First-tier Tribunal (General Regulatory Chamber) |
||
You are here: BAILII >> Databases >> First-tier Tribunal (General Regulatory Chamber) >> Dransfield v IC & Devon County Council [2011] UKFTT EA_2010_0152 (GRC) (30 March 2011) URL: http://www.bailii.org/uk/cases/UKFTT/GRC/2011/2010_0152.html Cite as: [2011] UKFTT EA_2010_152 (GRC), [2011] UKFTT EA_2010_0152 (GRC) |
[New search] [Printable PDF version] [Help]
"I now wish to downgrade my FOI request for the Operations Maintenance Manual (OMM) for the ISCA College only. I don't mind if it is via CD or electronic transfer."
"This is a data storage and project management application, understood to be hosted on a university server in the United States, which enables contractors to upload and amend documentation and plans relating to projects, and thereby permit their staff and clients to have access to up-to-date versions of the documents as necessary. Buzzsaw was introduced by the contractors after the contract was signed. Access to documents was largely confined to the build phase of the project and is granted at the contractors' discretion and under their control. DCC also understands that it may be charged for access in some circumstances."
"32. OPERATING MANUAL
The Contractor shall throughout the Operational Period maintain and update an operating and maintenance manual setting out the procedures for providing the Services which if complied with would constitute compliance by the Contractor with its obligations in respect of the Services (the "Operating Manual").
The Contractor shall at the request of the Authority provide the Authority with access to the Operating Manual in order to demonstrate that the Contractor has complied with its obligation to maintain and update the Operating Manual under clause 32.1.
On termination of this Agreement (howsoever arising including expiry) the
Contractor shall within 10 Working Days provide a copy of the Operating Manual to the Authority."
"57. INFORMATION AND CONFIDENTIALITY
The parties shall keep confidential all matters relating to this Agreement and the Project Documents and shall use all reasonable endeavours to prevent their employees and agents from making any disclosure to any person of any matters relating to this Agreement."
"For the purposes of this Act, information is held by a public authority if-
(a) It is held by the Authority, otherwise than on behalf of another person, or
(b) It is held by another person on behalf of the Authority"
Judge Christopher Hughes
30 March 2011