
resulted in a figure of 5.3 years supply of effective land, and a surplus of 137 units. The
justification which the Council provided in their 2017 Housing Land Audit was as follows:
SPP requires that planning authorities maintain a 5 year supply of Effective Land at
all times. The precise method of calculation is disputed, with varying approaches
being demonstrated across Scotland at both local and national level, and the private
sector. At the time of publication there was no finalised guidance from the Scottish
Government in place. This audit utilises the calculation method as outlined in the
Planning Performance Framework.
Table 9 demonstrates that Stirling Council is maintaining a 5 year supply of housing
land as required by SPP, with evidence of a 5.3 year supply.”
No further explanation for the change in the Council’s methodology was given. The
appellants disputed this methodology before the Reporter.
[24]       There was therefore a stark dispute between the parties about methodology. The
appellants’ calculation, as stated in their statement of appeal to the Reporter, and which took
into account previous under delivery and past completions, resulted in 3.87 or 4.49 years of
effective land supply, and the Council relied on its 2017 Housing Land Audit which gave a
result of 5.3 years supply. The Reporter noted that there was a dispute as to the appropriate
methodology but did not seek to resolve that dispute or determine the issue.
Page 19 ⇓
19
[25]       We agree with the submission of the appellants that this was an issue with which the
Reporter required to grapple, and to reach a determination. She had identified that the key
issue in the appeal was whether there was a shortfall in the 5 years effective housing land
supply. In order to decide this issue, we consider that she had to reach a view as to which of
the competing methodologies she preferred, and to give reasons for her decision. There
were alternative methods of calculation before her, and she was not bound to accept the
calculation advanced by the Council in preference to that advanced by the appellants.
Although she referred to Planning Advice Note 2/2010, nothing in that Advice Note obliged
her to accept the methodology adopted by the Council. The appellants categorised the
statement by the Reporter (in paragraph 16) that:
In these circumstances I am not in a position to contradict the Council’s conclusion
that its 2017 Annual Housing Land Audit confirms that the commitment to
maintaining a 5 years effective housing land supply is currently being met”
as an abdication of her responsibility to determine the key issue. We agree with this
categorisation.
[26]       The respondents submitted that the Reporter was entitled to reach this conclusion,
and that this was a matter of planning judgment. However, it does not appear to us that the
Reporter exercised any planning judgment on this issue; instead, she considered herself
bound by the Council’s methodology, and gave no adequate reasons for taking this view.
[227]       We therefore consider that the appellants’ first ground of challenge must succeed.
[28]       The appellants’ second ground of challenge was that the Reporter erred in law by
failing to take account of the decisions of the reporters and the Scottish Ministers in other
planning appeals, and of the Reporter in the examination of the proposed Stirling Council
LDP in November 2017. Senior counsel for the appellants accepted that these were not
binding precedents, and further accepted that the Reporter into the proposed LDP was
Page 20 ⇓
20
engaged in a different exercise from that facing the Reporter in the present appeal and that
the conclusions with regard to the proposed LDP were not directly relevant. However, he
submitted that the circumstances in these other proceedings were sufficiently similar that
they amounted to material considerations to which the Reporter ought to have had regard.
[29]       We emphasise that each planning application, and each appeal to the Scottish
Ministers, requires to be considered on its own facts and circumstances; there is no question
of previous decisions constituting a precedent by which reporters in further appeals will be
bound. However, previous decisions of the Scottish Ministers or their reporters on planning
appeals are capable of being material considerations DLA Delivery Limited v Secretary of
State for Communities and Local Government [2018] EWCA Civ 105 at paragraph 29; North
Wiltshire District Council v Secretary of State for the Environment (1993) 65 P & Cr 137 at 145;
Hallam Land Management Limited v Scottish Ministers [2014] CSIH 110A.
