BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just Β£1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Commercial Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Commercial Court) Decisions >> Jiangsu Guoxin Corporation Ltd v Precious Shipping Public Co Ltd [2020] EWHC 1030 (Comm) (30 April 2020) URL: http://www.bailii.org/ew/cases/EWHC/Comm/2020/1030.html Cite as: [2021] 1 Lloyd's Rep 413, [2020] EWHC 1030 (Comm), [2020] BLR 653, [2020] 1 CLC 762 |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
QUEEN'S BENCH DIVISION
COMMERCIAL COURT
IN THE MATTER OF THE ARBITRATION ACT 1996
AND IN THE MATTER OF APPLICATIONS UNDER
SECTION 69 OF THE ARBITRATION ACT 1996
AND IN THE MATTER OF TWO ARBITRATION CLAIMS
Fetter Lane, London, EC4A 1NL |
||
B e f o r e :
____________________
JIANGSU GUOXIN CORPORATION LTD (formerly known as SAINTY MARINE CORPORATION LTD) |
Claimant |
|
- and - |
||
PRECIOUS SHIPPING PUBLIC CO. LTD |
Respondent |
____________________
Roderick Cordara QC, Adam Board and Andrew Dinsmore (instructed by Watson Farley and Williams LLP) for the Respondent
Hearing dates: 18 March 2020
____________________
Crown Copyright ©
Mr Justice Butcher:
The Contracts
Factual Background
The Dispute in Outline
(1) That the 'prevention principle' applies. It contends that time was set 'at large' as a result of what it contends was the unlawful rejection of hulls 17B-20B, which had resulted in the occupation of berths at the yard and the delay of Hulls 21B and 22B, and constituted an act of wrongful prevention on the part of the Buyer; and/or
(2) That there had not been 150 days of 'non permissible delay' by the time of the Buyer's purported termination. It contends that construction was delayed and, to the extent relevant, it is entitled to an extension of time, due to (i) late payment by the Buyer of instalments of the Contract Price; (ii) investigations and modifications in relation to the stern tube bearing issue; and (iii) the effect of the cancellation of the contracts for hulls 17B-20B.
(1) The SBCs provide a complete code of the circumstances in which the Seller was entitled to claim extensions of time. The relevant contractual machinery had never been exercised to extend time, and therefore the Seller was not entitled to an extension, even if (which the Buyer denied) it would otherwise have been entitled to such an extension.
(2) There is no room for the 'prevention principle' on the facts of these cases.
The Awards
(1) 'Was the Seller entitled to extend the Delivery and/or Cancellation Date in circumstances where it failed to and/or did not operate, and/or exercise any relevant contractual machinery (including Article XI of the SBC)?' This was referred to as 'the Second Issue'.
(2) 'Is there any scope for the application of the prevention principle in light of the express terms of the SBC (including relevant arguments on implied terms)?' This was referred to as 'the Third Issue'.
(1) Whether a failure to serve a notice under Article VIII.2 allows the Buyer to ignore permissible delay in the calculation of the cancellation date.
(2) Whether service of a notice under Article VIII.2 is a condition precedent to any extension of time under Article V.1 or Article XI.4(a).
(3) If not: (i) in case of a modification under Article V, if no agreement is reached as to the extension of time for delivery, whether the Seller is prevented from claiming any such extension of time; and (ii) in case of a default by the Buyer, whether the Seller needs to do anything in order to postpone the Delivery Date under Article XI.4(a).
(1) In relation to the first sub-issue, that the notice provision in Article VIII.2 applies when the Seller claims that it is entitled to an extension of time for delivery under Article VIII.1. The tribunal said, in paragraph [67] of the awards: 'We do not think that the parties can possibly have intended that the notice provision in Article VIII.2 should not apply just because the delay fell within Article VIII.1 and was therefore a permissible delay'. Accordingly, unless the Seller served the notices for which Article VIII.2 provided, it was not entitled to an extension of the Delivery Date. On this point, the tribunal agreed with the analysis of Leggatt J in paragraphs [63]-[68] of Zhoushan, where he considered the case on the hypothesis that buyer's breach delays were potentially within Article VIII.1.
