BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Severfield (UK) Ltd v Duro Felguera UK Ltd (No. 2) [2017] EWHC 3066 (TCC) (29 November 2017) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2017/3066.html Cite as: [2017] EWHC 3066 (TCC), 175 Con LR 266 |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT
Rolls Building, Fetter Lane, London, EC4A 1NL |
||
B e f o r e :
____________________
SEVERFIELD (UK) LIMITED |
Claimant |
|
- and - |
||
DURO FELGUERA UK LIMITED |
Defendant |
____________________
The Defendant did not appear and was not represented
Hearing date: 14 November 2017
____________________
Crown Copyright ©
The Hon. Mr Justice Coulson :
1. INTRODUCTION
2. THE FACTUAL CONTEXT
"13. COMPLETION DATES
13.1 The CONTRACTOR shall comply with the following dates fulfilling with all the conditions established in this Contract
|
STEEL STRUCTURE END OF ERECTION DATE |
|
BUILDING |
Unit 1 |
Unit 2 |
TURBINE HALL |
01/02/2014 |
01/03/2014 |
ELECTRICAL MODULES |
10/03/2014 |
10/04/2014 |
FEED WATER |
28/02/2014 |
03/03/2014 |
OTC |
11/01/2014 |
15/02/2014 |
HRSG ENCLOSURE |
17/07/2014 |
16/08/2014 |
PLATFORMS |
09/04/2014 |
08/05/2014 |
"
"With reference to the revised delivery schedule noted below we confirm that we can achieve these dates subject to the following parameters been achieved by the Design/Construction Team;
1. All Design Information [Full Construction Drawings with Design Loads] issued to us by 19th August for the following elements -
- Turbine Building 1 [Connection details for Internal Platforms to Main Frame also required to insure details are incorporated into Main Frame]
- Electrical Module 1
- OTC 1
2. All Design information [Full Construction Drawings with Design Loads] issued to us by 2nd September for the following elements -
- Turbine Building 2 [Connection details as noted in item 1 above also required]
- Electrical Module 2
- OTC 2
- Feedwater 1
- Platforms l & 2.
3. All Design information [Full Construction Drawings with Design Loads] issued to us by 9th September for the following elements -
- Feedwater 2
4. All Design information [Full Construction Drawings with Design Loads] issued to us by 6th January 2014 for the following elements -
- HRSG Enclosure l
- HRSG Enclosure 2"
3. CLAIM HISTORY
4. OVERVIEW OF THE CLAIMANT'S CLAIMS
Item |
SUK Claim Value
£ |
DF Value
£ |
Delta
£ |
|
A Nash Assessment Primary position
£ |
A Nash Assessment Secondary position (high)
£ |
A Nash Assessment Secondary position (low)
|
Comments |
Measured Works - including night shift sum |
7,686,067.12 |
7,675,113.12 |
10,954.00 |
|
7,732,734.70 |
7,732,734.70 |
7,732,734.70 |
|
EHS Managers |
393,364.00 |
28,600.00 |
364,764.00 |
|
114,741.00 |
114,741.00 |
114,741.00 |
|
Sub-total |
8,079,431.12 |
7,703,713.12 |
375,718.00 |
|
7,847,475.70 |
7,847,475.70 |
7,847,475.70 |
|
Lump Sum Discount |
-219,446.32 |
-219,446.32 |
0.00 |
|
-219,446.32 |
-219,446.32 |
-219,446.32 |
|
Variation Account Agreed |
830,220.45 |
830,220.45 |
0.00 |
|
830,220.45 |
830,220.45 |
830,220.45 |
|
Variation Account Unagreed Delta under £10k |
247,940.51 |
178,476.68 |
69,463.83 |
|
247,940.51 |
247,940.51 |
247,940.51 |
Included as SUK Claim Value |
Variation Account Unagreed Delta £10k-£20k |
627,989.80 |
502,672.16 |
125,317.64 |
|
627,989.80 |
627,989.80 |
627,989.80 |
Included as SUK Claim Value |
Variation Account Unagreed Top 12 |
2,933,233.15 |
610,949.66 |
2,322,283.49 |
|
2,333,070.01 |
2,194,745.95 |
2,032,804.05 |
Secondary position (low) only applies to VO 117 |
VO G - Loss and Expense - on site prelims |
1,010,386.44 |
nil |
1,010,386.44 |
|
209,464.79 |
209,464.79 |
209,464.79 |
|
VO G - Loss and Expense - off site prelims |
inc above |
nil |
nil |
|
147,138.69 |
147,138.69 |
147,138.69 |
|
Parking Charges |
0.00 |
-600.00 |
600.00 |
|
0.00 |
0.00 |
0.00 |
|
DF Back Charges |
0.00 |
-214,466.36 |
-214,466.36 |
|
0.00 |
0.00 |
0.00 |
|
Gross Contract Price |
13,509,755.15 |
9,391,519.39 |
4,118,235.76 |
|
12,023,853.63 |
11,885,529.57 |
11,723,587.67 |
|
Paid to date |
8,999,204.76 |
8,999,204.76 |
0.00 |
|
8,999,204.76 |
8,999,204.76 |
8,999,204.76 |
|
Net Amount Due |
4,510,550.39 |
392,314.63 |
4,118,235.76 |