[30]       Of course, in many planning appeals the issues will be site specific and the decision
in one appeal may carry little, if any, significance in another appeal. It will always be open
to a reporter to distinguish the circumstances of an earlier appeal, provided that adequate
reasons are given for the distinction. As it was put by Mann LJ in North Wiltshire District
Council (at 145):
"... It was not disputed in argument that a previous appeal decision is capable of being
a material consideration. The proposition is in my judgment indisputable. One
important reason why previous decisions are capable of being material is that like cases
should be decided in a like manner so that there is consistency in the appellate
process. Consistency is self-evidently important to both developers and development
control authorities. But it is also important for the purpose of securing public
confidence in the operation of the development control system. I do not suggest and it
would be wrong to do so, that like cases must be decided alike. An inspector must
always exercise his own judgment. He is therefore free upon consideration to disagree
with the judgment of another but before doing so he ought to have regard to the
importance of consistency and to give his reasons for departure from the previous
decision.
Page 21 ⇓
21
To state that like cases should be decided alike presupposes that the earlier case is
alike and is not distinguishable in some relevant respect. If it is distinguishable then
it usually will lack materiality by reference to consistency although it may be material
in some other way. Where it is indistinguishable then ordinarily it must be a material
consideration. A practical test for the inspector is to ask himself whether, if I decide
this case in a particular way am I necessarily agreeing or disagreeing with some
critical aspect of the decision in the previous case? The areas for possible agreement
or disagreement cannot be defined but they would include interpretation of policies,
aesthetic judgments and assessment of need. Where there is disagreement then the
inspector must weigh the previous decision and give his reasons for departure from
it. These can on occasion be short, for example in the case of disagreement on
aesthetics. On other occasions they may have to be elaborate.”
[31]       In R v Secretary of State for the Environment ex parte Baber [1996] JPL 1034,
Glidewell LJ (at page 1040) suggested a slightly different question for the decision-maker,
which was:
“’ [A] previous decision having been drawn to my attention, do I take the view that
it may well be sufficiently closely related to the matters in issue in my appeal that I
ought to have regard to it and either follow it or distinguish it?. Morritt L.J. (at
p.1041) framed the question slightly differently again: May the earlier decision be
sufficiently related to the decision I have to make? That is something that I should
properly comment on either following or, if disagreeing, saying why’.”
(See also Lindblom LJ in DLA Delivery Limited (supra) at paragraph 34.)
[32]       These considerations apply with particular force in an appeal such as the present, in
which the issue was agreed to relate to methodology rather than to particular site specific
circumstances.
[33]       The appellants in the present case placed before the Reporter three decisions of other
reporters in other local authority areas, which grappled with the same issue. In each of these
decisions one of the issues was the appropriate methodology to calculate the effective
housing land supply, and whether past completions should be taken into account in
calculating the 5 year requirement for the future. In other words, there was the same
Page 22 ⇓
22
dispute as to methodology as there was in the present case.
[34]       The first of these decisions related to an appeal regarding an application for
residential development at Murieston, Livingston. The decision by the reporter in that
appeal was dated 16 August 2017. At paragraph 3.56 of his decision the reporter observed
that:
In determining the housing land requirement for the period to 2009/19, the Council
takes no account of the number of completions achieved to date. Therefore, the
annual requirement of 1142 units stays the same regardless of what development
progress has been made to date, resulting in a 5 year requirement of 5710 units. The
appellants’ housing land requirement is net of completions, providing a residual
annual requirement of 2024 units resulting in a 5 year requirement of 10122 units.”
So the dispute as to methodology was the same as in the present case.
[35]       At paragraph 3.58 the reporter in the Murieston appeal observed as follows:
“I consider the purpose of maintaining a 5-year effective supply is to make it more
likely that the development plan’s overall housing land requirement is met. In doing
so, it is clear that previous completions should be considered in the calculation. The
only reason I can see why this would not be the case is for policy reasons.”
[36]       At paragraph 3.66 he observed:
“Whether there needs to be a standard method for calculating the 5-year effective
land supply and if so, what method, is largely a policy matter. My understanding is
that Scottish Ministers intend to publish policy guidance and replace PAN 2/2010.
However, at the time of submitting my report, no further actions have been made in
this regard. Scottish Ministers are invited to consider my assessment and
conclusions in this context.”
[37]       In giving his conclusions on housing land supply, he stated at paragraph 3.93:
“The purpose of having a 5-year supply of effective housing land is to achieve a
particular development plan based housing land requirement. In this regard, previous
completions would need to be considered. However, the actual methodology that
should be adopted to calculate a 5-year supply is essentially a policy matter.”