(2) In relation to the second sub-issue, the tribunal considered that Article VIII.2 was capable of applying more generally than to delays within Article VIII.1, but it should not be applied to other provisions 'which either have their own notice provision or where a notice under Article VIII.2 is not necessary to make the SBC work'. However, if there were no such separate provision, and a notice was necessary to make the SBC work, then Article VIII.2 was applicable irrespective of whether the delay was within Article VIII.1. In this respect the tribunal disagreed with the view of Leggatt J in paragraph [70] of Zhoushan, and agreed with the award published as London Arbitration 9/13 in LMLN on 29.5.2013. The tribunal considered that Article V.1 and Article XI.4 (a) were each cases of other provisions which did have their own notice requirements or where a notice under Article VIII.2 was not necessary, and accordingly Article VIII.2 was not applicable. By contrast, the tribunal considered that the Article VIII.2 regime was applicable to Article III.1(c).
(3) In relation to the first part of the third sub-issue, the tribunal considered that, in a situation in which the parties had not reached an agreement on the relevant modification, and on any consequential change in the Contract Price and Delivery Date, but the Seller had nevertheless carried out the modification, the Seller needed to serve a notice under Article VIII.2, and if it did not do so, would be prevented from claiming an extension of time.
(4) In relation to the second part of the third sub-issue, the tribunal concluded that in the case of Buyer's Default, the Seller has to communicate that it is exercising its option to postpone the Delivery Date for the period of continuance of the Buyer's Default under Article XI.4(a), but does not have to serve notices under Article VIII.2.
(1) In relation to 'the Second Issue', that the answer was 'No the Seller was not entitled to extend the Delivery and/or Cancellation Date in circumstances where it failed to and/or did not operate, and/or exercise any relevant contractual machinery'.
(2) In relation to 'the Third Issue', that the answer was 'No there is no scope for the application of the prevention principle in light of the express terms of the SBC (including relevant arguments on implied terms).'
The Hearing of the Appeals
Legal Background
Implied terms as to prevention
The 'Prevention Principle'
[10] In the 19th century, the courts concluded that it was wrong in principle for an employer to hold a contractor to a completion date, and a concomitant liability to pay liquidated damages, in circumstances where at least a part of the subsequent delay was caused by the employer. Thus, in Holme v Guppy (1838) 3 M&W 387, the defendant failed to give possession of the site for four weeks following execution of the contract. Parke B found that there were clear authorities to the effect that 'if the party be prevented by the refusal of the other contracting party from completing the contract within the time limited he is not liable in law for the default '
[11] Similarly in Dodd v Churton [1897] 1 QB 566, where the employer ordered extra work which delayed completion. Lord Esher said:
'... where one party to a contract is prevented from performing it by the act of the other, he is not liable in law for that default; and accordingly a well-recognised rule has been established in cases of this kind, beginning with Holme v Guppy, to the effect that, if the building owner has ordered extra work beyond that specified by the original contract which has necessarily increased the time requisite for finishing the work, he is thereby disentitled to claim the penalties for non-completion provided by the contract.'
[12] As a result of these decisions, construction contracts began to incorporate extension of time clauses, which provided that, on the happening of certain events (which included what might generically be described as 'acts of prevention' on the part of the employer), the date for completion under the contract would be extended, so that liquidated damages would only be levied for the period after the expiry of the extended completion date. Such clauses were not, as is sometimes thought, designed to provide the contractor with excuses for delay, but rather to protect employers, by retaining their right both to a fixed (albeit extended) completion date and to deduct liquidated damages for any delay beyond that extended completion date.
[56] From this review of authority I derive three propositions:
(i) Actions by the employer which are perfectly legitimate under a construction contract may still be characterised as prevention, if those actions cause delay beyond the contractual completion date.
(ii) Acts of prevention by an employer do not set time at large, if the contract provides for extension of time in respect of those events.