|
3,024,648.87 |
2,886,324.81 |
2,724,382.91 |
|
Liquidated Damages |
0.00 |
960,000.00 |
960,000.00 |
|
Not assessed |
Not assessed |
Not assessed |
|
Final Amount Due |
4,510,550.39 |
-567,685.37 |
5,078,235.76 |
|
3,024,648.87 |
2,886,324.81 |
2,724,382.91 |
|
5. MEASURED WORKS
6. EHS MANAGERS
7. LUMP SUM DISCOUNT
8. VARIATIONS WHERE THE DISPUTE IS LESS THAN £10K
9. VARIATIONS WHERE THE DISPUTE IS BETWEEN £10K AND £20K
10. VARIATIONS: TOP 12
11. TIME/DELAY
"The CONTRACTOR may only request changes to the Completion Dates when the following circumstances occur: (i) a cause of Force Majeure that affects any Completion Dates or (ii) suspension of the Contract by order of the BUYER or (iii) any act of prevention or default of the BUYER, or (iv) deferment of the giving of possession of the Site or any part thereof as needed to perform the Scope and provided that CONTRACTOR has fulfilled all the conditions required for such access, or (v) modifications to the Scope pursuant to clause 12, or (vi) any strike at the Site, other than strikes of CONTRACTOR's personnel and/or subcontractors, that directly impacts performance of CONTRACTOR's Scope or(vii) in case of CONTRACTOR's suspension In accordance to clause 15.6 or (viii) in the other cases expressly established in this Contract."
Building/Unit |
Contract Completion Date |
Actual Steel structure Completion Date |
Delay (Calendar days) |
Turbine Hall 11 |
01/02/14 |
07/04/14 |
65 |
Turbine Hall 21 |
01/03/14 |
30/04/14 |
60 |
OTC 11 |
11/01/14 |
07/08/14 |
208 |
OTC 21 |
15/02/14 |
15/09/14 |
212 |
Feedwater 11 |
28/02/14 |
05/09/14 |
189 |
Feedwater 21 |
03/03/14 |
12/11/14 |
254 |
Electrical Module 11 |
10/03/14 |
01/10/14 |
205 |
Electrical Module 21 |
10/04/14 |
01/10/14 |
174 |
HRSG 11 |
17/07/14 |
07/07/15 |
355 |
HRSG 21 |
16/08/14 |
17/06/15 |
305 |
Turbine Hall Platforms 11 |
09/04/14 |
05/02/15 |
302 |
Turbine Hall Platforms 21 |
08/05/14 |
25/02/15 |
293 |
"In my opinion, SUK could not reasonably have completed the steel structure works in the Units any earlier than the identified Complete Steel Structure Erection date in the table below [the table set out at paragraph 46 above] taking into account all of the circumstances that it encountered including the access issues caused by DF, the increased scope, the change circumstances in respect of the site logistics and the variation works required by DF."
"…so peculiar, so unexpected, and so different from what any person reckoned or calculated upon, that it is not within the contract at all; then, it appears to me, one of two courses might have been open to him; he might have said: I entirely refuse to go on with the contract…or he might have said, I will go on with this, but this is not the kind of extra work contemplated by the contract, and if I do it, I must be paid a quantum meruit for it."
12. THE FINANCIAL CONSEQUENCES OF DELAY
(a) There was 37 days delay between 31 December 2013 and 25 March 2014;
(b) That delay had increased to 128 days by 30 July 2014;
(c) That delay had increased to 244 days by 17 December 2014;
(d) That delay had increased to 272 days by 24 March 2015;
(e) That delay had increased to 325 days by 7 July 2015.
13. CONTRA CHARGES
14. SUMMARY OF SUMS DUE
Item |
Amount |
Measured Works |
£7,732,734.70 |
EHS Managers |
£114,741 |
Sub-Total |
£7,847,475.70 |
Less Lump Sum Discount |
-£219,446.32 |
Variation Account Agreed |
£830,220.45 |
Variation Account Unagreed (disputes under £10k) |
£198,352.41 |
Variation Account Unagreed (dispute between £10k-£20k) |
£565,331 |
Variation Account
Unagreed |
£2,194,745.95 |
VO G On Site Preliminaries |
£209,464.79 |
VO G Loss Expense - Off Site Preliminaries |
£147,138.69 |
Gross Sum Due |
£11,773,282.67 |
Agreed Sum Paid To Date |
£8,999,204.76 |
Net Amount Due |
£2,774,077.91 |
Parking charges |
nil |
DF Back Charges |
nil |
Liquidated Damages |
nil |
Sum Due |
£2,774,077.91 |
15. THE FINANCIAL POSITION AS AT 31 DECEMBER 2014
16. CONCLUSIONS AND INTEREST
Note 1 Which were added to the contract and signed off after this exchange of emails. [Back] Note 2 Mr Williams was the claimant’s expert programmer, and his report was dated 20 October 2017. [Back]