Page 23 ⇓
23
[38]       The second decision on which the appellants relied before the Reporter was a Notice
of Intention in relation to residential development at Wellhead Farm, Murieston Road,
Livingston. The date of the Notice was 13 November 2017. The Reporter observed at
paragraph 12 of the decision letter:
“Previous decisions on planning appeals are, of course, not binding upon me.
However, conclusions on the interpretation of policy in those decisions are material
considerations in this appeal. Where such conclusions have recently been endorsed
by Ministers, that adds to their weight. Where relevant findings of fact are made,
those findings are evidence in this appeal. I do not, of course, take them as
incontrovertible evidence but consider them in the light of other evidence before
me.”
The Reporter in that case identified the same dispute as to methodology (at paragraph 42),
and then went on to record the similar methodological dispute before the reporter in the
earlier Murieston appeal. He set out the reporter’s reasoning in that earlier appeal,
including her decision that the appellant’s method best addressed the relevant principles,
and that this conclusion was accepted by the Scottish Ministers. He accepted the reasoning
in that decision, and considered that the appellant’s method should be applied to assessing
land supply in the decision which he took.
[39]       The third decision letter relied on by the appellants before the present Reporter was
in relation to residential development at a site at Hornshill Farm Road, Stepps. The decision
letter was dated 17 November 2017. The final decision was taken by the Scottish Ministers,
who agreed with the Reporter’s reasoning. At paragraph 23 the Reporter gave the following
reasoning:
“In circumstances where the annual average supply target is not being met, it follows
that in the absence of any redress in the shortfall, the housing supply target over the
course of the development plan period will not be met. As also noted in Pan 20/2010,
if an audit is to provide an accurate picture of housing land supply, it is necessary to
ensure that the annual completions are recorded accurately and shown in the audit.
Page 24 ⇓
24
I would agree with the appellants that it is essential that the land supply calculation
takes into account the number of completions achieved to date in order to ensure
that the supply target is achieved by the end of the development plan period. “
[40]       Senior counsel for the appellants acknowledged that the exercise in which the
Reporter on the proposed Stirling Local Development Plan was engaged was different from
the exercise in which the Reporter in the present case was engaged. However, he drew our
attention to some of the Reporter’s observations in that report which had some significance
in the present appeal. The Reporter made the following observations:
“40 Following the hearing and closing submissions, and all other written
evidence, I have concluded that the housing land calculation for this plan should be
based on the 2010 evidence base of the HNDA 2011 and should include any surplus
or shortfall of completions from the period 2010 to 2015 in the calculation.
50 The shortfall in delivery in the period 2010 to 2015 remains unaccounted for
in the Council’s proposed method of calculation. While on one hand the calculation
accepts the Housing Supply Target, it then appears to fail to take into account all the
consequences of the same Housing Supply Target in terms of delivery of homes in
Stirling.
51 The primary disagreement between the Council and all other parties on this
issue is whether the shortfall in completions from 2010 to 2015 should be included,
and for the reasons set out above, I conclude that any surplus/shortfall should be
part of the calculation.
52 I find no compelling evidence as required by Scottish Planning Policy or
convincing argument from the Council to support the omission of a shortfall in
completions in Stirling in the period 2010 to 2015.
53 … I find that Scottish Planning Policy at paragraph 115 clearly states that the
Housing Supply Target is ‘a policy view of the number of homes the authority had
agreed will be delivered over the periods of the development plan and local housing
strategy’.
54 Omitting the shortfall in delivery does not appear to achieve any particular
purpose other than to numerically achieve a lower target for this planned period. It
does not address the fundamental issue of Scottish Planning Policy requiring the
target and housing land requirement to be met in full, nor does it account for the
Page 25 ⇓
25
unmet yet identified need and demand for homes in the period 2010 to 2015.”
[41]       We accept that the reporter who prepared the report on the proposed Stirling Local
Development Plan was fulfilling a different role from the Reporter in the present case, but
that report was published not long before the decision in the present appeal was issued, and
the new LDP was adopted shortly after the decision letter in the present appeal. The issues
regarding methodology, and the Reporter’s determination of them, were not identical to the
issues in the present appeal, but they contained notable similarities.