(iii) In so far as the extension of time clause is ambiguous, it should be construed in favour of the contractor.
[57] The third proposition must be treated with care. It seems to me that, in so far as an extension of time clause is ambiguous, the court should lean in favour of a construction which permits the contractor to recover appropriate extensions of time in respect of events causing delay. This approach also accords with the principle of construction set out by Lewison in The Interpretation of Contracts (3rd edition, 2004). That principle reads as follows:
Where two constructions of an instrument are equally plausible, upon one of which the instrument is valid and upon the other of which it is invalid, the court should lean towards that construction which validates the instrument.
[58] That principle is supported by a line of authority as set out in para. 7.14 and is encapsulated in the latin maxim verba ita sunt intelligenda, ut res magis valeat quam pereat.
[242] The authorities on the prevention principle show that:
(1) In a basic shipbuilding contract, which simply provides for a Builder to complete the construction of a vessel and to reach certain milestones within specific periods of time, the Builder is entitled to the whole of that period of time to complete the contract work.
(2) In the event that the Buyer interferes with the work so as to delay its completion in accordance with the agreed timetable, this amounts to an act of prevention and the Builder is no longer bound by the strict requirements of the contract as to time.
(3) The instruction of variations to the work can amount to an act of prevention.
[243] However, as Jackson J stated in the Multiplex v Honeywell case, the prevention principle does not apply if the contract provides for an extension of time in respect of the relevant events. Where such a mechanism exists, if the relevant act of prevention falls within the scope of the extension of time clause, the contract completion dates are extended as appropriate and the Builder must complete the work by the new date, or pay liquidated damages (or accept any other contractual consequence of late completion)...
(2) It avoids the unsatisfactory consequence of the parties being in a contractual 'limbo'.
(3) It is inherently unlikely that the parties would have intended there to be such a 'limbo', particularly in an obviously foreseeable situation such as a failure to agree an adjustment.
(4) This is all the more so given the potentially extreme circumstances of the application of the prevention principle, as explained by Colman J in Balfour Beatty v Chestermount Properties (1993) 62 BLR 1, 27. A trivial variation may lead to the loss of the right to liquidated damages for a long period of culpable delay and, in this case, loss of the right to rescind as well.
(7) As stated by Jackson J in Multiplex v Honeywell where there is ambiguity the court should lean in favour of a construction which makes the contract work.
Analysis
Is there room for the 'prevention principle' to apply?
Notification: The Ambit of Article VIII.2
As [counsel for the buyers] showed, the contract wording is replete with provisions requiring any extension of the delivery date to be communicated and agreed between the parties (or ascertained by arbitration). Furthermore the operation of the cancellation clauses depends on the parties knowing where they stand. Those provisions depend for their efficacy on the parties being able to calculate with precision and know at any given time how many days of (i) permissible delay and (ii) non-permissible delay have occurred. The parties could no doubt have made a contract which left them each to perform their own calculation and then argue about the causes of delay after a cancellation has occurred. However, they have tried to avoid such an anarchic situation. Instead, they have adopted a scheme which provides for notices to be given and agreement reached, or any dispute resolved by arbitration if necessary, whenever an event occurs which the Yard wishes to say justifies an extension of time for delivery.
Modifications
Buyer's Default in Payments
Conclusion
APPENDIX
ARTICLE II WARRANTY OF QUALITY
1
2 TERMS OF PAYMENT:
The CONTRACT PRICE shall be paid by the BUYER to the SELLER in installments as follows:
(c) Third Installment
The sum of United States Dollars Two Million Seven Hundred and Ninety Thousand only (US$2,790,000.00), representing ten percent (10%) of the CONTRACT PRICE should become due and payable and be paid by the BUYER to the SELLER within five (5) Banking Days after (i) the keel laying for the VESSEL as evidenced by the Class that the number of blocks, not less than 10 blocks of about 50 tonnes each, have been laid in the dry-dock from which the VESSEL will be launched, and (ii) the BUYER'S receipt of the Third Installment Refund Guarantee in the form annexed hereto as Exhibit 'A' issued by the SELLER's bank acceptable to the BUYER via authenticated SWIFT
The date stipulated for payment of each of the installments mentioned above is hereinafter in this Article and in Article XI referred to as the 'Due Date' of that installment.
ARTICLE III ADJUSTMENT OF THE CONTRACT PRICE
The CONTRACT PRICE of the VESSEL shall be subject to adjustments as hereinafter set forth.
1 DELIVERY
(a)No adjustment shall be made, and the CONTRACT PRICE shall remain unchanged for the Thirty (30) days of delay in delivery of the VESSEL beyond the Delivery Date as defined in Article VII hereof ending as of twelve o'clock midnight Chinese Standard Time of the Thirtieth (30th) day of delay.
(b)If the delivery of the VESSEL is delayed more than Thirty (30)days after the date as defined in Article VII hereof, then, in such event, beginning at twelve o'clock midnight Chinese Standard Time of the Thirtieth (30th) day after the date on which delivery is required under this Contract, the CONTRACT PRICE of the VESSEL shall be reduced as follows by the sum of United States Dollars as follows:-
In case the days of delay are more than 30 days:
From the 31st to 60th day USD 7,500.- per day
From the 61st to 90th day USD 10,000.- per day
From the 91st to 180th day USD 12,500.- per day
Unless the parties hereto agree otherwise, the total reduction in the CONTRACT PRICE shall be deducted from the Final Installment of the CONTRACT PRICE and in any event (including the event that the BUYER consents to take the VESSEL at the later delivery date after the expiration of One Hundred and Eighty (180) days delay of delivery as described in Paragraph 1(c) of this Article or in Paragraph 3 of Article VIII) shall not be more than United States Dollars One Million Six Hundred Fifty Thousand Only (USD 1,650,000.-) being the maximum.
(c) If the delay in the delivery of the VESSEL continues for a period of one Hundred and Fifty (150) days (being the total of non permissible delays and excluding extension of delivery date by reason of causes and provisions of Article V, VI, XI, XII and XIII hereof and the delays by reason of permissible delays as defined in Article VIII hereof) after the Delivery Date as defined in Article VII, then in such event, the BUYER may, at its option, rescind or cancel this Contract in accordance with the provisions of Article X of this Contract by written notice to the SELLER at any time after the expiration of the said one Hundred and Fifty (150) days period.
(d) For the purpose of this Article, the delivery of the VESSEL shall not be deemed delayed and the CONTRACT PRICE shall not be reduced when and if the Delivery Date of the VESSEL is extended by reason of causes and provisions in Articles V, VI, XI, XII, and XIII hereof. The CONTRACT PRICE shall not be reduced if the delivery of the VESSEL is delayed by reason of permissible delays as defined in Article VIII hereof. However, notwithstanding anything stated herein, if the total delay (inclusive of all permissible and non-permissible delays as mentioned in this Contract exceeds One Hundred and Eighty (180) days from the Contractual delivery date as mentioned in Article VII of the Contract, BUYER shall be entitled to rescind the Contract and claim the refund of advance payments as provided in the Contract.