[42]       The respondents drew our attention to the fact that not all of the recent appeal
decisions have been determined in the same way, and pointed to a decision of the Scottish
Ministers in relation to a proposed residential development at Torrance, East
Dunbartonshire. This decision was issued on 31 May 2017, before the Chief Planning
Officer’s withdrawal of the draft guidance.
[43]       The Reporter did refer to the conclusions of the Reporter who recently examined the
proposed local development plan (see paragraph 17 of her report), and explained that she
did not consider these conclusions to be of direct relevance to the determination of this
planning application, because the task of assessing how much housing land should be
allocated in the next LDP to cover the period to 2027 was different from that which was
before her. We accept that difference, although we observe that the reasoning and
conclusions of the Reporter on the new LDP have at least peripheral relevance to the
methodological dispute in the present appeal. However, the Reporter did at least make
reference to the report into the new LDP. She made no reference at all to the three previous
decisions, nor to their reasoning as to the appropriate methodology to be used for assessing
a 5-year supply of effective housing land. We consider that these were material
Page 26 ⇓
26
considerations to which she ought to have had regard. We do not suggest that she was
bound to follow the same reasoning nor to adopt the same methodology for calculating
effective housing land supply or shortfall. However, given that the same issue arose in
those appeals, and that the decisions of the reporters (or, as the case may be, the Scottish
Ministers) was to support the methodology favoured by the appellants, we consider that she
was bound to make reference to these and to explain why in the circumstances she was not
in a position to contradict the Council’s conclusion. She made no reference to these
decisions, nor did she make any attempt to distinguish them. In this respect also we
consider that she erred in law, and the appellants’ second challenge also succeeds.
[44]       In summary, we consider that the Reporter has failed to address the key issue of the
appropriate methodology for assessing whether there was a shortfall in effective housing
land supply which might justify the “tilted” balancing exercise required by SPP paragraphs
33 and 125 Hopkins Homes v Communities Secretary (supra); Grahams the Family Dairy Limited
v The Scottish Ministers (supra). In failing to address this, she fell into error of law. She also
fell into error of law in failing to have regard to material considerations, namely the three
appeal decisions which considered the appropriate methodology for assessing the existence
and extent of any such shortfall. She was not required to follow these as precedents;
however, she required to make reference to them and, if departing from the reasoning in
those appeals, to explain why she was doing so.
[45]       Counsel for the respondents submitted that, even if we were against his primary
submissions and found that the Reporter had fallen into error of law, this court should
exercise its discretion not to quash the Reporter’s decision. He submitted that there was no
realistic prospect that the decision in relation to the appeal would have been different even if
Page 27 ⇓
27
the Reporter had preferred the appellants’ methodology for calculating the 5-year effective
land supply. The proposed development was clearly contrary to the housing policies of the
2014 LDP and the emerging LDP. The Reporter found that the proposed development was
contrary to the purpose of the green belt policy in the area and also that it was contrary to
the spacial strategy of the development plan. At paragraph 18 of her decision she concluded
that the presumption in favour of development that contributes to sustainable development
which was introduced by SPP did not apply. The appellants did not go so far as to submit
that the Reporter was bound to find that there was a shortfall in the 5-year housing land
supply; their complaint was merely that the Reporter did not give adequate reasons for her
preferred methodology. Relying on Hallam Land Management Limited v Scottish Ministers
(supra), counsel for the respondents submitted that the appeal was academic and should be
refused.
[46]       We do not agree. Because of her decision that she was not in a position to contradict
the Council’s conclusion that a 5-year effective housing land supply was currently being
met, she did not address the “tilted” balancing exercise which she might (depending on how
she determined the key issue) have been required to address. Her errors of law went to the
root of the only key issue which she identified, and which both parties agreed was the key
issue. We do not consider that it would be appropriate in the circumstances of this appeal to
exercise our discretion not to quash the decision.
[47]       For these reasons we shall allow the appeal, and quash the decision.



BAILII: Copyright Policy | Disclaimers | Privacy Policy | Feedback | Donate to BAILII
URL: http://www.bailii.org/scot/cases/ScotCS/2019/2019_CSIH_34.html