ARTICLE V MODIFICATION, CHANGES AND EXTRAS
1 HOW EFFECTED
The Specifications and Plans in accordance with which the Vessel is constructed, may be modified and/or changed at any time hereafter by written agreement of the parties hereto, provided that such modifications and/or changes or an accumulation thereof will not, in the SELLER's reasonable judgment, adversely affect the SELLER's other commitments and provided further that the BUYER shall assent to adjustment of the Deadweight and capacity, CONTRACT PRICE, time of delivery of the VESSEL and other terms of this Contract, if any, as hereinafter provided. Subject to the above, the SELLER hereby agrees to exert its best efforts to accommodate such reasonable requests by the BUYER so that the said changes and/or modifications may be made at a reasonable cost and within the shortest period of time which is reasonable and possible. Any such agreement for modifications and/or changes shall include an agreement as to the increase or decrease, if any, in the CONTRACT PRICE of the VESSEL together with an agreement as to any extension or reduction in the time of delivery, providing to the SELLER additional securities satisfactory to the SELLER, or any other alterations in this Contract, or the Specifications occasioned by such modifications and/or changes. The aforementioned agreement to modify and/or to change the Specifications may be effected by an exchange of duly authenticated letters, or telefax, or e-mail, manifesting such agreement. The letters, telefaxes and e-mails exchanged by the parties hereto pursuant to the foregoing shall constitute an amendment of the Specifications under which the VESSEL shall be built, and such letters, telefaxes and e-mails shall be deemed to be incorporated into this Contract and the Specifications by reference and made a part hereof. Upon consummation of the agreement to modify and/or to change the Specifications, the SELLER shall alter the construction of the VESSEL in accordance therewith, including any additions to, or deductions from, the work to be performed in connection with such construction. If due to whatever reasons, the parties hereto shall fail to agree on the adjustment of the CONTRACT PRICE or extension of time of delivery or providing additional security to the SELLER or modification of any terms of this Contract which are necessitated by such modifications and/or changes, then the SELLER shall have no obligation to comply with the BUYER's request for any modification and/or changes and the BUYER shall take delivery of the VESSEL as the VESSEL is pursuant to the terms and provisions of the Contract.
4 BUYER'S SUPPLIED ITEMS
The BUYER shall deliver to the SELLER at its shipyard the items specified in the Specifications which the BUYER shall supply on BUYER's account by the time designated by the SELLER. The SELLER shall at all times if requested (whether by the Supervisor or otherwise) provide all reasonable assistance to the BUYER in connection with any formal documentary, customs, or other requirements of the People's Republic of China in connection with the import into the People's Republic of China of the BUYER's supplied items.
Before the BUYER's supplied items enter the People's Republic of China, the BUYER shall provide necessary, reasonable documentation and guidance or make an appropriate plan together with the SELLER. Should the BUYER fail to deliver to the SELLER such items within the time specified, the delivery of the VESSEL shall automatically be extended for a period of such delay, provided such delay in delivery of the BUYER's supplied items shall affect the delivery of the VESSEL. In such event, the BUYER shall pay to the SELLER all losses and damages sustained by the SELLER due to such delay in the delivery of the BUYER's supplied items and such payment shall be made upon delivery of the VESSEL.
Furthermore, if the delay in delivery of the BUYER's supplied items should exceed fifteen days, the SELLER shall be entitled to proceed with construction of the VESSEL without installation of such items in or onto the VESSEL, without prejudice to the SELLER's right hereinabove provided, and the BUYER shall accept the VESSEL so completed.
ARTICLE VI TRIALS
1 NOTICE
The BUYER and the Supervisor shall receive from the SELLER at least twenty (20) days notice in advance and seven (7) days definite notice in advance in writing or by telefax or e-mail confirmed in writing, of the time and place of the VESSEL's sea trial as described in the Specifications (hereinafter referred to as 'the Trial Run') and the BUYER and the Supervisor shall promptly acknowledge receipt of such notice. The BUYER's representatives and/or the Supervisor shall be on board the VESSEL to witness the Trial Run, and to check upon the performance of the VESSEL during the same. Failure of the BUYER's representatives to be present at the Trial Run of the VESSEL, after due notice to the BUYER and the Supervisor as provided above, shall had the effect to extend the date for delivery of the VESSEL by the period caused by such failure to attend. However, if the Trial Run is delayed more than seven (7) days by reason of the failure of the BUYER's representatives to be present after receipt of due notice as provided above, then in such event, the BUYER shall be deemed to have waived its right to have its representatives on board the VESSEL during the Trial Run The SELLER shall assist the BUYER on necessary visa for the BUYER's representatives to enter into China. However, should the nationalities and other personal particulars of the BUYER's representatives be not acceptable to the SELLER in accordance with its best understanding of the relevant rules, regulations and/or Laws of the People's Republic of China then prevailing, then the BUYER shall, on the SELLER's telefax or e-mail demand, effect replacement of all or any of them immediately. Otherwise the Delivery Date as stipulated in Article VII hereof shall be extended by the delays so caused by the BUYER. In the event that the Trial Run is postponed because of unfavourable weather conditions, such delay shall be regarded as a permissible delay, as specified in Article VIII hereof.
ARTICLE VII DELIVERY
1 TIME AND PLACE
The VESSEL shall be delivered safely afloat by the SELLER to the BUYER at SELLER'S yard, in accordance with the Specifications and with all Classification and Statutory Certificates in accordance with the Specifications and after completion of Trial Run (or, as the case may be, re-Trial or re-Trials) and acceptance by the BUYER in accordance with the provisions of Article VI hereof on or before August 31st 2015, in the event of delays in the construction of the VESSEL or any performance required under this Contract due to causes which under the terms of the Contract permit extension of the time for delivery, the aforementioned time for delivery of the VESSEL shall be extended accordingly.
The aforementioned date or such later date to which delivery is extended pursuant to the terms of this Contract is hereinafter called the 'Contract Delivery Date'.
ARTICLE VIII DELAYS & EXTENSION OF TIME FOR DELIVERY
1 CAUSE OF DELAY
If, at any time before actual delivery, either the construction of the VESSEL, or any performance required hereunder as a prerequisite of delivery of the VESSEL, is delayed due to war, blockade, revolution, insurrection, mobilization, civil commotions, riots, strikes, sabotage, lockouts, local temperature higher than 35 degree centigrade and lower than minus 15 degree centigrade, local continuous raining lasts 5 days or more, Acts of God or the public enemy, terrorism, plague or other epidemics, quarantines, prolonged failure or restriction of electric current from an outside source, freight embargoes, if any, earthquakes, tidal waves, typhoons, hurricanes, storms or other causes beyond the control of the SELLER or of its sub-contractors, as the case may be, or by force majeure of any description, whether of the nature indicated by the forgoing or not, or by destruction of the SELLER or works of the SELLER or its sub-contractors, or of the VESSEL or any part thereof, by fire, flood, or other causes beyond the control of the SELLER or its sub-contractors as the case may be, or due to the bankruptcy of the equipment and/or material supplier or suppliers, or due to the delay caused by acts of God in the supply of parts essential to the construction of the VESSEL, then, in the event of delay due to the happening of any of the aforementioned contingencies, the SELLER shall not be liable for such delay and the time for delivery of the VESSEL under this Contract shall be extended without any reduction in the CONTRACT PRICE for a period of time which shall not exceed the total accumulated time of all such delays subject nevertheless to the BUYER's right of cancellation under Paragraph 3 of this Article and subject however to all relevant provisions of this Contract which authorize and permit extension of the time of delivery of the VESSEL.
2 NOTICE OF DELAY
Within seven (7) business days from the date of commencement of any delay on account of which the SELLER claims that it is entitled under this Contract to an extension of the time for delivery of the VESSEL, the SELLER shall advise the BUYER by telefax or e-mail confirmed in writing, of the date such delay commenced, and the reasons therefore.
Likewise within seven (7) business days after such delay ends, the SELLER shall advise the BUYER in writing or by telefax or e-mail confirmed in writing, of the date such delay ended, and also shall specify the maximum period of the time by which the date for delivery of the VESSEL is extended by reason of such delay. In case of failure of the BUYER to object the SELLER's notification of any claim for extension of the Contract Delivery Date within seven (7) business days after receipt by the BUYER of such notification, the time of delivery will be automatically extended according to the SELLER's notification.
Failure of the SELLER to give the BUYER notice of delay as provided in this Article except in the case of entire power failure or cut-off of the communication facilities shall preclude the BUILDER from claiming extension of the Delivery Date by reason of such failure.
3 RIGHT TO CANCEL FOR EXCESSIVE DELAY
If the total accumulated time of all non-permissible delays on account of the causes specified in Paragraph 1 of the Article III aggregate more than One Hundred and Fifty (150) days, or if the total accumulated time of all permissible days on account of the causes specified in Paragraph 1 of this Article and all non-permissible delays as described in Paragraph 1 of Article III aggregate to One Hundred and Eighty (180) days, in any circumstances, excluding delays due to arbitration as provided for in Article XIII hereof or due to default in performance by the BUYER, or due to delays in delivery of the BUYER's supplied items, and excluding delays due to causes which, under Article V, VI, XI and XII hereof, permit extension or postponement of the time for delivery of the VESSEL, then in such event, the BUYER may in accordance with the provisions set out herein cancel this Contract by serving on the SELLER telefaxed or e-mailed notice of cancellation in writing and the provisions of Article X of this Contract shall apply.
4 DEFINITION OF PERMISSIBLE DELAY
Delays on account of such causes as provided for in Paragraph 1 of this Article excluding any other extensions of a nature which under the terms of this Contract permit postponement of the Contract Delivery Date, shall be understood to be (and are herein referred to as) permissible delays, and are to be distinguished from non-permissible delays on account of which the CONTRACT PRICE of the VESSEL is subject to adjustment as provided for in Article III hereof.
ARTICLE X CANCELLATION, REJECTION AND RESCISSION BY THE BUYER
1
The BUYER shall be entitled to rescind or terminate this Contract upon occurrence of any following event:
(a) there occurs excessive delays in delivery of the VESSEL entitling the BUYER to rescind the Contract as specifically permitted in Paragraph 1(c) of Article III or Paragraph 3 of Article VIII hereof
ARTICLE XI BUYER'S AND SELLER'S DEFAULT
1 DEFINITION OF DEFAULT
The BUYER shall be deemed in default of its obligation under the Contract if any of the following events occurs:
(a) The BUYER fails to pay any of the First, Second, Third and/or Fourth Installment to the SELLER within three (3) Banking Days after the expiry of the payment period (5 Banking Days) for such installment under the provisions of Article II hereof, or
(b) The BUYER fails to pay the final installment to the SELLER in accordance with Paragraph 2(e) and 4a(ii) of Article II hereof; or
(c) The BUYER fails to take delivery of the VESSEL, when the VESSEL is duly tendered for delivery by the SELLER under the provisions of Article VII hereof within fourteen business days from the tendered date and without any justifiable reason thereof under this Contract; or
(d) The BUYER becomes bankrupt.
(Such bankruptcy shall be informed by the BUYER to the SELLER in written form within five working days after the BUYER becomes bankrupt.)
2 NOTICE OF DEFAULT
If the BUYER is in default of payment or in performance of its obligations as provided hereinabove, the SELLER shall notify the BUYER to that effect by telefax or e-mail after the date of occurrence of the default as per Paragraph 1 of this Article and the BUYER shall forthwith acknowledge by telefax or e-mail to the SELLER that such notification has been received. In case the BUYER does not give the aforesaid telefax or e-mail acknowledgment to the SELLER within five (5) business days it shall be deemed that such notification has been duly received by the BUYER.
4 DEFAULT BEFORE DELIVERY OF THE VESSEL
(a) If any default by the BUYER occurs as defined in Paragraph 1 of this Article, the Delivery Date shall, at the SELLER's option, be postponed for a period of continuance of such default by the BUYER.
ARTICLE XIII DISPUTES AND ARBITRATION
6 ALTERATION OF DELIVERY TIME
In the event of reference to arbitration of any dispute arising out of matters occurring prior to delivery of the VESSEL, the BUYER shall not be entitled to extend the Delivery Date as defined in Article VII hereof. The arbitrator(s) or the Arbitration Board or the Expert, as appropriate, however, shall be empowered to decide as to what extent if any the Delivery Date is altered as a result of the arbitration proceedings, if at all. And the SELLER shall be permitted to extend the Contract Delivery Date in accordance with the arbitration award and the award shall include a finding as to what extent the SELLER shall be permitted to extend the Contract Delivery Date.